<DOC>
[DOCID: f:ke95296.wais]

 
R B COAL COMPANY, INCORPORATED
November 28, 1995
KENT 95-596


           FEDERAL MINE SAFETY AND HEALTH REVIEW COMMISSION

                    1730 K STREET N.W., 6TH FLOOR

                       WASHINGTON,  D.C.  20006

                          November 28, 1995


SECRETARY OF LABOR,            :    CIVIL PENALTY PROCEEDING
 MINE SAFETY AND HEALTH        :
 ADMINISTRATION (MSHA),        :    Docket No. KENT 95-596
                Petitioner     :    A. C. No. 15-17077-03543
           v.                  :
                               :    RB No. 5 Mine
R B COAL COMPANY,              :
 INCORPORATED,                 :
                Respondent     :

                           DECISION TO REOPEN
                     ORDER TO FILE PENALTY PETITION

Appearances:  Mark Malecki, Esq., Office of the Solicitor,
              U.S. Department of Labor, Arlington, Virginia,
              for the Petitioner;
              Richard D. Cohelia, R B Coal Company Inc.,
              Pathfork, Kentucky, for Respondent.

Before: Judge Merlin

     The issue presented is whether the operator may be allowed
to proceed to a hearing on the merits of its claim or whether 
the case  should  be  dismissed  because the operator did not 
request a hearing within the period allowed by the Mine Act and 
Commission regulations.

     On November 28, 1994, an inspector of the Mine Safety and
Health Administration issued to the operator Citation No. 4247308
under section 104(d) of the Act, 30 U.S.C. �  814(d). On the same
date the operator  was  also  issued  Order No. 4247309 under
section 104(d). Thereafter, on March 23, 1995, the Mine Safety
and Health Administration issued a Notice of Proposed Assessment
for the subject citation and order as well as for a  citation
issued under section 104(a).[1] The notice advised the operator 
that it had 30 days from the date it received the proposed 
assessment to either pay or notify MSHA that it wished to contest
the proposed assessment and was requesting a hearing. The notice
further told the operator that if it did not exercise these rights
within 30 days, the proposed assessment  would  become  a  final
order of the Commission. The notice was mailed certified mail
return receipt requested and received by the operator on March 28,
1995.

      The 30th day from the date of the operator's receipt of the
proposed assessment was April 27, 1995. MSHA's Civil Penalty 
Compliance Office received a request for hearing from the operator
which is date stamped May 26, 1995. The hearing request is signed
and dated May 12, 1995, by the operator's  engineer. On June 8,
1995, MSHA wrote the operator that the proposed assessment was 
final and that the hearing request could  not be honored because
the case had not been timely contested.

      On June 16, 1995, the operator  through its engineer wrote
the Commission seeking permission to contest these civil penalty 
assessments. The operator admitted that it had failed to contest
the assessments  within the 30 day period specified in section 
105(a) of the Act, 30 U.S.C. � 815(a), and section  2700.26  of
Commission regulations, 29 C.F.R. � 2700.26. According to the
engineer's letter, the hearing request was not filed on time
because it was misplaced in the paperwork of numerous assessments.
The letter further  stated that the company had just recently 
begun implementing a program aimed at contesting citations which
it considered excessive and that it was learning by trial and 
error, because it would be more expensive to hire an attorney 
than pay the assessments.

      On July 18, 1995, the Commission issued an  order treating
the operator's letter as a petition for discretionary review and
stated that it was unable to evaluate the merits of the operator's
position. Therefore, it remanded the case for a determination
whether relief was appropriate under applicable criteria. 17
FMSHRC 1110.

      On July 25, 1995, I issued an order requiring the Solicitor
to show cause why  the  case  should  not  be  assigned  to  an 
Administrative  Law  Judge  for  disposition  on the merits. 
Thereafter, on August 14, 1995, the Solicitor filed a response 
to the order to show cause, asserting that the operator had not
demonstrated  that  it  was entitled to  relief  and arguing that
even if the  reasons advanced justified relief, they were not
presented in such a manner as to obviate the need for a hearing.

