FEDERAL MINE SAFETY AND HEALTH REVIEW COMMISSION

721 19th Street, Suite 443

Denver, CO 80202-2536

303-844-5267/ FAX 303-844-5268

 

May 13, 2013

SECRETARY OF LABOR,   
MINE SAFETY AND HEALTH    
ADMINISTRATION (MSHA), 
Petitioner,

v.

DINO TRUJILLO, employed by Mountain
Cement Company, 
Respondent.


:
:
:
:
:
:
:
:
:
:

CIVIL PENALTY PROCEEDING

Docket No. WEST 2013-389-M
A.C. No. 48-00007-310682 A

 

Mountain Cement Company



 

 

ORDER DENYING RESPONDENT’S MOTION TO DISMISS

 

Before:                        Judge Manning

 

This case is before me under section 110(c) of the Federal Mine Safety and Health Act of 1977, 30 U.S.C. § 820(c) (the “Mine Act”).  Dino Trujillo (“Respondent”), who was a maintenance supervisor for Mountain Cement Company (“MCC”), contested the proposed penalty filed by the Secretary of Labor.  Respondent filed a Motion to Dismiss due to the Secretary’s delay in proposing a penalty for the alleged violation and the Secretary filed a reply in opposition to the motion.  For the reasons set forth below, I deny Respondent’s motion to dismiss the proceeding.

 

            On February 11, 2010, MSHA issued 104(d)(1) Order No. 6447118 to MCC alleging a violation of section 56.14107(a).  Section 56.14107(a) mandates that moving machine parts must be guarded to prevent miners from contacting those parts.  30 C.F.R. § 56.14107(a).  Order No. 6447118 states, in part, that Respondent removed the guard for a shuttle belt.  (Ex. R-A).

 

On April 5, 2011, MSHA informed Respondent that it intended to file a 110(c) proceeding against him as an agent of MCC.  MSHA conducted a 110(c) conference call with Respondent on May 6, 2011, to discuss the issues.  On June 6, 2011, I was informed that the 110(c) investigation had been forwarded to MSHA headquarters for a decision.[1]  On January 3, 2013, MSHA issued its proposed penalty under section 110(c) to Respondent for $3,500.00.  MSHA alleges that Respondent knowingly authorized, ordered, or carried out MCC’s violation of section 56.14107(a).  Respondent contested the penalty on January 17, 2013.  The Secretary filed his petition for assessment of civil penalty on March 1, 2013, and Respondent filed a Motion to Dismiss on March 28, 2013.

 

Respondent argues that this proceeding should be dismissed because the Secretary failed to show adequate cause for an unreasonable delay that prejudiced Respondent.  Section 554(b) of the Administrative Procedure Act requires that the Secretary file a petition for penalty in a timely fashion and section 105(a) of the Mine Act requires that the length of time to do so be reasonable.  Numerous Commission judges have applied the law developed under section 105(a) to alleged 110(c) violations. The Secretary did not file his petition in a reasonable or timely fashion and he did not show adequate cause for his delay.  The Secretary’s delay also prejudiced Respondent, which means that the proceeding should be dismissed even if the Secretary had shown adequate cause.  The Secretary’s delay was 1,057 days long, which fundamentally causes prejudice because it violates Respondent’s due process and causes the memory of witnesses to fade.  Respondent also argues that public policy favors dismissal of this proceeding.

 

            The Secretary argues that the Secretary’s Petition should not be dismissed because it was not filed late, was not filed in unreasonable time, and did not prejudice Respondent.  The Secretary also argues that Congress did not intend to authorize the Commission to dismiss penalties as the result of procedural delays.  The Secretary filed his petition within 45 days of the notice of contest and within five years of the issuance of the underlying order.

