FEDERAL MINE SAFETY AND HEALTH REVIEW COMMISSION

OFFICE OF ADMINISTRATIVE LAW JUDGES

7 PARKWAY CENTER, SUITE 290

875 GREENTREE ROAD

PITTSBURGH, PA 15220

TELEPHONE: (412) 920-7240

FACSIMILE: (412) 928-8689

June 5, 2013

DOMINION COAL CORPORATION, 
Contestant, 

v.

SECRETARY OF LABOR,   
MINE SAFETY AND HEALTH    
ADMINISTRATION (MSHA),  
Respondent 


SECRETARY OF LABOR
MINE SAFETY AND HEALTH 
ADMINISTRATION (MSHA), 
Petitioner 

v.

DOMINION COAL CORPORATION,
Respondent 

:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:

CONTEST PROCEEDINGS

Docket No. VA 2011-334-R
Order No. 8185281; 03/02/2011 

Docket No. VA 2011-549-R
Order No. 8173479; 06/27/2011

Mine: No. 36
Mine ID: 44-06759

CIVIL PENALTY PROCEEDING

Docket No. VA 2012-126
A.C. No. 44-06759-272556-01


Mine: No. 36

 

 

DECISION

 

Appearances:              Emily K. Hargrove, Esq., & Daniel Povich, Esq., U.S. Department of Labor, Office of the Solicitor, Arlington, VA for the Secretary

 

                                    Scott Wickline, Esq., Hardy Pence, PLLC, Charleston, WV for Respondent

 

Before:                        Judge Steele

 

STATEMENT OF THE CASE

 

This civil penalty proceeding is conducted pursuant to the Federal Mine Safety and Health Act of 1977, 30 U.S.C. § 801 et seq. (2000) (the “Mine Act” or “Act”).  This matter concerns Order Nos. 8185281 and 8173479 and Citation No. 8189545.  However, at hearing Dominion Coal Corporation (“Dominion” or “Respondent”) asserted that it would no longer contest Citation No. 8189545.  (Transcript at 7).[1]  Order No. 8185281 was issued under Section 104(d)(1) for failure to comply with 30 C.F.R. §50.10(d).  Order No. 8173479 was issued under Section 104(d)(2) for failure to comply with 30 U.S.C. §876(b).  Both Orders were served on The Secretary seeks civil penalties in the amount of $30,000.00.  A hearing was held in Grundy, VA on December 12, 2012 where the parties presented testimony and documentary evidence.  After the hearing, the parties submitted Post Hearing Briefs.

 

STIPULATIONS

 

            The parties have stipulated to the following:

 

1.     Dominion was an “operator” as defined in Section 3(d) of the Mine Act, 30 U.S.C. §803(d), at Mine #36.

 

2.     Respondent’s Mine #36 is a “mine” as that term is defined in Section 3(h) of the Mine Act, 30 U.S.C. §803(h).

 

3.     Operations at Respondent’s Mine #36, where the Orders at issue in this proceeding were issued, are subject to the jurisdiction of the Mine Act.

 

4.     This proceeding is subject to the jurisdiction of the Federal Mine Safety and Health Review Commission and its designed Administrative Law Judges pursuant to §§105 and 113 of the Mine Act, 30 U.S.C. §§ 815 and 823.

5.     The total proposed penalty for the Orders in this proceeding will not affect Respondent’s ability to continue in business.

 

6.     The Orders at issue in this proceeding were issued by an authorized representative of the Secretary.

 

ORDER NO. 8173479

 

1. Contents of the Order

 

            On June 27, 2011 at 10:20 a.m., Inspector Dennis Shortt (“Shortt”) issued to Respondent Order No. 8173479.  Simmons found:

 

The approved Emergency Response Plan for this mine was not being followed.  A communications failure occurred on 6/24/2011 at approximately 6:00 pm.  Wireless communication capability was lost from T-1 belt drive up to an including the T section.  The plan states that the operator will notify MSHA of a communication system failure that extends longer than 12 consecutive hours.  The operators has not reported the failure

 

Government’s Exhibit 1 (Hereinafter GX-1).  Shortt noted that the gravity of this violation was “No Likelihood,” “No Lost Workdays,” and would affect ten persons.  Id.  He further marked that Respondent exhibited “High” negligence with respect to this violation.  Id.  Shortt noted that the respondent terminated the cited condition on June 27, 2011 by reporting the failure.  Id. 

 

            On June 27, 2011 at 1:37 p.m., Shortt issued a modification of the order changing the “Condition or Practice” section to include the following:

 

The wording in this violation should also state:  Management engaged in aggravated conduct constituting more than ordinary negligence in that the operator failed to comply with the Approved Emergency Response Plan.  This violation is an unwarrantable failure to comply with a mandatory standard.

 

Id.

2. Legal Standards

 

Order No. 8173479 was issued under Section 104(d)(2) of the Mine Act.  That provision provides the following:

 

If a withdrawal order with respect to any area in a coal or other mine has been issued pursuant to paragraph (1), a withdrawal order shall promptly be issued by an authorized representative of the Secretary who finds upon any subsequent inspection the existence in such mine of violations similar to those that resulted in the issuance of the withdrawal order under paragraph (1) until such time as an inspection of such mine discloses no similar violations. Following an inspection of such mine which discloses no similar violations, the provisions of paragraph (1) shall again be applicable to that mine.

30 U.S.C. § 814(d)(2).

 

The Order deals with an alleged violation of Section 316(b) of the Mine Act (titled “Communication facilities; locations and emergency response plans”).  That section provides, in pertinent part, the following:

 

Accident preparedness and response

(1) In general - Each underground coal mine operator shall carry out on a continuing basis a program to improve accident preparedness and response at each mine.

(2) Response and preparedness plan

(A) In general - Not later than 60 days after June 15, 2006, each underground coal mine operator shall develop and adopt a written accident response plan that complies with this subsection with respect to each mine of the operator, and periodically update such plans to reflect changes in operations in the mine, advances in technology, or other relevant considerations. Each such operator shall make the accident response plan available to the miners and the miners' representatives…

(E) Plan content-general requirements - To be approved under subparagraph (C), an accident response plan shall include the following:

(i) Post-accident communications - The plan shall provide for a redundant means of communication with the surface for persons underground, such as secondary telephone or equivalent two-way communication…

(F) Plan content-specific requirements…

(ii) Post accident communications - Not later than 3 years after June 15, 2006, a plan shall, to be approved, provide for post accident communication between underground and surface personnel via a wireless two-way medium, and provide for an electronic tracking system permitting surface personnel to determine the location of any persons trapped underground or set forth within the plan the reasons such provisions can not be adopted. Where such plan sets forth the reasons such provisions can not be adopted, the plan shall also set forth the operator's alternative means of compliance. Such alternative shall approximate, as closely as possible, the degree of functional utility and safety protection provided by the wireless two-way medium and tracking system referred to in this subpart.

30 U.S.C. §876(b). 

 

3. Summary of Testimony

 

a. Testimony of Dennis Allen Shortt, Jr.:

 

Shortt started in the coal industry in 1994.  (Tr. 15).  He attended college and worked in the industry through a Co-Op program.  (Tr. 15).  After college he worked in the mines as a maintenance foreman until 2003.  (Tr. 15).  He was out of the industry until 2005 when he went to MSHA.  (Tr. 15).  He has worked for MSHA for seven years.  (Tr. 14-15). 

 

Shortt is an electrical specialist for MSHA.  (Tr. 14).  In that capacity, he checks the main power distribution system throughout the mine, starting with the substations.  (Tr. 16).  He also checks ground faults, cables, pumps, gas, fire suppression systems, and seal marking systems.  (Tr. 16).  In addition, he reviews emergency response plans (“ERP”).  (Tr. 16).  For an electrical specialist, the ERP mostly consists of the tracking and communication system.  (Tr. 16). [2]  

 

Shortt went to #36 Mine with Gary Perkins, another electrical specialist, to terminate citations issued by Perkins.  (Tr. 17-18).  That morning he reviewed the mine file and those citations.  (Tr. 18).  When he arrived at the mine, he found out that the carbon monoxide system was down.  (Tr. 18).  He waited to see if they would fix the CO system so he could proceed underground and terminate the citation there, but they did not.  (Tr. 18-19). 

 

While he waited, Shortt learned that the communication system was down on the T Section.  (Tr. 19). He believed he learned this when he overheard a conversation on the mine page pole (a hard-line communication system).  (Tr. 19).  Two inspectors, Frankie Sullivan and Wade Taylor, were going to the section and when they arrived at T-1 there was no wireless or hard-line communication.  (Tr. 19, 48).  The communications were down from T-1 belt drive all the way up to and including T Section.  (Tr. 20, 48). 

 

Shortt spoke with Dan Vance (“Vance”), the chief electrician.  (Tr. 19-20).  Vance was aware and said the wireless system went down the previous Friday.  (Tr. 19-20).  Vance said there was a high-voltage problem: a miner struck a cable and caused an arc, spark, or surge in the system.  (Tr. 20).  This caused the power supplies to go out on the wireless system and he had ordered power supplies.  (Tr. 20).  Vance showed Shortt the purchase order where he had ordered power supply replacements.  (Tr. 20).

 

Vance stated that he did not know that he was required to report the failure.  (Tr. 20, 46, 49).  He offered no other reasons for the failure to report.  (Tr. 21).  He was not trying to hide anything.  (Tr. 44-45).  However, Vance did report the condition before Shortt learned about it from other sources.  (Tr. 45).  Shortt did not read anything negative into that fact.  (Tr. 45). 

