<DOC>
[DOCID: f:kt99182.wais]

 
LODESTAR ENERGY, INC.
February 28, 2000
KENT 99-182


        FEDERAL MINE SAFETY AND HEALTH REVIEW COMMISSION

               OFFICE OF ADMINISTRATIVE LAW JUDGES
                      2 Skyline, Suite 1000
                       5203 Leesburg Pike
                  Falls Church, Virginia 22041

                        February 28, 2000

SECRETARY OF LABOR,             :  CIVIL PENALTY PROCEEDINGS
     MINE SAFETY AND HEALTH     :
     ADMINISTRATION (MSHA),     :  Docket No.  KENT 99-182
               Petitioner       :  A. C. No.  15-13920-03925
          v.                    :
                                :  Docket No.  KENT 99-212
LODESTAR ENERGY, INC.,          :  A. C. No.  15-13920-03927
               Respondent       :
                                :  Wheatcroft Mine

                             DECISION

Appearances:  J. Phillip Giannikas, Esq., Office of the
              Solicitor, U.S. Department of Labor, Nashville,
              Tennessee;
              Richard M. Joiner, Esq., Mitchell, Joiner & 
              Hardesty, P.S.C., Madisonville, Kentucky, for 
              Respondent.

Before:       Judge Hodgdon

     These consolidated cases are before me on Petitions for
Assessment of Civil Penalty filed by the Secretary of Labor,
acting through her Mine Safety and Health Administration (MSHA),
against Lodestar Energy, Inc., pursuant to section 105 of the
Federal Mine Safety and Health Act of 1977,  30 U.S.C. � 815. 
The petitions allege two violations of the Secretary's mandatory
health and safety standards and seek penalties of $797.00.  A
hearing was held in Evansville, Indiana.  For the reasons set
forth below, I modify the two orders to citations and assess
penalties of $205.00.

                            Background

     The Wheatcroft Mine is an underground coal mine owned by
Lodestar Energy, Inc., and located in Webster County, Kentucky.
The mine is operated by Green Pond Energy Corporation under
contract with Lodestar.

     On November 24, 1998, MSHA Inspector Archie Coburn went to
the mine to conduct a quarterly inspection, customarily referred
to as a "Triple A" inspection.  He accompanied Lodestar Fire Boss
Dennis Marsili to examine the air courses and seals in the
inactive area of the mine.[1]  While they were crawling through
the cross-cut going toward the first seal of the No. 6 set of
seals, Marsili informed the inspector that the roof in that area
was getting heavy, that he had written in the mine book that
additional support was needed and that he had orally informed
Charlie Dame, the Safety Director for Green Pond, of the
situation.

     On hearing this, Inspector Coburn examined the area after he
got through it.  He observed that the roof was sagging six to
eight inches in various locations in an area that was
approximately 40 feet long and 20 feet wide.  When he got back to
the surface, the inspector checked the weekly examination book
which had the following entry for the previous week:

          Walked ret O/C[2] from #5 seals up to ret O/C
          0.1% 20.6%; across and down through #4 seals
          0% 20.7% 7:47 am/10:28 am 11-17-98.  No
          hazards observed.  DFM
          NOTE:  The top in x-cut in front of #1 seals
          #6 set, to next entry needs extra support -
          top getting heavy.  11-17-98  DFM

(Govt. Ex. 5 at 4.)  The initials DFM are Marsili's.

     Inspector Coburn then asked Jess O'Rourke, Green Pond
General Superintendent, when they were going to add support to
the area.  O'Rourke questioned Charlie Dame about the situation
and Dame advised him that he had told David Weinbarger, Lodestar
Mine Manager, and Kevin Vaughn, Lodestar Safety Director, about
the condition, but that Weinbarger was on vacation and nothing
had been done.

     Based on these facts, Inspector Coburn issued Order No.
4274546 alleging a violation of section 75.364(d) of the
Secretary's regulations, 30 C.F.R. � 75.364(d), because:

               The hazardous condition recorded in the
          mine book provided for weekly examination has
          not been corrected.  The examiner recorded in
          the mine book on 11/17/98 that additional
          roof support was needed in the entry outby
          the No. 1 seal in the No. 6 set of seals,
          that the top was getting heavy.  Several of
          Lodestar management were informed of the
          hazardous condition on 11/17/98.  As of
          11/24/98 no corrective action has been made.
          Some draw rock has already fallen in the
          area.

(Govt. Ex. 3.)

     On January 19, 1999, MSHA Inspector Robert Simms was
conducting a ventilation review at the Wheatcroft Mine.  While
going through the weekly examination books, he discovered
numerous record-keeping errors for which he issued citations not
involved in this proceeding.  He returned the following day to
examine the books more thoroughly.  In trying to match the areas
shown on the mine map with the notations in the examination
books, he discovered that entries were not being made for some
areas in the mine and that this had occurred for a period of
several weeks.