      Attached to the Solicitor's motion were copies of the citation
and order issued to the operator for the alleged violations which 
had  been  designated  significant  and  substantial  and  due to 
unwarrantable failure.  Also attached was a copy  of  the  notice of
the proposed assessment, dated March 23, 1995,  together with the
assessment sheet.  The first alleged  violation  was assessed at 
$1,200 and the other at $1,500.

      A  notice  of  hearing was issued on September 28, 1995, and
a hearing was held on November 1, 1995.

      At the hearing the operator's engineer testified that he is
the individual at the mine who is served with citations and orders,
receives the notices of proposed assessments, and decides whether
to pay or contest them (Tr. 5-6, 10-11). He is the only person at
the mine who performs these tasks. Because the  operator is small
with only 100 to 120 total employees and in view  of the present 
state of mining, he has many other duties to perform (Tr. 16, 58). 
These other duties include  training  new  employees,  performing 
surveys, taking dust samples, inspecting sections before the MSHA
inspector comes and accompanying the inspectors on their inspections
(Tr. 5-6, 16). After receiving a citation he disagrees  with, the
engineer has a closeout conference  with the inspector and if the
matter remains unresolved, a health and safety conference is held
and if a resolution is not reached, he requests a hearing before
the Commission (Tr. 6-7). All citations issued by an inspector on
the same day do not come on  the  same proposed assessment notice
(Tr. 8). If a citation is going to be paid, the engineer tries to
stagger payments depending upon the operator's cash position at 
the particular time so that a few are paid at a time (Tr. 12).
Therefore, citations he decides to pay are not always forwarded
immediately to the operator's corporate office for payment (Tr. 
12). If he decides to appeal to the Commission, he also staggers
mailing hearing requests so that hearings will not all be at the 
same time (Tr. 28, 47-48). Due to his other responsibilities he 
cannot spend all his  time  during  a  given  period  contesting
citations (Tr. 16). According to  the  engineer,  the  operator  
routinely  contests citations and orders issued  under  section 
104(d) of the Act, supra, because it disagrees with the findings
of significant and substantial and unwarrantable failure (Tr. 7,
30). Also the assessments  in  these  cases  are  expensive and 
significant and substantial findings count toward their "pattern 
of violations" under section 104(e), 30 U. S. C. � 814(e) (Tr.
32).  In  the  engineer's  opinion  these  findings  have  been
excessive and he has been successful  in having them changed 
and securing settlements (Tr. 30-31, Op. Exh.  No. 3). He does
not necessarily let 104(a) citations slide either (Tr. 11).

      The engineer testified that two or three  months before he
received  the notice of proposed  assessment in this  case,  he
obtained a  new  computer  (Tr.  8-9).   When he received this
notice, he was entering on the computer citations  and notices
of  assessment  back  to 1993 (Tr. 25, 51).  For each case  he
enters the citation number,  the  assessment  control  number,
dollar  amount,  prior  action, and status (Tr. 9-10, Op. Exh.
No. 3).  This case is the  only  time  he  failed to request a
hearing  timely (Tr. 59-60).  After the late  filing  in  this
case, he purchased  additional  software  whereby he now has a
daily calender and can bring up deadlines (Tr.  49-50).  If he
had had this software when he received this notice,  he  would
not have been late (Tr. 50).