 

Vance admitted to Shortt that he had attended a class taught by Jason Lane (“Lane”), an electrical supervisor with MSHA a month earlier.  (Tr. 20-21, 47-49).  The class was offered because there was confusion about the ERP requirements.  (Tr. 21).  Respondent voluntarily agreed to have its employees participate and Shortt believes that is a good thing.  (Tr. 33).  Shortt reviewed Respondent’s ERP that was apparently in effect when the Order was issued (GX-2).  (Tr. 21-22).  The maintenance requirements on page 5 state, “[t]he operator shall [sic] the MSHA Hotline of a communication system failure that extends longer than 12 consecutive hours at 1-800-746-1553.”  (Tr. 22).[3]  Shortt assumed Lane discussed this section in class.  (Tr. 22, 34).  Despite the class, Vance did not report the communication outage.  (Tr. 48).  On cross-examination he conceded that he was not at the class and does not know what was discussed.  (Tr. 34-35, 42).  He just knows what Lane taught the electrical specialists.  (Tr. 35, 49).  Lane told Shortt that an outage for any reason was reportable.  (Tr. 49). 

 

The ERP says that Respondent must notify MSHA of communication failures lasting longer than 12 hours but it does not say when that notification must take place.  (Tr. 42-43).  Vance fixed the high voltage problem, but not the communication problem, on Friday because he was waiting for parts.  (Tr. 43-44).  As far as Shortt knew, Respondent ran coal on the weekend.  (Tr. 43).  Vance was not working on the system when Shortt arrived on Monday; he was waiting for parts.  (Tr. 44).  Shortt did not think it would be reasonable for Vance to wait until the failure was corrected before reporting.  (Tr. 45).  Shortt believed that if the communication system goes down on Friday at 5:00 pm it must be reported even if no one will be at the mine during the weekend.  (Tr. 41).  He said this during inspections.  (Tr. 41).  If there was confusion about the requirements, then the question should have been asked; especially in light of Lane’s class.  (Tr. 41). 

 

The purpose of the reporting requirements was to help MSHA collect data on the reliability of new systems.  (Tr. 35).  The wireless system was a new requirement for the mining industry.  (Tr. 30-31).  There were different manufacturers of different types of wireless systems.  (Tr. 31).  The mining environment and changing conditions in mining created some unique challenges to wireless systems.  (Tr. 31-32).  During this period, operators were having some issues with these systems.  (Tr. 32).  Shortt conceded that this situation was not like the reporting requirement of an accident where MSHA needs to take control of the scene, preserve evidence, and conduct an investigation.  (Tr. 35).  Time would not be of the essence.  (Tr. 35-36). 

 

Shortt recalled that Respondent’s wireless system had been up since May 11, 2011, a month before it was cited.  (Tr. 31).  Respondent and other operators had a lot of questions about the new reporting requirements under the ERP.  (Tr. 32).  An operator seeking clarification from MSHA is a good sign that it wants to comply.  (Tr. 32).  Respondent trained its employees, including Vance, on the ERP.  (Tr. 32).  Shortt felt Respondent did its part in training and getting “ahead of the game” as far as reporting was concerned.  (Tr. 33).

 

Only the T-section was down and to the best of Shortt’s understanding, wireless communications at Mine #36 R Section and U section were not down.  (Tr. 36-37).  The ERP discusses the system as a singular unit.  (Tr. 36). 

 

Shortt’s notes at Page 6 show that the wireless system was down because of a ground-fault condition, not because of a defect in the wireless system.  (Tr. 38).  A surge in the high voltage took out the power supplies for the system.  (Tr. 39).  However, he maintained that the ERP did not limit the reporting requirement to certain conditions.  (Tr. 39).  He believed reporting was required regardless of cause. (Tr. 40).

 

Shortt reviewed an MSHA Escalation Report dated June 24, 2011 (GX-3).  (Tr. 23).  An Escalation Report is a record of communication with MSHA’s 1-800 number. (Tr. 23-24).  The report stated, “Details provided by customer.  The caller is reporting their tracking and communication system is down.  The caller stated the system has been down since 9:10 last night 6/23/2011 in section A of the mine.”  (Tr. 24).  Shortt included this in his notes at page 11 because he called Lane to see if any failure had been reported for #36.  (Tr. 23).  He learned that #36 had not reported a communication failure but #30 had.  (Tr. 23, 32-33).  There were two sections in #30.  (Tr. 24).  Tim Thompson, the safety director for Dominion Coal reported this condition.  (Tr. 24-25). 

 

Shortt reviewed Order No. 8173479 (GX-1).  (Tr. 17).  He issued a 104(d)(2) order because Vance was the chief electrician and had been negligent.  (Tr. 26).  He went to Lane’s class and had knowledge of reporting requirements.  (Tr. 26).  Shortt learned from the mine file that Respondent was already on the (d) sequence.  (Tr. 26). Shortt did not go underground and actually observe the violation.  (Tr. 27).  He wrote the citation based on information he got from Vance.  (Tr. 27). 

 

With modifications, Shortt wrote the Order as no likelihood, no lost workdays, non S&S, and no miners affected.  (Tr. 46).  He initially marked the Order as “unlikely” because it was just a reporting requirement.  (Tr. 25).  He later changed it to “no likelihood” after speaking with his supervisors.  (Tr. 25).  They decided that no people would be affected and therefore there was no likelihood of injury.  (Tr. 25-26).  That is also why he marked no lost workdays.  (Tr. 26).

 

Shortt marked “High” negligence because Vance knew the system was down from the previous Friday and did not report it.  (Tr. 26).  Also, the negligence was designated as high, in part because the ERP was approved in December 2009.  (Tr. 27-28). On cross examination, Shortt conceded that the cut-off date for implementing the ERP was June 15, 2011.  (Tr. 28, 31).  Shortt’s deposition at page 51 also conceded this point.  (Tr. 29-30).  He explained that the plan was approved in 2009 and no changes were made between 2009 and 2011.  (Tr. 47).  Shortt does not believe there could be an honest mistake about reporting after Lane’s class; which cleared up any gray areas.  (Tr. 37).  Another mine, #30, received the class and properly reported an outage in one section.  (Tr. 37).  Shortt did not believe there were any mitigating circumstances.  (Tr. 46-47).

 

The violation was terminated when it was reported, but Shortt does not know when the actual problem was corrected.  (Tr. 51-52). 

 

b. Testimony of Ricky Keith Lawson:

 

Lawson had worked in the coal industry for 33 years.  (Tr. 53).  He had first-class foreman’s paper, repairmen’s paper, advanced first aid, and a dust card.  (Tr. 53).  He worked for Dominion for around 14 or 15 years.  (Tr. 53).  At the time Order No. 8173479 was issued, Lawson was the superintendent at #36.  (Tr. 54, 63).  A number of people, including Vance, reported to Lawson.  (Tr. 63).  Lawson reviewed reports on a daily basis.  (Tr. 63-64). 

 

Lawson was familiar with Order No. 8173479 (GX-1).  (Tr. 54).  Lawson was also familiar with the ERP for Mine #36 (GX-2).  (Tr. 54-55).  Lawson received yearly training by Respondent on this ERP, as did Vance.  (Tr. 55, 65).  He also received special voluntary training by Lane in May 2011.  (Tr. 55-56, 68).  Respondent’s superintendents, chief electricians, and anyone dealing with wireless communications attended that training.  (Tr. 58).  The tracking and communications requirements were about to go into effect and the training covered issues related to that event.  (Tr. 56, 65).  Those new requirements included a new wireless communication system and reporting duties.  (Tr. 56).  He could not remember the particulars of that training and was unsure if Lane discussed reporting.  (Tr. 68).  The reason the training was set up was because people had questions.  (Tr. 69).  The effective date for the ERP was June 15, 2011.  (Tr. 56).  Respondent had the wireless system in place at #36 by May 2011.  (Tr. 56-57).

 

There were different manufacturers of wireless systems in the industry.  (Tr. 57).  The mining environment and the changing conditions in a mine create unique challenges to wireless communication.  (Tr. 57).  Lawson described how Respondent had problems with its system.  (Tr. 57, 66).  On cross examination he conceded that was one of the reasons MSHA wanted to track outages.  (Tr. 66).  Respondent and other operators had questions about the reporting requirements for communication system failures in the summer of 2011.  (Tr. 57-58).  The questions dealt with both the communication system and the reporting requirements.  (Tr. 58). 

 

The power went down on T Section on Friday June 24, 2011.  (Tr. 58-59, 61).  This power outage caused problems with the wireless communication, because without power the wireless system cannot work.  (Tr. 59, 61).  Lawson learned about it on Friday via his home telephone.  (Tr. 64-65, 69).   There was no problem with the wireless; it was a high voltage problem.  (Tr. 61).  Vance worked on the power problem.  (Tr. 59).  He was responsible for reporting outages.  (Tr. 59-60).  Lawson could not recall if they moved coal on Saturday at the time they only produced every other weekend.  (Tr. 70). 

 

Lawson reviewed the Post-Accident Tracking Section on the ERP (GX-2).  (Tr. 60).  On cross examination he conceded that the ERP was approved in 2010 and the reporting requirement was there in 2010.  (Tr. 65).  He now knows that if communications go down on a single section he must report the condition.  (Tr. 60).  However, at the time of the outage this was a “gray area.”  (Tr. 60).  Similarly, the ERP says that the operator must report communication systems failures that extend longer than 12 consecutive hours but it does not say when to report.  (Tr. 62). 

 

Lawson discussed the Order with Vance.  (Tr. 67).  They did not discuss confusion over reporting, only the power.  (Tr. 67).  Lawson believed he spoke with Shortt on the day of the Order.  (Tr. 66).  He was aware that Shortt had issued a (d)(2) Order.  (Tr. 66).  He could not recall if he told Shortt that he believed he did not have to report the condition because it was only on the T section or because it was a power failure issue.  (Tr. 66-67).  He could not recall the reasons he gave to not reporting.  (Tr. 67).  On cross examination Lawson conceded that the communication requirements are in the ERP because in an emergency it is important for the outside to communicate with miners.  (Tr. 67).  If there was an emergency it would not matter if the power was down in the entire mine.  (Tr. 67-68).  He agreed that it did not matter what caused an outage in an emergency.  (Tr. 68). 