     As a consequence, Inspector Simms issued Order No. 4275621
charging a violation of section 75.364(h), 30 C.F.R. � 75.364(h),
in that:

               There is no record showing that the
          return air course has been traveled from the
          #2 seals to the #3 seal and from the #6 seal
          toward the #2 belt entry.  There is also no
          record showing that the Intake and Return of
          the Main North Parallels have been made.  At
          the completion of any shift during which a
          portion of a weekly examination is conducted,
          a record of the results of each weekly exam .
          . . shall be made.

(Govt. Ex. 6.) The order was subsequently modified to delete the
first sentence concerning the "#2 seals to the #3 seal" and "the
#6 seal toward the #2 belt entry."  (Id. at 2.)

     Order No. 4274546 makes up Docket No. KENT 99-182 and Order
No. 4275621 is found in Docket No. KENT 99-212.  Since the two
violations are not related, they will be discussed separately.

             Findings of Fact and Conclusions of Law

Order No. 4274546

      Section 75.364(d) provides, in pertinent part, that:
"Hazardous conditions shall be corrected immediately."  It is the
company's position that the sagging roof was not a "hazardous
condition."  I find that it was and that the company violated the
regulation by not adding additional roof support.

     At the hearing, everyone agreed that there is no way to know
when a sagging roof is going to fall.  It could fall sooner or
later, with later being months or years later.

     Marsili testified that his main concern was that if the roof
did fall it would affect ventilation, not that he would be caught
in the fall.  According to him, he did not consider this to be a
hazard, but was notifying management of the condition so they
could add the roof support and the ventilation system would not
be affected.[3]  Dame testified that based on Marsili's entry in
the examination book, and his discussion with Marsili, he was of
the same opinion.  On the other hand, Inspector Coburn testified
that the roof was hazardous because it could fall on a mine
examiner traveling through the area.

     Section 75.364(d) does not define the term "hazardous
condition."    Nonetheless, the Commission, in discussing the
same term concerning section 75.360(b), 30 C.F.R. � 75.360(b),[4]
noted that it had

          recognized in National Gypsum [Cement
          Division, National Gypsum Co., 3 FMSHRC 822
          (April 1981)] that, based on its dictionary
          definition, a "hazard" denotes a measure of
          danger to safety or health.  3 FMSHRC at 827
          & n.7.  The Commission has approved the
          definition of "hazard" as `a possible source
          of peril, danger, duress, or difficulty,' or
          `a condition that tends to create or increase
          the possibility of loss.'  Id. (citing
          Webster's Third New International Dictionary
          1041 (1971).

 Enlow Fork Mining Co., 19 FMSHRC 5, 14 (January 1997).

     While it may not have been likely that the roof would fall
on the examiner since he was only in the area once a week, it was
certainly a possibility.  Thus, it was a possible source of
peril, danger, duress or difficulty as well as a condition that
tended to create or increase the possibility of loss and,
therefore, involved a measure of danger to safety.  Consequently,
I conclude that the roof was a hazardous condition.

     The regulation requires that hazardous conditions be
corrected "immediately."  In this case, no one would be traveling
the area until the next week.  Accordingly, I find that for this
violation, "immediately" means before anyone is in the area
again.  Since no roof support had been added before Marsili and
the inspector went into the cross-cut, I conclude that the
company violated section 75.364(d).

     Unwarrantable Failure

     This order was issued under section 104(d)(2) of the Act, 30
U.S.C. � 814(d)(2).  That section provides that:

               If a withdrawal order with respect to
          any area in a coal or other mine has been
          issued pursuant to paragraph (1), a
          withdrawal order shall promptly be issued by
          an authorized representative of the Secretary
          who finds upon any subsequent inspection the
          existence in such mine of violations similar
          to those that resulted in the issuance of the
          withdrawal order under paragraph (1) until
          such time as an inspection of such mine
          discloses no similar violations.  Following
          an inspection of such mine which discloses no
          similar violations, the provisions of
          paragraph (1) shall again be applicable to
          that mine.[5]

     To establish that a violation comes within section
104(d)(2), the Secretary must prove three things:  "(1) a valid
underlying section 104(d)(1) withdrawal order; (2) a violation of
a mandatory safety or health standard caused by unwarrantable
failure; and (3) the absence of an intervening clean inspection."
Cyprus Cumberland Resources Corp., 21 FMSHRC 722, 725 (July 1999)
(citation omitted); Kitt Energy Corp., 6 FMSHRC 1596, 1600 (July
1984).  In this case, the Secretary did not present any evidence
concerning the absence of an intervening clean inspection.  Nor
is there any evidence in the record from which such a finding can
be inferred.  Consequently, I conclude that this violation does
not come within the purview of section 104(d)(2).

     The order will be modified accordingly.  In this regard, it
cannot be modified to a section 104(d)(1) order because there is
no evidence that this order was issued within 90 days of a
104(d)(1) citation.  Indeed, the assumption is that it was not
since in that case it should have originally been issued as a
104(d)(1) order rather than a 104(d)(2) order.  Nor can it be
modified to a 104(d)(1) citation inasmuch as the parties
stipulated that the violation was not "significant and
substantial."  (Tr. 14-15.)  Hence, it will be modified to a
104(a) citation, 30 U.S.C. � 814(a).