 

I find that the “reasonable time” standard in section 105(a) applies to section 110(c).[2]  Section 105(a) of the Mine Act states that the Secretary “shall, within a reasonable time after the termination of such inspection or investigation notify the operator by certified mail of the civil penalty proposed to be assessed under section 110(a).”  30 U.S.C. § 815(a) (emphasis added).  Neither party argues that 105(a) should not apply to 110(c) and Commission administrative law judges have consistently agreed that it should.  Christopher Brinson, Gerald Hastings, Ronald Colson, 35 FMSHRC __, slip op. at 4, SE 12-340M (May 7, 2013); Dyno Nobel East-Central Region, 35 FMSHRC __, slip op. at 1, LAKE 11-13 (Jan. 2, 2013) (ALJ); Stephen Reasor, 34 FMSHRC 920, 924 (Apr. 2012) (ALJ); Doyal Morgan, 20 FMSHRC 40 (Jan. 1998) (ALJ).

 

Application of the 105(a) reasonable time requirement requires evaluating and balancing the competing interests of respondents and the Secretary.  Procedural fairness is a substantial concern under the Mine Act.  Salt Lake County Road Department, 3 FMSHRC 1714, 1716 (July 1981).  The expeditious resolution of penalty cases is also a public interest.  Buck Creek Coal, 17 FMSHRC 500, 503 (Apr. 1995); Scotia Coal Mining Co., 2 FMSHRC 633, 635 (Mar. 1980).  The overriding purpose of the Mine Act, however, is addressing the public interest to protect miners by enforcing the Secretary’s safety and health standards.  When an important public interest is at issue, “the great principle of public policy” dictates that procedural failures by an agency do not automatically void subsequent agency action.   Brock v. Pierce County, 476 U.S. 253, 260 (1986).  It is, however, a “basic principle of administrative law that substantive agency proceedings” may be overturned upon a showing prejudice.  Salt Lake, 3 FMSHRC at 1716.  Without a respondent’s showing of prejudice, it is “inappropriate” to dismiss a citation or order based upon the Secretary’s delay.  Twentymile Coal Co., 411 F.3d 256, 262 (2005).

 

            I deny Respondent’s Motion to Dismiss because Respondent failed to show prejudice.  Effectuating the substantive goals of the Mine Act to protect the health and safety of miners is the primary purpose of the Mine Act, which is why the operator must show prejudice before the dismissal of its case.  Respondent cites the length of the delay as the cause of prejudice, stating that “the delay alone is fundamentally unfair” and the memory of defense witnesses will have faded.  (R. Mot. at 11).  I hold, however, that Respondent’s showing of prejudice must be “real or substantial” and “mere allegations of potential prejudice or inherent prejudice should be rejected.” Long Branch Energy, 34 FMSHRC 1984, 1991-93 (Aug. 2012).  Respondent claims that prejudice is inevitable due to the length of the delay.  Respondent does not cite specific instances of prejudice or difficulties of locating evidence or witnesses.  Respondent shows no real or substantial prejudice and does not provide specific facts in an attempt to show prejudice. 

 

I disagree with Respondent’s argument that the Commission’s test in Long Branch Energy controls in this instance.  There is no specific procedural rule that governs 110(c) and the current case does not involve a violation of Procedural Rule 28(a). [3]  Although the Secretary must act within reasonable time, no period of delay shorter than the five year limitation cited by the Secretary is per se unreasonable.[4]  See Gabelli v. S.E.C., 133 S.Ct. 1216, 1219 (U.S. 2013).  Considering that the Mine Act’s main concern is mine safety, I do not believe that the initial burden should be placed upon the Secretary in this instance because there was no violation of the Commission’s procedural rules.  Respondent, therefore, must show that it was actually and meaningfully prejudiced by the Secretary’s delay in filing the penalty proposal.   See Twentymile Coal Co., 411 F.3d at 262.  The burden is also upon Respondent because he is the moving party.  I hold that the Secretary’s petition for penalty should not be dismissed at this stage of the proceeding because there was no showing of actual prejudice by Respondent.[5]

 

            Respondent’s Motion to Dismiss this proceeding his hereby DENIED and he is ordered to file his answer to the Secretary’s petition for assessment of civil penalty within 30 days of the date of this order.