 

Lawson did not know if Respondent’s other mines reported a wireless failure at this time.  (Tr. 61).  Respondent was not trying to avoid reporting requirements.  (Tr. 61). 

 

4. Contentions of the Parties

 

            The Secretary contends that Order No. 8173479 was validly issued, that the violation had no likelihood of resulting in a no lost-workday injury, that no people were affected, that Respondent was highly negligent, that the violation was caused by an unwarrantable failure, and that the proposed civil penalty is, if anything, too low.  The Secretary argues that the citation is valid because power and communication went down and there was no report.  (Secretary’s Post-Hearing Brief at 12-13).  The Secretary argues that, with respect to gravity, the violation prevented proper implementation of vital accident preparedness systems.  Id. at 14.  Further, Respondent’s actions were highly negligent and the result of an unwarrantable failure because the area and time of the violation were extensive, the danger was obvious, there was notice to Respondent of the need to comply, knowledge of the violation, and abatement only occurred after the Order was issued.  Id. at 16-19.  Finally, the Secretary argues that the penalty should be increased to $16,000.00 in light of the seriousness of the violation.  Id. at 31. 

 

Respondent contends that Citation No. 8173479 was not validly issued, that it did not exhibit high negligence, that the violation was not the result of an unwarrantable failure, and that the proposed penalty is inappropriate.  Respondent argues that the citation was not valid because this was a power failure not a communications system failure, and because the standard did not state a time at which a report to MSHA had to be made.  (Respondent’s Post-Hearing Brief at 4-5).  Respondent argues that it was not negligent or guilty of an unwarrantable failure because of several mitigation factors, including their efforts to comply and sincere belief that a report was not necessary in this situation.  Id. at 9-12. 

 

5. Findings and Conclusions

 

a. Validity

 

            Pursuant to 30 U.S.C. §876(b) Respondent maintained an ERP.  According to page 5 of that Plan, “The operator shall [notify] the MSHA Hotline of a communication system failure that extends longer than 12 consecutive hours at 1-800-1553.”  (GX-2).[4]  It is uncontested that on June 24, 2011, at approximately 6:00 pm Mine #36 experienced a power outage that resulted in a failure of the communication system.  (Tr.  19-20, 58-59, 61).  Further, it is uncontested that Respondent did not report this failure to MSHA until MSHA’s inspection on the following Monday, June 27.  (Tr. 19, 43, 67). 

 

Therefore, the only issue that remains to determine whether this Order is Valid is if this outage had to be reported.  Respondent argues in its brief that this failure was not reportable because there was no system failure and because there was no time frame within which a system failure must be reported.  Respondent’s Post-Hearing Brief at 4-8.

 

With respect to the claim that the cited condition was not a system failure, Respondent notes that the communication system was down not as a result of a “system failure” but instead because of a power outage.  Id. at 4.  It argues that power outages, even if they result in loss of communication, are not required to be reported.  Id.  It supports this argument with several claims.  First, Respondent cites Shortt’s testimony to the effect that the purpose of the reporting requirement is to allow MSHA to evaluate wireless communication systems in order to determine that a loss of communication due to a power outage, to argue that a power outage does not relate to the reliability of the communication system.  Id. at 4-5.  It argues that the sort of reliability that MSHA wants to evaluate only deals with failure in the internal aspects of the communication system.  Id. at 5.  It goes so far as to say that reporting power outage as communication system failures would cause MSHA to reject communication systems for “failures” when, in fact, the systems functions perfectly.  Id.

 

I do not find this to be a compelling argument.  Respondent speculation as to how MSHA analyzes reported data has no basis in any evidence in the record.  There is no reason to believe that MSHA’s reporting requirements are different based on the cause of the communication system failure.  If one is to speculate on MSHA’s use of the reporting data, it is entirely possible that MSHA could glean important information about the reliability of a particular communication system based on the way it performs in the event of a power failure.  Perhaps MSHA could determine how a communication system would behave in the event of a mine emergency that results in a power outage.  Surely such an event is not beyond the realm of possibility.  In fact, in a catastrophic event like a fire or explosion it might be likely.  In short, MSHA is in the best position to determine the information it needs to evaluate the effectiveness of various communications systems. 

 

Also, I do not believe that requiring a report in the cited situation will decrease safety by marking a compliant system as a “failure.”  MSHA requires notification any time a wireless communication system goes down and presumably uses the data it receives in a manner consistent with the regulation’s objectives.  Information on how systems fare when the power goes out is certainly relevant to the regulations objective of communicating with miners in the event of an emergency.  Further, Respondent presented no evidence to support its contention that MSHA regards all system failures as equal.  It is possible that MSHA considers the reasons for a failure in its evaluation so that an otherwise stellar system would not be rejected solely because it fails during a power outage.

 

Respondent also claims that the wording of subpart (a) and subpart (b) of the ERP indicate that a “power outage” or the system “being down,” should not be considered a system failure.  Specifically, Respondent argues that subpart (a) on page 5 of the ERP describes what should be done in the event of a “communication loss,” which it argues is applicable to any loss of communication in a broad sense.  Respondent’s Post-Hearing Brief at 6, FN 4.  It further argues that subpart (b), the part at issue here, refers to a “system failure” not a communication loss, showing that this section has a narrower meaning that only deals with communication losses caused by internal communication system failures.  Id. 

 

Once again, Respondent’s argument is not compelling.  The entire focus of the section, entitled “Survivability Requirements,” is the operation of the communication system.  There is no indication that some subparts of that section are talking about broader or narrower issues.  Respondent does not explain why subpart (a) would be broader than the rest of the section.  Subpart (a) states, “In the event that communication is lost, the operator shall begin repairs to the system immediately…”  (Emphasis added).  If this section were talking about a broader conception of communication as a whole rather than just the internal system, it would make little sense for the first step in repairing lost communication to be to repair “the system.”  If anything, these two subparts show that the ERP treats “lost communications” and “system failure” synonymously.  A loss of communication is system failure and there is no reason to believe ERP contemplates different reporting or repairing requirements based on the cause of that failure.  As a result, the loss of communication in the cited situation, even though it was caused by a power outage, was a reportable system failure under the ERP.

 

Respondent’s next argument is that it was not required to report the cited condition because there was no time frame within which a system failure must be reported.  Id. at 6.  Respondent notes that ERP page 5, Subpart (b) states a system failure, “[t]hat extends longer than 12 consecutive hours,” be reported, but is silent as to when that report must be made.  Id. at 6-7.  Respondent states that MSHA learned about the condition about 52 hours later but that there is no way to know if it would have been a violation at 51 hours or after an 8 hour shift.  Id. 

 

There is perhaps some truth to that.  However, taken to its logical conclusion, Respondent’s position would mean that it would never have to report a system failure.  If 52 hours is absolutely permissible, then why would 52 days or 52 years not be absolutely permissible?  Of course, such a result would be absurd.  In the absence of a set deadline, the only way to read a reporting requirement is that a report be made within a reasonable time.  See Steele Branch Mining, 15 FMSHRC 597, 601-602 (Apr. 1993) (“Where a standard is silent as to the period of time required for compliance, the Commission has imputed a reasonable time.”) citing Penn Allegh Coal Co., 3 FMSHRC 2767, 2771 (Dec 1981); Monterey Coal Co., 5 FMSHRC 1010, 1019 (June 1983); and Old Ben Coal Co., 3 FMSHRC 608, 610–611 (March 1981); see also Cyprus Emerald Resources Corp., 20 FMSHRC 790, 798-799 (Aug. 1998). 

 

I do not need to define what a reasonable amount of time for delay would have been in this case.  Suffice it to say that a delay of over two days after the system failure is not reasonable in light of the goal of quickly providing MSHA with information to allow evaluation of communication systems.[5]  This is especially true in light of the fact that Respondent did not report the failure to the proper hotline, but was instead cited by Shortt.  There is no indication that Respondent would have ever reported the failure had Shortt not issued the Order. 

 

Finally, with respect to all of Respondent’s arguments regarding the validity of this order, it cites to no authority and simply appeals to my “common sense.”  However, I do not believe that common sense dictates the finding urged by Respondent.  As a result, I find that this Order was validly issued. [6]

 

            b. Gravity

 

The Secretary presented evidence that there was no likelihood of a lost workday injury and that no miners were affected.  (Tr. 25-26, 46).  This means this violation is merely a paperwork violation. Respondent did not contest these determinations in its Post-Hearing Brief.  Therefore, I find that the Secretary proved the gravity in the Order by a preponderance of the evidence.[7]   

 

c. Unwarrantable Failure and Negligence

 

Order No. 8173479 was marked as an unwarrantable failure and high negligence.  The Commission has recognized the close relationship between a finding of unwarrantable failure and a finding of high negligence.  San Juan Coal Co., 29 FMSHRC 125, 139 (Mar. 2007) (remanded because a finding of high negligence without a corresponding finding of unwarrantable failure was “seemingly at odds.”).  Emery Mining Corp., defines an unwarrantable failure, as “aggravated conduct constituting more than ordinary negligence.” Emery Mining Corp., 9 FMSHRC 1997, 2002 (Dec. 1987).  The Commission formulated a six factor test to determine aggravating conduct. IO Coal Co., Inc., 31 FMSHRC 1346, 1350-1351 (Dec. 2009).[8]  Before discussing the high negligence designation, I will consider each of those factors in turn:

 

1.     Extent of the violative condition

 

            According to the evidence presented at hearing, this condition affected the entirety of the T-Section.  (Tr. 20).  This was one of only three active working sections of the mine and therefore constituted a large area of the working area of the mine.  Respondent presented no evidence that would suggest this outage was less extensive.

 

2.     The Length of Time of the Violation Existed

 

            According to the evidence presented at hearing, the communication system went down at approximately 6:00 p.m. on June 24 and was still down, and unreported, on Monday morning when Shortt arrived.  This means that the extensive communication failure existed for more than 50 hours before MSHA learned of the condition. 