      The  engineer  explained  that it is his practice to put
contested citations in a file cabinet with their number on the
file (Tr. 27).  Citations that are to be paid are placed in  a
basket  on  his  desk  to  be taken to the corporate office at
Brookside which is 40 miles  away (Tr. 10-11, 25).  He circles
the citations he is going to contest and leaves a note for the
ones to be paid (Tr. 37, Gov't.  Exh.  1).   He  knew  when he
first saw the 104(d) citation and order in this case that they
would  be  appealed (Tr. 28).  At that time he was working  on
about 20 assessment  sheets (Tr. 14-15).  He could have filled
out the explanation portion of the hearing request entered the
data on the same day he  received  the  proposed assessment, a
couple of days later or even 15 days later (Tr. 28-29, 38-40).
Several orders were issued by the inspector at that particular
time and the engineer tried to space them  out  (Tr.  29).  He
does not dispute the date of receipt as March 28 and said that
the  return receipt card had been signed by an individual  who
works  in  the warehouse (Tr. 34-35).  Subsequently, on May 12
he signed the  hearing  request  and gave it to be mailed (Tr.
42-43).  As already stated, he staggers  hearing  requests  so
that  all the hearings will not occur at the same time, and he
did not intend this request to be late (Tr. 48).  The engineer
did not know why the request was mailed almost two weeks after
he signed it (Tr. 33).  When he signs a request for hearing he
gives it  to  the  office  worker  to  mail  (Tr.  33-34).  He
subsequently  found the request for hearing in the basket  for
assessments to  be paid, which was the wrong pile (Tr. 25, 29,
49).  Mail goes to  several different places and may have been
put in the wrong pile  or  misplaced (Tr. 47).  The individual
working in the office who is  responsible  for  mailing  is  a
miner's  widow  and  does  not know too much about secretarial
work (Tr. 46).  She just more  or  less  answers the telephone
(Tr.  34).   She  could  have  sent  the  hearing  request  to
Brookside by mistake (Tr. 47).

      According to the engineer, all citations issued on the same
day do not come out in the same notice of proposed  assessment and
assessment sheet (Tr. 8).  The number of notices and  assessment
sheets vary (Tr. 8).  As previously set  forth, the citation and
order at issue were included in the notice of proposed assess-
ment,   and  constitute  the  items  in  this  docket  number.
However,  on  November  28,  1994,  the  day  these items were
issued, two more citations also were issued (Tr.  29,  Op. Exh
No.  2).   All  these items were considered at the same Health
and Safety Conference  (Tr.  17 Op. Exh. No. 2).  However, the
other two citations were in a  different  notice  of  proposed
assessment  and  therefore,  when a hearing was requested  for
them, they were in a different docket number (Tr. 18).  I take
official note that according to  Commission records the docket
number  for  those  citations  is KENT  95-343  and  that  the
Secretary's  penalty  petition  there  was  filed  late  by  a
Conference and Litigation Representative ("CLR"), 29 C.F.R.
� 2700.28.  The reasons given for  the  late  filing  were the
newness  of the CLR program in which non lawyer MSHA employees
represent  the  Secretary in selected cases, and the confusion
of the CLR over the  correct contest date.  On May 26, 1995, I
accepted  the  explanations   offered   and  issued  an  order
accepting  the  Secretary's petition.  I noted  that  the  CLR
program represents  a  new  approach  which  I had approved in
prior  cases.   I also pointed out that the operator  was  not
prejudiced  by  the  delay.   Subsequently  those  cases  were
settled (Tr. 19, 21).

      Section 105(a) of the Act, supra, provides that an operator
has  30  days within which to notify  the  Secretary  that  it
wishes to  contest  the  citation  or proposed assessment.  If
within 30 days of receipt of the Secretary's notification, the
operator  fails to notify the Secretary  that  it  intends  to
contest the  citation  or  proposed  assessment,  the proposed
assessment becomes a final order of the Commission.   Id.   In
Jim  Walter  Resources,  Inc.,  15  FMSHRC 782 (May 1993), the
Commission  held that it has jurisdiction  to  decide  whether
final judgments can be reopened.

      Commission Rule  1(b)  provides  that  the Commission and
its judges shall be guided so far as practicable by the Federal
Rules of Civil Procedure.  29 C.F.R. � 2700.1(b).  In its July
18  order,  the Commission once again stated that it possesses
jurisdiction  to  reopen  uncontested  assessments  which have
become  final  under  section  105(a),  supra,  and that these
determinations are made with reference to Federal  Rule 60(b).
Federal Rule 60(b)(1) provides as follows:

           On  motion  and  upon such terms as are just, the
           court may relieve  a  party  or  a  party's legal
           representative from a final judgment,  order,  or
           proceeding    for    the    following    reasons:
           (1) mistake, inadvertence, surprise, or excusable
           neglect *   *    *.