 

           

 

 

 

 

                                                                                    /s/ Richard W. Manning       

                                                                                    Richard W. Manning

                                                                                    Administrative Law Judge

 

 

Distribution:

 

Jason Grover, Esq., Office of the Solicitor, U.S. Department of Labor, 1100 Wilson Blvd., 22nd Floor West, Arlington, VA 22209-2247

 

Jason Nutzman, Esq., Dinsmore & Shohl, LLP, Huntington Square, 900 Lee Street, Suite 600, Charleston, WV 25301

 

RWM/bjr



[1]  This information was provided in response to an inquiry I made in the penalty case brought against MCC as to the status of the section 110(c) investigation.

[2] Respondent argues that the proceeding should be dismissed because Secretary violated the “timely” requirement of the Administrative Procedure Act. 5 U.S.C § 554(b).  For the purposes of 110(c) proceedings, timely filing is defined by section 105(a) of the Mine Act.  The timely requirement in section 554(b), therefore, is met by the Secretary if he complies with section 105(a) of the Mine Act.

[3] Long Branch concerns the application of 105(a) to 110(a) and a respondent’s motion to dismiss due to the procedural delay of the Secretary.  Section 110(a) and section 110(c) violations are subject to the Commission’s Procedural Rule at 29 C.F.R § 2700.28.  Long Branch addresses a violation of Procedural Rule 28(a), which states “[w]ithin 45 days of receipt of a timely contest of a proposed penalty assessment, the Secretary shall file with the Commission a petition for assessment of penalty.” 29 C.F.R § 2700.28(a).  The Secretary violates Rule 28(a) if he files his petition for assessment of civil penalty more than 45 days after the respondent contests the penalty proposal.  The initial burden of proof, therefore, falls upon the Secretary to show adequate cause for the delay if he violates Rule 28(a).  34 FMSHRC at 1992.  Cases under the Long Branch test can be decided “solely on the adequacy of the cause provided by the Secretary[,]” without a respondent’s showing of prejudice.  Id.  It is important to recognize that the present case involves the period of time between the “termination of [the] inspection or investigation” and Respondent’s notification of the proposed penalty.  The Secretary timely filed his petition for assessment of civil penalty 43 days after Respondent contested the penalty proposal.  Thus, Rule 28(a) was not violated by the Secretary.

 

[4] Which time period should be considered in the “reasonable time” analysis is not controlling under the facts in this case.  I hold, however, that the relevant time period commenced at the conclusion of MSHA’s section 110(c) investigation.  See Twentymile Coal Co., 411 F.3d at 261-62.

 

[5]  Commission Judge Jeffrey Tureck, in a recent order involving similar issues, acknowledged that Long Branch did not concern the period of time to notify a respondent of the penalty proposal.  Christopher Brinson et al. 35 FMSHRC ____, Slip Op. at 6, No. SE 2012-340-M  (May 7, 2013).  He denied the respondents’ motions to dismiss several section 110(c) proceedings because there was no substantial delay between the time the Secretary concluded his special investigation and when he proposed penalties under section 110(c).  Id. at 5.  Judge Tureck went on to apply the principles of Long Branch assuming arguendo that the relevant time period commenced with the issuance of the citation and he applied the two part test set forth in that decision and in Salt Lake County.  He applied those decisions because “they concern the length of time it is reasonable to permit the Secretary to delay an action and the legal standard to apply in making this analysis. . . .”  Id. at 6.  In that respect, Judge Tureck’ s analysis of the legal issues differs from mine.

 

Furthermore, I find that the Secretary presented “adequate cause” for his delay.  The Secretary fulfilled his burden in Long Brach because he proffered an adequate cause or non-frivolous explanation for his delay:  the increased workload of MSHA during the relevant time period, which delayed the issuance of 110(c) penalties.  Id. at 1992.  Under my analysis such a showing was not necessary, however.