 

            Respondent presented no evidence that would suggest the violation existed for a shorter time.  However, it argued that the length of time in this case is immaterial because the standard contained no deadline for reporting the condition.  Respondent’s Post-Hearing Brief at 12.  However, as discussed earlier, the absence of a set deadline cannot be used to ignore the reporting requirement entirely.  This was an unreasonably long delay in reporting the cited condition.  Therefore, I cannot find the lack of a set deadline in the ERP to be a mitigating factor with respect to the unwarrantable failure determination.

 

3.     Whether the violation is obvious or poses a high degree of danger

 

            As already discussed with respect to gravity, this particular violation did not pose a high degree of danger.  However, the complete failure of the communication system in 1/3 of the active working sections of the mine was readily apparent.  In fact, Respondent actually knew about the condition almost immediately, on Friday evening and did not report it. 

 

4.     Whether the operator had been placed on notice that great efforts were necessary for compliance or on notice that this was an issue.

 

            This factor is the most heavily contested in this case.  The Secretary argues that Respondent voluntarily agreed to participate in training with MSHA and therefore should have known the reporting requirements.  Secretary’s Post-Hearing Brief at 17-18.  Furthermore, Respondent’s other conversations with MSHA indicate that Respondent was on notice.  Id. at 18.  Respondent counters, citing the same conversations and training to assert that it was attempting to be proactive in compliance with the rules and that its assumption that the power outage was not a reportable “system failure” was reasonable.  Respondent’s Post-Hearing Brief at 10-11.  Also, Respondent notes that Shortt was not present for the training conducted by Lane and therefore cannot attest to whether this particular issue was discussed.  Id. at 10.  Finally, Respondent argues that the requirements had only become effective nine days before the power outage and therefore they lacked experience with respect to whether this was an issue.  Id. at 11.    

 

            I do not believe that the factors cited by the Respondent mitigate the fact that Respondent was on notice that it was required to report the cited condition.  Vance, Respondent’s official responsible for reporting outages, knew or should have known that this was a reportable condition.  The fact that Respondent spoke with MSHA about the ERP and requested training is admirable, but it does not mitigate this particular violation.  If anything, it shows that MSHA was available to speak with Respondent about any “gray areas” that existed in the enforcement of the ERP and was willing to work with Respondent to ensure compliance.  Respondent’s decision to assume that it was not required to report the outage, in light of the fact that it has admitted that it was confused about the requirements, was not reasonable.  The prudent course of action would be to err on the side of caution and report the condition to MSHA.  Respondent’s conduct is best seen as a break from its previous proactive attitude with resepct to the communication system.  

 

            Similarly, I do not believe it is relevant that Shortt was not present for Respondent’s training.  It is not important whether Respondent’s employees were specifically told that they were required to report a communication system failure under any circumstances.  Instead, it is important that Respondent knew that MSHA would be focusing on these new communication systems and that MSHA was willing to answer questions to assist in compliance.  There is no evidence to suggest that Respondent was not aware of these facts.

 

            Finally, the fact that the standard was new is not a mitigating factor.  The Secretary presented evidence showing that the ERP had been in effect for a considerable amount of time, even if it had not yet been mandatory.  Perhaps even more importantly, the legal requirement to follow the ERP did not contain a grace period.  It would not have mattered if the power outage had occurred on the day the law became effective, Respondent was responsible for following the law.  Again, if there was any legitimate confusion, MSHA was available for consultation.

 

5.     The operator’s efforts in abating the violative condition

 

            Respondent only reported the wireless outage when directed to do so by Shortt.  There is no evidence to suggest Respondent’s agents would have reported the outage of their own accord.

 

6.     Operator’s knowledge of the existence of the violation

 

            Well-settled Commission precedent recognizes that the negligence of an operator’s agent is imputed to the operator for penalty assessments and unwarrantable failure determinations.  See Whayne Supply Co., 19 FMSHRC 447, 451 (Mar. 1997); Rochester & Pittsburgh Coal Co., 13 FMSHRC 189, 194-197 (Feb. 1991); and Southern Ohio Coal Co., 4 FMSHRC 1459, 1463-1464 (Aug. 1982).  An agent is “any person charged with responsibility for the operation of all or part of a…mine or the supervision of the miners in a…mine.”  30 U.S.C. §802(e).  A supervisor’s knowledge  and involvement is an important factor in an unwarrantable failure determination.  See Lopke Quarries, Inc., 23 FMSHRC 705, 711 (July 2001) citing (REB Enterprises, Inc., 20 FMSHRC 203, 224 (Mar. 1998) and Secretary of Labor v. Roy Glenn, 6 FMSHRC 1583, 1587 (July 1984).  In this case, it is undisputed that both Lawson and Vance were aware that wireless communications were unavailable and did not report the condition. 

 

            Respondent does not contest the supervisory status of the Mine Superintendent (Lawson) and Chief Electrician (Vance).  Instead, it argues that they did not have knowledge because that this sort of event was reportable.  Respondent’s Post-Hearing Brief at 12.  As previously stated, even if Respondent did not know of the requirements it should have known or at least known to ask about the proper actions to take.  This is not a mitigating circumstance.

 

Further, high negligence exists where the operator knew or should have known of the violative condition or practices and there are no mitigating circumstances.  30 C.F.R. § 100.3(d).[9]  The Secretary presented extensive evidence that Respondent’s conduct exhibited high negligence.  Specifically, Vance knew the system was down from the previous Friday and did not report it.  (Tr. 26).  The ERP was approved on December 2009 and MSHA had conducted classes to ensure that Respondent was aware of its requirements.  (Tr. 27-28, 37).  Shortt did not believe there were any mitigating circumstances.  (Tr. 46-47). 

 

Respondent argues that there are several mitigating circumstances.  The list of mitigating factors provided by Respondent include many of the same arguments it used in defending against the unwarrantable failure designation.  Specifically, it argued its failure to report was a reasonable mistake (especially in light of the fact that the standard was new), that there was no deadline for making a report, that the employees were not trained to know this was a reportable event, and the fact that that Respondent was proactive in installing the communication system.  For the same reasons described above, these are not mitigating circumstances.

 

Respondent also provided several other possible mitigating factors.  Respondent’s Post-Hearing Brief at 12, FN 12.  Those possible mitigating factors are irrelevant.  Specifically, Respondent argues its negligence in failing to report the condition was mitigated by the fact that the gravity was low, because it ordered pieces to fix the power outage, and because the purpose of the reporting requirement was to test reliability rather than deal with an immediate safety concern.  Id.  None of these are relevant to the question of whether Respondent knew or should have known it was required to report the outage and are not mitigating factors. 

 

            Considering the six factors of the Emery Mining Corp. test, the Secretary has proven by a preponderance of the evidence that this violation was an unwarrantable failure.  Furthermore, none of the factors discussed at the hearing or in Respondent’s brief mitigate Respondent’s negligence or undermine the unwarrantable failure designation.   

 

d. Penalty

 

            Under the assessment regulations described in 30 CFR §100, the Secretary proposed a penalty of $4,000.00 for Order No. 8173479.  However, in his Post-Hearing Brief, the Secretary requested the penalty be increased to $16,000.  In light of the operator’s history (16 violations of Section 316(b) at this mine since 1/17/2012 (GX-2)), it’s size, it’s negligence, it’s ability to stay in business, the gravity of the violation, and the abatement; I do not believe an increase in the penalty is appropriate.  Instead, I affirm the originally assessed penalty of $4,000.00. 

 

ORDER NO. 8185281

 

1. Contents of the Order

 

            On March 2, 2011 at 9:20 a.m., Inspector Cornelius M. Simmons issued to Respondent Order No. 8185281.  Simmons found:

 

The operator of this mine has failed to contact MSHA immediately upon discovery of accident unplanned roof fall.  A roof fall occurred in the #2 entry of the CJ&L intake of this mine within fifty feet of the surface.  In the weekly examiner takes and records an air reading in this portal. In the record of the weekly examination the air reading stated “a movement of air”. The surface of the #2 entry has been covered with dirty by using an end loader.  The teeth marks from the loader bucket are visible in the dirt.  It is obvious that the weekly examiner was aware of the unintentional roof fall and it was not reported as required since the fall was above the anchorage horizon of the roof bolts.  The operator of this mine has engaged in aggravated conduct because they knew this fall had occurred and did not report it.  This violation is an unwarrantable failure to comply with a mandatory standard.

 

Government’s Exhibit 1 (Hereinafter GX-1).  Simmons noted that the gravity of this violation was “No Likelihood,” “No Lost Workdays,” and would affect one person.  Id.  He further marked that Respondent exhibited “Reckless Disregard” with respect to this violation.  Id.  However, on March 3, 2011 Simmons issued a modification, changing the negligence from “Reckless Disregard” to “High.”  Id. 

 

            2. Legal Standards    

 

Order No. 8185281 was issued under Section 104(d)(1) of the Mine Act.  That provision provides the following:

 

If, upon any inspection of a coal or other mine, an authorized representative of the Secretary finds that there has been a violation of any mandatory health or safety standard, and if he also finds that, while the conditions created by such violation do not cause imminent danger, such violation is of such nature as could significantly and substantially contribute to the cause and effect of a coal or other mine safety or health hazard, and if he finds such violation to be caused by an unwarrantable failure of such operator to comply with such mandatory health or safety standards, he shall include such finding in any citation given to the operator under this chapter. If, during the same inspection or any subsequent inspection of such mine within 90 days after the issuance of such citation, an authorized representative of the Secretary finds another violation of any mandatory health or safety standard and finds such violation to be also caused by an unwarrantable failure of such operator to so comply, he shall forthwith issue an order requiring the operator to cause all persons in the area affected by such violation, except those persons referred to in subsection (c) of this section to be withdrawn from, and to be prohibited from entering, such area until an authorized representative of the Secretary determines that such violation has been abated.