      In  Pioneer  Investment Services  Company  v.  Brunswick 
Associates Limited Partnership, 113 S. Ct. 1489 (1993), 123  L.Ed
2d 74, the Supreme Court recognized that Bankruptcy Rule 9006(b)(1),
which  contains  the same "excusable neglect" standard  as  Rule
60(b)(1), grants a reprieve for out-of-time filings  delayed  by
"neglect".   123  L.Ed   2d   at  85.   In  interpreting  this
provision, the Court first turned  to  the  ordinary  meaning  of
"neglect",  which  it  said  was to give little  attention  or
respect  to  a matter or to leave  undone  or  unattended  to,
especially through carelessness.  Id.  The Court said that the
word "neglect"  therefore,  encompassed both simple, faultless
omissions  to  act  and, more commonly,  omissions  caused  by
carelessness.   Id.   The   Court  further  held  that  absent
sufficient  indication  to the  contrary  courts  assume  that
Congress  intends  words in  its  enactments  to  carry  their
ordinary  contemporary  common  meaning.   Id.   Consequently,
based on the  plain  meaning of neglect, the Court rejected an
inflexible  approach that  would  exclude  every  instance  of
inadvertent or negligent omission.  Id. at 89.

      With respect  to the meaning of excusable neglect the Court
in Pioneer stated as follows:

           Because Congress has provided no other guideposts
           for determining  what  sorts  of  neglect will be
           considered  "excusable,"  we  conclude  that  the
           determination  is  at  bottom  an equitable  one,
           taking  account  of  all  relevant  circumstances
           surrounding    the   party's   omission.    These
           include,. . . the  danger  of  prejudice  to  the
           debtor, the length of the delay and its potential
           impact  on  judicial  proceedings, the reason for
           the delay, including whether  it  was  within the
           reasonable control of the movant, and whether the
           movant acted in good faith.

 Id. at 89.

     Many Courts of Appeals have acknowledged and followed the test
set forth in Pioneer.  It has been explicitly recognized  that  the
decision in Pioneer represented a change from prior law

and adopted a new and more lenient interpretation.  U.S. v. Hooper,
9 F.3d 257 (2nd Cir. 1993); Matter of Christopher, 35 F.3d 232 (5th
Cir.  1994);  U.S. v. Clark, 51 F.3d 42 (5th Cir. 1995); Reynold v.
Wagner, 55 F.3d  1426  (9th  Cir. 1995); City of Chanute, Kansas v.
Williams Nat. Gas Co., 31 F.3d  1041  (10th Cir. 1994); Information
Systems and Networks Corp. v. U.S., 994  F.2d 792 (Fed. Cir. 1993).
See also, In Re SPR Corp., 45 F.3d 70 (4th  Cir.  1995).   Although
Pioneer  was  a case that arose under the bankruptcy rules, it  has
been applied beyond  the  context of bankruptcy to other situations
where  pertinent rules contain  the  same  standard  of  "excusable
neglect".   U.S.  v.  Hooper, supra at 259; U.S. v. Clark, supra at
44; Reynold v. Wagner,  supra  at  1429;  Information  Systems  and
Networks Corp. v. U.S., supra at 796.

      Applying the criteria of Pioneer, I find first that there 
will be no prejudice to the Secretary if the operator is allowed
to proceed on the merits. There has been no allegation that the
delay which  occurred  here  will  hinder the Secretary in  the
presentation of his case on the merits.   In addition, a trial
on  the  merits  is always favored over default.   Information
Systems and Networks  Corp.  v.  U.S., supra at 795.  The fact
that the operator was not represented  by  counsel  is another
factor  to  be  taken  into account.  As described above,  the
operator's engineer testified how he treats citations, notices
of proposed assessments,  and  requests  for hearing.  I found
him  truthful  and  credible.  His methods were  sensible  and
obviously undertaken  in  good  faith.   That  he  was  in the
process  of  computerizing  his records and that there were  a
large  number  of  cases  going  back  to  1993  are  relevant
circumstances.  Most importantly,  this  is the only time this
small operator has been out of time in requesting  a  hearing.
Nor  do  I  believe  reopening  this case will have an adverse
impact on Commission proceedings  given  the circumstances and
the  short  delay  involved.  After balancing  all  the  above
factors and bearing  in  mind  the  Supreme Court's admonition
that  the  determination  of  what  sorts  of  negligence  are
excusable is at bottom an equitable one,  I  conclude that the
operator's  late filed hearing request should be  allowed  and
the case reopened.