30 U.S.C. § 814(d)(1).

 

            The Order deals with an alleged violation of 30 C.F.R. §50.10(d) (titled “Immediate notification.”).  That section provides the following:

 

The operator shall immediately contact MSHA at once without delay and within 15 minutes at the toll-free number, 1–800–746–1553, once the operator knows or should know that an accident has occurred involving:

 

(d) Any other Accident

 

30 C.F.R. §50.10(d).

 

3. Summary of Testimony

 

a. Testimony of Cornelius Mack Simmons:

 

Simmons started in the coal industry in 1974.  (Tr. 72).  He worked at Dominion #36 from 2003 to 2007.  (Tr. 72-73).  He ran equipment and did repair work.  (Tr. 73).  He did not have any examination duties and was not a foreman, although he does have foreman papers.  (Tr. 73).  Simmons had been a coal mine inspector for MSHA for about six years.  (Tr. 71-72).  As an inspector, Simmons duties include finding violations in coal mines.  (Tr. 73). 

 

At the time of issuance, Simmons had inspected #36 for two or three inspection periods.  (Tr. 73-74). He was familiar with the CJ&L intake entryway.  (Tr. 74).  He had inspected it twice before the issuance of Order No. 8185281 on March 2.  (Tr. 74).  The CJ&L air intake was used to ventilate the mine, remove harmful gasses and/or render them harmless, and to help carry dust away from working miners.  (Tr. 74).  There were three entries into CJ&L.  (Tr. 74).  Simmons sketched a map of the CJ&L (GX-3).  (Tr. 74-76).  He labeled the entries 1, 2, and 3.  (Tr. 76).  The circles on the map are timbers.  (Tr. 79).  There were timbers across all three entries.  (Tr. 118).  The entries were approximately 20 feet wide and four feet tall. (Tr. 76).  The distance from the entryway, outby the timbers, to the surface was about 100 feet.  (Tr. 76-77). 

 

Under 30 C.F.R. §75.364(b)(1) Respondent is required to travel one of the entries in its entirety weekly to record hazards (including bad top and harmful gases), methane accumulations, and air tank leaks.  (Tr. 74, 77, 97, 118).  “Traveling in its entirety” means traveling from start to finish. (Tr. 78).  There were no signs directing the examiner which entry to travel.  (Tr. 118).  It was not necessary to actually travel out of the portal.  (Tr. 113-114).  Respondent had to record their findings in a weekly record.  (Tr. 77).[10]  It also had to take air readings in each of the three entries.  (Tr. 77-78, 97).  Entry #1 contained an old fan housing that would allow travel outside.  (Tr. 97-98).  On cross examination, he conceded that if an examiner traveled the entirety of the #1 Entry weekly but not the #2 Entry, then the examiner complied with 30 C.F.R. 75.364(b)(1) (Tr. 98, 114).  Respondent was not cited for a violation of that standard.  (Tr. 98). 

 

On March 2, 2011 Simmons went to #36.  (Tr. 80).  He went into the mine office and reviewed the weekly book.  (Tr. 80, 83).  The report for #2 entry did not contain a normal air reading but instead said there was a movement of air.  (Tr. 80).[11]  The measurements showed that the amount of air moving dropped from 30,000 to 50,000 feet per minute to 60 feet per minute.  (Tr. 81, 90-92).  This signified an air blockage.  (Tr. 81).  Below 50 feet per meter the blades on the anemometer will not turn.  (Tr. 91).  On cross examination, Simmons conceded that Respondent was not required to maintain any specific cubic feet of movement or any specific velocity in #2 entry and was not cited for failure to maintain air velocity.  (Tr. 96).  Further, the CJ&L intake was supplemental ventilation for the mine.  (Tr. 96).  By the time of the hearing the CJ&L was sealed.  (Tr. 96). 

 

At some point he traveled underground with T.J. Howington (“Howington), a weekly mine examiner.  (Tr. 83).  Simmons and Howington traveled all three entries in their entirety and had done so in the past.  (Tr. 78-79).  He had not seen dangers in these areas before.  (Tr. 79). Simmons asked why there was no air reading and Howington told him there had been a roof fall a few weeks earlier, after February 11, 2011.  (Tr. 81, 83).  Howington said it had occurred right after there was a gas inundation on T Section.  (Tr. 83).  Simmons asked Howington if anyone had reported the roof fall.  (Tr. 82).  Howington did not answer so Simmons asked again.  (Tr. 82).  Howington said he did not know what Lawson had done.  (Tr. 82). 

 

At the #2 Entry, Simmons and Howington saw downed timbers, a sign of danger.  (Tr. 84).  There were no danger signs on the timbers.  (Tr. 85).  Timbers are used to support the roof.  (Tr. 87).  Timber does not necessarily mean the area is dangered off; in some cases people can travel through timbers.  (Tr.87).  It was possible to travel through the timbers here.  (Tr. 87-88). 

 

There was a roof fall in the area.  (Tr. 84).  Some rocks fell and pulled the heads off of the bolt.  (Tr. 84).  Inby there was so much rock that the bolts were not visible.  (Tr. 84, 85).  The bolts were probably covered; likely more than the length of the bolts that had fallen out.  (Tr. 85).  The top of the fall was at least five feet tall.  (Tr. 84-85, 95,100, 118).  However, he would have exposed himself to danger by looking, so it may have been higher.  (Tr. 84-85).  In his deposition he stated that the material was as high as the entry or higher.  (Tr. 101, 108).  On cross examination he conceded that the entry was around four feet before it fell, though his notes say five feet.  (Tr. 101, 108).  However, he stated that when the fall occurred, it pulled some material from the bolts, broke the heads off, and left these bolts sticking down from the top.  (Tr. 102).  Beyond that point, more fell in, so there was at least five feet in the fall.  (Tr. 102).  The fall was as wide as the entry, but thicker in the middle than at the sides.  (Tr. 85, 102).  He could not walk through the entryway and could not get beyond the fall.  (Tr. 85). 

 

Respondent had reported unplanned roof falls at Dominion #36 to MSHA in the past.  (Tr. 98-99).  Simmons does not know why Respondent would not report this roof fall, but they still may have had an incentive he did not know about.  (Tr. 99-100). 

 

Simmons and Respondent disagreed on whether the #2 entry was dangered-off. (Tr. 114).  Examiners know not to travel in a dangered-off area.  (Tr. 115).  If #2 Entry had been dangered-off and the examiners knew it then the area would not be a place where miners were normally required to work and travel.  (Tr. 115-116).  As a result, an unplanned roof fall, even above the anchorage, would not be reportable.  (Tr. 116). 

 

Simmons was familiar with the mud seam that ran from Entry #3 to Entry #1.  (Tr. 89).  The CJ&L had mud seams depositing loose material on the mine floor in all three entries through roof cracks.  (Tr. 90, 102-103).  There were mounds of dirt, about a foot high, where material had fallen.  (Tr. 89, 102-103).  It was possible to walk over that material and Simmons had done so.  (Tr. 90).  There was mud between the portal and the dual row of timbers in #2 entry that had dribbled down.  (Tr. 103).  He could not see what was inside this pile of debris.  (Tr. 103-104).  A mud seam can deposit material on the mine floor from up into the mountain above the entry.  (Tr. 103, 111).  The amount of deposits can vary depending on climate conditions and rain.  (Tr. 103).   The roof fall had rocks in it.  (Tr. 90, 105).  Simmons did not see any way to differentiate between material that fell from the mud seam and how much came from a rock fall.  (Tr. 104).  There was some material from the mud seam with rock on top.  (Tr. 104-105). 

 

Simmons reviewed Citation No. 8186555, which was issued on August 15, 2011 and stated that mud accumulated in the CJ&L up to half the entry.  (Tr. 106, 117).  The inspector did not indicate seeing any roof bolts pulling down near the mud seam in this citation.  (Tr. 117).  The citation was beyond the timbers.  (Tr. 117).  Mud depositing is not an unplanned roof fall.  (Tr. 108).  Respondent was not cited for an unplanned roof fall on August 15.  (Tr. 108). 

 

With Respect to Order No. 8185281, if a mud seam deposited two and a half feet of material, it would not be an unplanned roof fall absent other evidence the fall was above the anchorage.  (Tr. 108-109).  The evidence that this fall was above the anchorage was that there were four-foot bolts and a five-foot entry.  (Tr. 110).  Simmons testified that if two and a half feet came from a mud seam and two and a half feet came from a rock fall then it would still be an unplanned roof fall.  (Tr. 110-111).  However, he admitted that the fact alone that there was a mud seam depositing material is not evidence of a roof fall above the anchorage.  (Tr. 111-112). 

 

Good evidence of a roof fall above the anchorage would be more material falling out and roof bolts.  (Tr. 112).  Simmons testified that he had seen unplanned roof falls with roof bolts in the material.  (Tr. 112, 118).  He did not see a single roof bolt in the material here.  (Tr. 113).  However, if the fall is deep the roof bolts will not be seen.  (Tr. 118-119).  The bolts break off in the top and stayed there.  (Tr. 119).  This is because they had been there so long and the heads of the bolts pulled off.  (Tr. 119).   This just leaves the bolts sticking in the top hanging down.  (Tr. 119).  The bolts had to be buried in the material.  (Tr. 119). 

 

In the CJ&L Simmons could not take an air reading because, as he learned when he went outside, Respondent had used an end loader to push dirt from outside.  (Tr. 85-86).  Therefore he does not know if the fall would have blocked the air.  (Tr. 85).  Howington said that when Stacy found the rock fall they had covered it up.  (Tr. 86). He did not know whether the dirt was causing the air restriction or if it was the material in the #2 Entry.  (Tr. 116).   All portals had a “do-not-danger” sign on the screen so no one would enter from the outside.  (Tr. 114). 

 

Simmons issued Order No. 8185281 (GX-1) for failure to report an unplanned roof fall at or above the anchorage zone.  (Tr. 94).  On cross examination, Simmons admitted that the fact that the fall was above the anchorage zone was the only support he gave for the Order.  (Tr. 95).  Further, he admitted that nothing in the inspection notes, the Order, or the deposition testimony says that travel or ventilation was impeded.  (Tr. 95-96). 

 

Simmons marked Order No. 8185281 with no likelihood of an injury.  (Tr. 88, 113).  This was because the fall already occurred; this was just a failure to report.  (Tr. 88).  That is the same reason it was marked no lost workdays.  (Tr. 88).  The Order was not S&S because Simmons did not expect people other than possibly weekly examiners to travel through the #2 entry.  (Tr.113).  It was a paper violation.  (Tr. 113). 

 

Simmons marked Order No. 8185281 as reckless disregard.  (Tr. 88).  However, he later talked to Stacy and his supervisors and decided it should be high negligence.  (Tr. 88-89).  Several foremen knew of the fall and did not report it as he should have.  (Tr. 89). 

 

b. Testimony of Greg Ratliff:

 

Ratliff worked for Respondent as a production manager and had worked in the mines for 27 years.  (Tr. 121-122).  A production manager helps with production, cut cycles, and mining.  (Tr. 121-122).  He worked as a belt shoveler, electrician, section foreman, maintenance foreman, chief electrician, mine foreman, and superintendent.  (Tr. 122).  He began with Respondent in 1988 and worked at #36 as superintendent from roughly 2000-2008. (Tr. 122-124, 135).  He then left that mine.  (Tr. 135). 

 

As superintendent, he had been through the mine and knew its intake entries, including the CJ&L.  (Tr. 124).  The CJ&L intake provides extra air for the mine.  (Tr. 124).  Ratliff reviewed a map of the CJ&L intake entries (RX-1).  (Tr. 125).  One of the entries, #3, has a fan house.  (Tr. 125).  The map appeared accurate.  (Tr. 125).  On cross examination he conceded it was only accurate as of 2009, he did not know if it was accurate for March 2, 2011.  (Tr. 137). 

 

Respondent conducted a weekly examination of the CJ&L wherein an examiner checked the roof conditions, the travel ways, and the air course.  (Tr. 125).  Only one entry had to be examined in its entirety.  (Tr. 125-126, 139).  He did not believe that they ever had to check for hazards in all three entries.  (Tr. 139).  However, if an examiner is traveling and sees a hazard, he is still required to report it in the weekly book, regardless of the entry.  (Tr. 140).  Further, air readings were taken at each entry.  (Tr. 140).  The only people who travel in the CJ&L intake were certified examiners.  (Tr. 141). 

 

Entry #3 had a path of travel where examiners could traverse the full length of the entry.  (Tr. 129).  To travel the entry in its entirety, an examiner would walk down the entry on the right rib to the fence portal and go out the fan door.  (Tr. 129).

 

Since 2009 it had not been possible to conduct the examination in Entry #2.  (Tr. 126).  In that year a state inspector issued a violation because the roof bolt plates deteriorated, so Respondent dangered it off.  (Tr. 126).  The area was dangered off outby the dual row of timbers and inby the portal, about 20 feet by 70 feet of space.  (Tr. 126, 138, 142).  The area remained unchanged from the time it was dangered off to March 2.  (Tr. 143).  Ratliff does not recall two rows of timbers also across Entry #1 and #3.  (Tr. 138).  To prevent people from entering the #2 Entry from outside, Respondent put up a chain-link fence and conducted regular security patrols.  (Tr. 127). These fences were placed on all three portals, though Ratliff did not recall if there were dangers signs on all three.  (Tr. 138). 

 

Ratliff knew that the area was dangered off because he personally placed the timbers.  (Tr. 127).  He also placed a “danger-do-not-enter” sign on one of the timbers.  (Tr. 127).  Respondent also wrote in chalk on the timbers and painted the ribs.  (Tr. 127-128).  The date board in the #2 Entry was near the center, on one of the timbers.  (Tr. 130).  Respondent did not authorize anyone to enter the dangered-off area.  (Tr. 128).  The weekly examiners were aware that the #2 Entry was dangered off. (Tr. 128).  Ratliff never traveled into the dangered-off area after placing the timbers.  (Tr. 129). 

 

There is a difference between dangered off areas and dangered off spots.  (Tr. 128).   To danger off an entire area, Ratliff would place a double row of timbers and a “do not enter” sign.  (Tr. 128).  To danger off a small spot he would just place some timbers or cribs that had “danger” written on them.  (Tr. 128).  It is possible to travel around such spots.  (Tr. 128).  There were danger spots in Entry #1 and #3.  (Tr. 128). 

 

Ratliff knew Howington as a contract belt examiner.  (Tr. 129).  Weekly examiners were trained that the #2 Entry was dangered off.  (Tr. 130).  David Addair (“Addair”) was a weekly examiner of the CJ&L intake before Howington.  (Tr. 130).  Addair showed Howington the area and told him it was dangered off.  (Tr. 130). No examiners were authorized to remove the danger sign in the #2 Entry.  (Tr. 131).  He believed that the Entry remained dangered off after he ceased to be superintendent.  (Tr. 131).  He also believed that Howington knew that this area was dangered off.  (Tr. 131).  However, on cross examination Ratliff conceded that he did not work at the mine when Howington conducted the examinations.  (Tr. 137). 

 

There is a difference between material from a mud seam and a roof fall.  (Tr. 131-132).  Ratliff never saw an unplanned roof fall in the dangered-off area of Entry #2.  (Tr. 132).  Simmons notes indicate that Ratliff found a roof fall there in February 2011 are inaccurate.  (Tr. 133).  However, he saw material from the mud seam there.  (Tr. 132).  Depending on the weather, mud or draw rock can build up quickly.  (Tr. 132-133).  Ratliff did not believe that the seam would weaken the roof, but it was an adverse condition.  (Tr. 138-139). 

 

When mining a new portal, it is standard practice to use bolts at least a foot longer than the normal bolts within 150 feet of the portal.  (Tr. 133-134).  The dangered off area in Entry #2 was within 150 feet of the portal.  (Tr. 134).  However, Ratliff was not able to confirm that longer bolts were used there.  (Tr. 134).  He did not know what type of bolts were required by the roof control plan.  (Tr. 139). 

 

Ratliff was not in the CJ&L intake when Order No. 8185281 was issued.  (Tr. 130).  He had no idea what the area looked like on the day of the Order or between 2009 and March 2011.  (Tr. 136-137).  However, he was in the CJ&L intake both before and after the issuance.  (Tr. 130-131).  On cross examination he discussed his deposition testimony wherein he stated he was not in the area on the day of the citation and could not recall the last time he was there before the Order.  (Tr. 136-137).  However, on re-direct examination he noted that in his deposition that he had been in the area of Entry #2 within the last year.  (Tr. 141).  He did not recall the exact time in his deposition, though he guessed around June 2011.  (Tr. 141-142).  This deposition testimony refreshed Ratliff’s recollection; he was in the #2 entry of the CJ&L intake in the summer of 2011.  (Tr. 142). 

 

c. Testimony of Timothy Harold “T.J.” Howington, Jr.:

 

Howington did not speak to Respondent’s counsel or the Secretary before the hearing.  (Tr. 158).  Howington had been in the coal industry for 12 years.  (Tr. 145).  In March 2011, he worked for Abby contractor at #36.  (Tr. 146).  He had done so for about two years starting in 2009 or 2010.  (Tr. 146).  Before that, he had worked for a time at #36 as an outby boss.  (Tr. 146).  As outby boss he examined belts, pre-shifted the mine, assigned work to care for and clean drives, and checked for hazardous conditions and corrected them.  (Tr. 146-147).  If he could not correct it, he would danger it off.  (Tr. 147).  To do this he would build something or set timbers and put up a sign.  (Tr. 147). He would also talk to the superintendent to correct a condition.  (Tr. 147).  Hazardous conditions were recorded in a book.  (Tr. 147).  There were many belt books at #36 including the main book and the books for Sections U and T.  (Tr. 147). 

 

Howington was familiar with the CJ&L.  (Tr. 148).  He was responsible for taking three air readings and drift amounts for the each of the three entries there.  (Tr. 148).  There were timbers in each entryway of the CJ&L.  (Tr. 148).  At #2 Entry, where he took an air reading, there were eight timbers set.  (Tr. 148).  The area was dangered off behind the timbers.  (Tr. 149). He was told never to go beyond the timbers.  (Tr. 162).  On a weekly basis, the examiner would be in the CJ&L and that person knew not to go beyond the dual row of timbers in the #2 entry.  (Tr. 160).  Entry #2 was not an active working area of the mine.  (Tr. 166).  He did not believe there were timbers in the #1 Entry.  (Tr. 149).  There were two rows of timbers and an old fan in the #3 Entry.  (Tr. 149).  The timbers were placed evenly across the 18-20 foot entries and spaced four feet apart.  (Tr. 149-150).  He did not think there were dangers signs on the timbers or the word “danger” written on the rib in Entry #2 or #3.  (Tr. 151).  Howington knew Addair, another miner who took him through the CJ&L and showed him how to do a weekly exam.  (Tr. 159).  Addair showed him where the area was dangered off with eight timbers.  (Tr. 159).  Addair might have showed him a danger sign.  (Tr. 159).  Addair told him that the entries were dangered off from access because the bolts had rotted, creating unsupported top.  (Tr. 160). 

 

Howington was required to check for hazardous conditions in the CJ&L intake.  (Tr. 150).  He looked to see if there were hazardous conditions in each entry.  (Tr. 150).  He would look behind the timbers for hazardous conditions.  (Tr. 150).  He went behind the timbers in the #3 entry where the fan housing was located.  (Tr. 150).  However, there was a safe path in the #3 entry to allow weekly examination.  (Tr. 160).

 

Howington recalled traveling with Simmons in the CJ&L at least one time, in March 2011.  (Tr. 151, 153).  He went to do his weekly examination and Simmons went with him.  (Tr. 153).  When they started Howington told Simmons there had been a roof fall.  (Tr. 153).  Simmons asked if it had been reported and Howington said he was sure Respondent did.  (Tr. 153).  They went to the area and looked at the fall.  (Tr. 153). 