     This conclusion is also consistent with Commission precedent.
In vacating defaults  and  remanding  cases  for  determination
whether reopening is warranted, the Commission  has repeatedly
reminded  its  Judges  that  default is a harsh remedy.   See,
e.g., A.H. Smith Stone Company, 11 FMSHRC 796, 798 (May 1989).
The Commission itself has ordered  a  case reopened under Rule
60(b)(1)  where the operator did not timely  file  an  appeal,
relying upon the fact that the operator was without benefit of
counsel.  C&B  Mining  Company,  15  FMSHRC  2096,  2097 (Oct.
1993).   In  its  remands  the  Commission has considered  the
absence of counsel in the forefront  of  relevant reasons that
could justify reopening.  Kelley Trucking  Company,  8  FMSHRC
1867,  1868  (Dec.  1986).   See also, CG&G Trucking, Inc., 15
FMSHRC 193 (Feb. 1993); Mustang  Fuels  Corporation, 13 FMSHRC
1061,  1062 (July 1991).  The Commission has  also  recognized
that an operator proceeding without counsel may be entitled to
relief when  serious personal problems are responsible for the
untimeliness.   James  D.  McMillen,  Employed  by  Shillelagh
Mining Company, 13 FMSHRC 778, 779 (May 1991).  The absence of
bad  faith  is  another  factor  which  should  be  taken into
account.  Kenneth Howard v. B & M Trucking, 11  FMSHRC  499,  
500 (April 1989). All the foregoing factors support a reopening
in the instant matter.

     It is clear that this case is an isolated instance where the
operator slipped up.  As appears  above,  I  have  excused  the
Secretary's  own  late  filing  in  the  companion case.   The
grounds here for operator relief are at the very least equally
persuasive as those advanced by the Secretary in the companion
case and in many other such cases where the Secretary seeks to
have  his  late  filings  allowed.   Salt  Lake   County  Road
Department,  3 FMSHRC 1714; Rhone-Poulenc of Wyoming  Company,
15 FMSHRC 2089  (Oct.  1993)  aff'd,  57  F.3rd 982 (10th Cir.
1995);  Roberts Brothers Coal Company, Inc.,  17  FMSHRC  1103
(June 1995);  Lone  Mountain  Processing,  Inc., 17 FMSHRC 839
(May 1995); Ibold Inc., 17 FMSHRC 843 (May 1995);  Long Branch
Energy,   16  FMSHRC  2192  (Oct.  1994);  Southmountain  Coal
Company, Inc.,  15  FMSHRC  2421  (Nov. 1993); Power Operating
Company Incorporated, 15 FMSHRC 931, (May 1993).

      The operator however, is cautioned  that  if  in the future
it should  be  late in filing the equities might not  be  in  its
favor.  The operator  is  now  on  notice  that  some  of  its
procedures, including mailing, need improvement.

      The parties have filed post-hearing briefs and statements. To
the  extent they are inconsistent with  this  decision,  they  are
rejected. The Solicitor appears unaware of Pioneer and the decisions
that follow it.

     In light of the foregoing, it is ORDERED  that  this case be
REOPENED.


   **FOOTNOTES**

     [1]:The  104  (a)  citation was paid and is not involved in
this case.


      It is further ORDERED  that  within  45 days of the receipt
of this order, the Solicitor file the penalty  petition  for this
case.


                               Paul Merlin
                               Chief Administrative Law Judge


Distribution: (Certified Mail)

Mark R. Malecki, Esq., Office  of the Solicitor,  U.S. Department
of Labor, 4015 Wilson Blvd., Suite 516, Arlington, VA 22203

Richard D. Cohelia,  Safety Director, R B Coal Co., Inc., Route 1,
Box 374, Evarts, KY 40828

Mr. David J. Partin, R B Coal Co., Inc., 8174 East Highway 72,
Pathfork, KY 40863

/gl