 

Howington learned about the roof fall from someone else but could not remember who.  (Tr. 154-156).  He learned about it when the mine had flooded and they had to pump out the CJ&L.  (Tr. 155).  He did not see it then because the mine was idle and only bosses were present, but Stacy and Ratliff had run water line in Entry #3.  (Tr. 155-156).  The fall happened sometime in a two-week period between an examination (where he did not see the condition) and the water situation.  (Tr. 165).  On the third week he saw the fall.  (Tr. 165).  His best guess was that it occurred between January 2 and March 2.  (Tr. 165-166). 

 

There was a mud seam in the CJ&L intake that deposited material on the bottom in the #2 entry and the whole area.  (Tr. 160-161).  Depending on weather conditions a lot of material could be deposited.  (Tr. 161-162).  If mud fell from the deposit it would not have been a roof fall.  (Tr. 163).  However, Howington believed that the material behind the timbers was where the roof had given way.  (Tr. 161-163).  All of the material was from the top.  (Tr. 163).  That is why it was dangered off.  (Tr. 162).  He could see the bolts hanging down.  (Tr. 164).  The fact that the bolts were out was an indication of how much had fallen.  (Tr. 164).  He could see the bolts with the glue packed around it.  (Tr. 164).  He could not remember if there were bolts at the bottom in addition to the bolts at the top.  (Tr. 164).  The bolts at the top were still anchored.  (Tr. 164). 

 

Howington did not recall discussing the previous day’s air readings with Simmons.  (Tr. 154). He had recorded a finding of “air movement” in a weekly record book.  (Tr. 156).  This means that there is enough air for the blades of the anemometer to move but not enough to get a good reading.  (Tr. 156). 

 

During the examination, Howington and Simmons walked to the portals in each entry but he could not recall going beyond the timbers.  (Tr. 151).  The portals were where the entries opened to the surface.  (Tr. 152).  All three portals were fenced off from outside.  (Tr. 152).  It is only possible to reach the outside through a door in the fan housing.  (Tr. 152).  None of the portals had danger signs.  (Tr. 152).  He recalled exiting out the #3 Entry.  (Tr. 152).  He could not remember if he went to the fence in #2 Entry.  (Tr. 142-153).  They went outside.  (Tr. 157).  There they saw dirt pushed up against the outer entry of #2.  (T. 157).  He did not know why this was done or who did it.  (Tr. 157). 

 

d. Testimony of David Addair: 

 

Addair worked as a mine foreman for Respondent and had been in the mines for about 32 years.  (Tr. 169).  He had worked as an outside man, a scoop man, miner operator, and foreman.  (Tr. 169).  He started with Respondent in January 2006 and was a full time employee starting in 2008.  (Tr. 169-170).  He is a certified foreman, electrician, shop foreman, dust sampler, and is certified in first aid.  (Tr. 170). 

 

He worked at #36 from January 2006 to October 2010 as a belt examiner.  (Tr. 170).  He also examined the CJ&L.  (Tr. 171).  The CJ&L provides extra intake of air.  (Tr. 171).  There were three entries to the CJ&L, examined weekly.  (Tr. 171).  Only certified examiners entered the CJ&L.  (Tr. 173).  To examine CJ&L, he would take air readings, put on the date, initials, and check for hazardous conditions.  (Tr. 171).  He did not travel all three entries, he just traveled one in its entirety, usually #3.  (Tr. 171-172, 177).  Entry #3 had the door to get outside in the fan housing.  (Tr. 172).  He took air readings in all three entryways, including #2.  (Tr. 176).  He did this even though it was dangered off but did not know why.  (Tr. 177).  However, he did not go beyond the double row of timbers to take air readings.  (Tr. 181-182).

 

He had to check for hazardous conditions.  (Tr. 177).  If he saw a hazardous condition he would take care of it.  (Tr. 178).  While he only traveled up one entry, he would look in the others.  (Tr. 178).  If he saw a hazardous condition he would fix it or danger it off.  (Tr. 178).  However, he never found any hazardous conditions in his weekly reports that he could not fix.  (Tr. 179).  He would not know about a hazardous condition in an entry if he did not travel it.  (Tr. 182).  All weekly reports were in the foreman’s office.  (Tr. 180).  He filled them out and the superintendent countersigned.  (Tr. 180). 

 

Addair did not go down #2 Entry after they set the timbers.  (Tr. 172). Entry #2 was dangered off with a piece of belt with “danger” written on it.  (Tr. 172-173).  It was hanging in the center of the first row of timbers on the inby side.  (Tr. 173).  Employees were not supposed to go beyond the dual row of timbers.  (Tr. 173).  There were areas where danger was written in chalk in #1 and #3 Entries.  (Tr. 173).  However, there was a path on the right side of #3 to walk.  (Tr. 174).  On cross examination, he conceded that there were two rows of timbers and danger signs across all three entries.  (Tr. 179).  He crossed the timbers in the #3 Entry.  (Tr. 179).  Sometimes they would travel #1 up to the portal.  (Tr. 179).  He crossed timbers that had “danger” on them.  (Tr. 179).

 

The last three months he was a belt examiner, Howington took over examining the CJ&L.  (Tr. 170-171, 174).  Addair walked Howington through the CJ&L and told him how to do the exam.  (Tr. 174-175).  Addair told Howington the #2 Entry with the dual rows of timbers were dangered off.  (Tr. 175).  He was not sure that he told Howington not to go beyond the dual row of timbers, but he knew what the timbers meant.  (Tr. 175).  When he showed Howington the area, the danger sign was there.  (Tr. 175).  Addair left #36 in October of 2010 and had not been doing examinations of the area for three months prior to his departure.  (Tr. 180).  He did not know anything about the conditions after Howington took over.  (Tr. 180-181). 

 

There was a mud seam in the CJ&L.  (Tr. 175).  The mud seam deposited material in the dangered-off area.  (Tr. 175).  The amount depended on the weather.  (Tr. 175-176). 

 

When driving a new portal entry, within 150 feet of the portal, it is proper procedure to use bolts a foot longer than usual.  (Tr. 176).  The dangered off area in #2 was within 150 feet of the portal.  (Tr. 176). 

 

4. Contentions of the Parties

           

            The Secretary contends that Order No. 8185281 was validly issued, that there was no likelihood that the violation would result in a no lost-workday injury, that one person was affected, that Respondent was highly negligent, that the violation was caused by an unwarrantable failure, and that the proposed civil penalty is, if anything, too low.  The Secretary argues that the citation is valid because a roof fall above the anchorage in a working section of the mine occurred and was not reported.  (Secretary’s Post-Hearing Brief at 22-26).  The Secretary argues that the Respondent’s actions were highly negligent and the result of an unwarrantable failure because the area and time of the violation were extensive, the danger was obvious, there was notice to Respondent of the need to comply, knowledge of the violation, and abatement only occurred after the Order was issued.  Id. at 28-29.  Finally, the Secretary argues that the penalty should be increased to $14,000.00 in light of the seriousness of the violation.  Id. at 31. 

 

Respondent contends that Citation No. 8185281 was not validly issued, that it did not exhibit high negligence, that the violation was not the result of an unwarrantable failure, and that the proposed penalty is inappropriate.  Respondent argues that the citation was not valid because the alleged violation did not occur in a working section and did not occur above the anchorage.  (Respondent’s Post-Hearing Brief at 17-25).  Respondent argues that it was not negligent or guilty of an unwarrantable failure because of several mitigation factors including their lack of knowledge and sincere belief that a report was not necessary in this situation.  Id. at 26-28.  Further, Respondent contends that Howington was not an agent of Respondent.  Id. at 29. 

 

5. Findings and Conclusions

 

            Order No. 8185281 was issued for an alleged violation of 30 C.F.R. §50.10(d), requiring an operator to contact MSHA within 15 minutes of several specific dangers or “Any other Accident.”  The regulations further define an “Accident” as, among other things, “An unplanned roof fall at or above the anchorage zone in active workings where roof bolts are in use; or, an unplanned roof or rib fall in active workings that impairs ventilations or impedes passage.”  30 C.F.R. §50.2(h)(8).  Therefore, the threshold issue in determining if this standard applies is whether the alleged roof fall occurred in active workings.  If the cited condition did not occur in active workings then it is not necessary to determine whether the alleged fall occurred above the anchorage zones, impaired ventilation, or impeded passage because the alleged fall would not be reportable.

 

Both the Mine Act and the Secretary's regulations define active workings as “any place in a coal mine where miners are normally required to work or travel” 30 U.S.C. § 878(g)(4) and 30 C.F.R. § 75.2.  In this case, the Secretary argues that the #2 Entry, where the cited condition was found, was an active working section where miners were normally required to work and travel.  Specifically, Simmons testified that Respondent was required to travel one of the entries in its entirety to conduct inspections.  (Tr. 74, 77, 97, 118).  The Commission has held that areas that are required to be inspected are active workings.  See e.g. Consolidation Coal Company, 22 FMSHRC 340, 348 (Mar. 2000) and Emerald Mines, 7 FMSHRC 437, 440-41 (Mar. 1985). 

 

Respondent countered that the Plan only required Respondent to inspect one of the entries in the CJ&L, that it always inspected the entry with the fan housing, and that the #2 Entry was dangered-off such that no one was required to enter the area.  It is undisputed that Respondent was only required to inspect one of the three entries; even Simmons testified that this was the case.  (Tr. 98, 114, 139, 171-172, 177).  Respondent’s witnesses testified that they always chose to inspect the entry with the fan housing because it had an unobstructed path to inspect in its entirety.  (Tr. 129, 171-172, 177).  Howington also testified that while the entries were dangered-off, there was a clear path in the fan house entry allowing it to be inspected in its entirety.  (Tr. 160).  Simmons was the only witness who testified that anyone inspected Entry #2 in its entirety.  Specifically, he claimed that he and Howington had done so on more than one occasion.  (Tr. 78-79).  Howington did not recall that event.  (Tr. 151).

 

Respondent claims that it did not inspect the #2 Entry because that entry was dangered-off.  This is the crux of the issue here.  The Commission has held that when an area has been dangered-off it is no longer an active working.  Cyprus Empire Corporation, 12 FMSHRC 911 (May 1990).  Even Simmons conceded during cross-examination, if the #2 Entry had been dangered-off and the examiners were aware of that fact the area would not be an active working.  (Tr. 115-116).  Respondent presented evidence to show that the area was dangered-off.  (Tr. 126, 177).  Further, Ratliff testified that everyone was aware that the #2 Entry was dangered off.  (Tr. 128).  Howington confirmed that the #2 Entry was dangered off and that this was known by the examiners.  (Tr. 149, 160).  Ratliff, Howington, and Addair disagree about how the #2 Entry was dangered off, but all agree that no one was supposed to enter the area. 

 

The only witness who testified that the miners were regularly required to enter the #2 Entry was the one witness, Simmons, who did not work there.  (Tr. 85-88).  In addition to Simmons testimony, the Secretary provided three arguments in his brief explaining why this area was not dangered-off.  First, the Secretary argued that the timbers did not indicate that the area was dangered off.  Specifically, he pointed to Simmons testimony that timbers were designed to allow people to enter the area and that Simmons, Howington, & Addair did so.  Secretary’s Post-Hearing Brief at 24.  However, I note that the Secretary’s argument that Simmons, Howington, and Addair traveled beyond the timbers is not based on the record.  Id.  It is true that Simmons testified he and Howington went past the timbers into the area.  (Tr. 78-79).  However, The Secretary cites to page 151 of the transcript for the proposition that Howington confirmed that assertion.  On that page of the transcript, Howington specifically stated that he did not travel beyond the timbers with Simmons.  In fact, he also stated that he knew never to go beyond the timbers and stated he could not recall traveling to the portal in the #2 Entry.  (Tr. 152-153, 160).  Further, the Secretary cites to page 179 for the proposition that Addair stated he traveled beyond the timbers.  However, that page deals with Entry #1, not Entry #2.  (Tr. 179).  Addair never said he traveled beyond the timbers in Entry #2; in fact he was emphatic that the area was dangered-off.  (Tr. 172-173).  The Secretary did not prove by a preponderance of the evidence that the timbers were placed in Entry #2 to allow miners to travel in that area or that miners regularly worked or traveled there.  I do not believe inspector’s entrance into a dangered-off area can, on its own, transform a dangered-off area into an active working section.

           

The Secretary also argues that there is a conflict in the in the testimony about what measures were taken to danger off Entry #2.  Secretary’s Post-Hearing Brief at 25.  The Secretary therefore asserts that the area was not actually dangered off.  Specifically, some witnesses testified that there were timbers across all three entries.  Id.  Some witnesses testified that there were danger signs at Entry #2 (or all of the Entries) while others did not.  Id.  The Secretary’s argument confuses appearance for substance.  The Secretary is correct that the three witnesses who worked at the mine differed on how the area was dangered off.[12]  Furthermore, it is true that some of the witnesses testified that there were signs and/or timbers across all of the entries.  (Tr. 114-115).  However, Ratliff, Howington, and Addair all testified unequivocally that the #2 Entry was dangered off with timbers and that they knew not to enter the area.  (Tr. 126, 128,149, 160, 177).  Further, they all testified that while there were timbers and blocked off areas in the other entries, there was an open travel path in Entry #3.  (Tr. 129, 160, 174).[13]  Clearly the miners who worked at #36 were aware of the active and inactive status of the various entries.  Simmons was the only witness who was not aware that it was impermissible to enter the #2 Entry.  Simmons’ belief was likely the result of confusion or misunderstanding and not because the area was active.

 

Finally, the Secretary argues that, as long as the CJ&L was open, Respondent was required to maintain and examine the area.  The Secretary asserts that before the alleged fall the examiners could have traveled any of the entries and nothing would stop them from continuing to do so after the fall.  As previously stated, it is clear that the miners who worked at #36 were aware of the conditions in the CJ&L and that they were not permitted to go beyond the timbers in the #2 Entry.  The Secretary provides no evidence to support his claim that the determination that this area was not active was made only for the purposes of the hearing or that miners regularly entered the area behind the timbers in Entry #2. 

 

I do not find any of the Secretary’s arguments to be compelling.  In light of the evidence, I find that the #2 Entry was dangered-off and therefore not an active working.  As a result, 30 C.F.R. §50.10(d) does not apply in this matter as there was no reportable accident as defined in 30 C.F.R. §50.2(h)(8).  Therefore, I find that the Secretary has not proven by a preponderance of the evidence that a violation has occurred.  This Order is DISMISSED and no civil penalty will be levied. 

 

 

 

ORDER

 

In light of the affirmation of Order No. 8173479 and the dismissal of Order No. 8185281, Respondent, Dominion Coal Corporation, is hereby ORDERED TO PAY the Secretary of Labor the sum of $4,000.00 within 30 days of the date of this decision.[14]  

 

 

 

                                                                        /s/ William S. Steele  

William S. Steele

                                                                        Administrative Law Judge

 

 

Distribution: (U.S. Certified Mail)

                                                                       

Emily K. Hargrove, Esq. & Daniel D. Povich, Esq., U.S. Department of Labor, Office of the Solicitor, 1100 Wilson Blvd., 22nd Floor West, Arlington, VA 22209. 

 

Wm. Scott Wickline, Esq. & David J. Hardy, Esq., Hardy Pence PLLC, 500 Lee Street, East, Suite 701, PO Box 2548, Charleston, WV 25329        



[1] Hereinafter references to the transcript will be cited “Tr.” with the page number.

[2] The wireless communication system is designed to allow miners to communicate throughout the mine at specific areas while they are working.  (Tr. 40).  The communication system helps miners escape during an emergency.  (Tr. 49). 

 

[3] There was an obvious typo in the ERP and Shortt believes it has since been corrected.  (Tr. 22). 

[4] The evidence established at hearing that there was a scrivener’s error in that plan and that the word “notify” should be included after the word “shall”.  (Tr. 22). 

[5] However, it is significant that the number Respondent was to call, 1-800-746-1553, is the same number used for reporting accidents.  That section states that “[t]he operator shall immediately contact MSHA at once without delay and within 15 minutes,” when an accident occurs.  30 CFR § 50.10.  The fact that the number given in the ERP was for a fast-response hotline with expertise in serious, even deadly, accidents indicates that the report should have been made rapidly.

 

[6] At hearing, Respondent’s witness raised the issues that communication system here was down in only one section and that it was only required to report system-wide failures.  (Tr.66-67).  As with the argument that it was not required to report communication failures caused by power outages, there is no reason to believe there is a distinction between communication loses in one area or in the entire mine.  As Lawson conceded, it would not matter in an emergency if power was down in one area of the entire mine.  (Tr. 67-68).  Furthermore, Respondent did not brief this issue.  Therefore, I find it is not a mitigating factor.

[7] The Secretary argues that there was some higher degree of gravity in this violation, even arguing that it could be S&S.  Secretary’s Post-Hearing Brief at 14-15.  However, this contradicts the opinion of the inspector; an opinion that is entitled to considerable deference.  MSHA inspectors are entitled to a certain level of deference as to their findings and opinions.  See e.g. Harlan Cumberland Coal Co., 20 FMSHRC 1275, 1278-79 (Dec. 1998) and Buck Creek Coal, Inc. v. MSHA, 52 F.3d 133, 135-36 (7th Cir. 1995).  As a result, I will not disturb the gravity cited in the Order.

 

[8] While an administrative law judge may determine, in his discretion, that some factors are not relevant, or may determine that some factors are much less important than other factors under the circumstances, all of the factors must be taken into consideration and at least noted by the judge.  IO Coal, 31 FMSHRC at 1351

[9] Under Commission precedent and promulgated standards, negligence “is conduct, either by commission or omission, which falls below a standard of care established under the Mine Act to protect miners against the risks of harm.”  30 C.F.R. § 100.3(d).  “A mine operator is required to be on the alert for conditions and practices in the mine that affect the safety or health of miners and to take steps necessary to correct or prevent hazardous conditions or practices.”  Id.  Low negligence exists when “[t]he operator knew or should have known of the violative condition or practice, but there are considerable mitigating circumstances.”  Id.  Moderate negligence is when “[t]he operator knew or should have known of the violative condition or practice, but there are mitigating circumstances.”  Id.  High negligence exists when “[t]he operator knew or should have known of the violative condition or practice, and there are no mitigating circumstances.”  Id.  Finally, an operator exhibits reckless disregard where it acts without the slightest degree of care.  30 C.F.R. § 100.3(d).  Mitigating circumstances may include, but are not limited to, actions taken by the operator to prevent or correct hazardous conditions or practices.  Id. 

 

[10] Respondent records weekly examination results in the weekly books.  (Tr. 82).  The books cannot be altered and they must be kept for one year.  (Tr. 82).  The weekly reports contain air readings, locations traveled, hazards, and corrections.  (Tr. 82). 

 

[11] A “movement of air” is not enough to be measured by an anemometer. (Tr. 81, 90).  An anemometer is a tool used to measure air.  (Tr. 90).  It measures air velocity and is used to determine the quantity of air passing through an area.  (Tr. 90). 

[12] Ratliff testified that he placed timber to block the #2 Entry, wrote in chalk on the rib, and place a “do-no-enter” sign.  (Tr. 127-128).  Howington testified that there were timbers across the entry.  (Tr. 159).  Addair testified that there was a piece of belt with the word “danger” written on it.  (Tr. 172-173). 

 

[13] I find that Howington’s testimony on these points particularly probative because he no longer works for the Respondent and was even subpoenaed by the Secretary to testify. 

 

[14] Payment should be sent to: MINE SAFETY AND HEALTH ADMINISTRATION, U.S. DEPARTMENT OF LABOR, PAYMENT OFFICE, P. O. BOX 790390, ST. LOUIS, MO 63179-0390