Order No. 4275621

     Section 75.364(h) requires, in pertinent part, that:  "At
the completion of any shift during which a portion of a weekly
examination is conducted, a record of the results of each weekly
examination, including a record of hazardous conditions found
during each examination and their locations, the corrective
action taken, and the results and location of air and methane
measurements, shall be made."  The Respondent argues that the
regulation was not violated.  I find that it was.

     After the order was modified, the only violation alleged is
that there was "no record showing that the Intake and Return of
the Main North Parallels have been made."  The parties agree that
the air courses had, in fact, been made.  Thus, this violation
is, as depicted by Inspector Simms, a "bookkeeping" violation.

     The company argues that because no hazardous conditions were
observed and no measurements of air and methane were required in
these areas, the examiner had not failed to follow the regulation
when he did not make any entry for the intake and return air
courses in the Main North Parallel.  However, the regulation
requires that the "results" of the examination be recorded.  The
fact that no hazardous conditions were observed is a result of
the examination.  Therefore, it should have been recorded.
Additionally, as Inspector Simms testified, making such an entry
allows someone reading the examination book to verify that the
required examinations were being performed.

     For these reasons, I conclude that the Respondent violated
section 75.364(h) when the examiner did not record the results of
his examination of the intake and return air ways in the Main
North Parallel.

     Unwarrantable Failure

     Like the previous order, this one was lodged under section
104(d)(2).  For the same reason that I found that the Secretary
did not demonstrate that the other order was properly issued
under that section, that there is no evidence of the absence of
an intervening clean inspection, I conclude that this order was
not properly issued under section 104(d)(2).  Accordingly, as
with the previous order, this violation will be modified to a
104(a) citation.

                     Civil Penalty Assessment

     The Secretary has proposed penalties of $797.00 for these
two violations.  However, it is the judge's independent
responsibility to determine the appropriate amount of penalty in
accordance with the six penalty criteria set out in section
110(i) of the Act, 30 U.S.C. � 820(i).  Sellersburg Stone Co. v.
FMSHRC, 736 F.2d 1147, 1151 (7th Cir. 1984); Wallace Brothers,
Inc., 18 FMSHRC 481, 483-84 (April 1996).

     In connection with the penalty criteria, the parties have
stipulated that a reasonable penalty will not affect the ability
of Lodestar to remain in business, that the Wheatcroft mine
produces 342,117 tons of coal per year and that Lodestar produces
9,387,053 tons of coal per year.  (Tr. 14.)  From this I conclude
that Lodestar's ability to remain in business will not be
adversely affected by the penalties in these cases and that the
mine is a medium size mine, while Lodestar is a large operator.

     Based on the company's Assessed Violation History Report and
the Proposed Assessment documents in this case, I find that
Lodestar has an average history of prior violations.  (Govt. Exs.
1 & 2.)  I further find from the evidence of record that the
company demonstrated good faith in attempting to achieve rapid
compliance after being notified of the violations.

     As previously noted, the parties stipulated that neither of
these violations were "significant and substantial."  (Tr. 14-
15.)  Therefore, I find that the gravity of these violations is
not very high.

     Finally, with regard to the negligence involved in these
violations, I find that the company was moderately negligent in
not adding roof support in the cross-cut before the No. 1 seal in
the No. 6 set of seals.  I make this finding based on the fact
that the violation was not S&S, that the area was only traveled
once a week, and that Marsili apparently indicated to the company
that the matter was not urgent.  I find that the negligence
involved in the bookkeeping violation was low in view of the
facts that the decision not to enter negative findings was not an
unreasonable interpretation of the regulation and that several
other inspectors had reviewed the examination books and had not
alerted the company to the deficiency.

     Taking all of these factors into consideration, I conclude
that a penalty of $150.00 is appropriate for Citation No.
4274546.  I find a penalty of $55.00 to be appropriate for
Citation No. 4275621.

                              Order

     Order No. 4274546 in Docket No. KENT 99-182 is MODIFIED to a
104(a) citation by deleting the "unwarrantable failure"
designation and by reducing the level of negligence from "high"
to "moderate," and is AFFIRMED as modified; Order No. 4275621 in
Docket No. KENT 99-212 is MODIFIED by deleting the "unwarrantable
failure" designation and reducing the level of negligence from
"high" to "low," and is AFFIRMED as modified.

     Lodestar Energy, Inc. is ORDERED TO PAY a civil penalty of
$205.00 within 30 days of the date of this decision.


                              T. Todd Hodgdon
                              Administrative Law Judge


Distribution:

J. Phillip Giannikas, Esq., Office of the Solicitor, U.S.
Department of Labor, 2002 Richard Jones Road, Suite B-201,
Nashville, TN 37215-2862 (Certified Mail)

Richard M. Joiner, Esq., Mitchell, Joiner & Hardesty, P.S.C., 
113 East Center Street, P.O. Box 659, Madisonville, KY 42431
(Certified Mail)

/nj


**FOOTNOTES**

     [1] The  responsibility for maintaining the inactive areas
was Lodestar's rather than Green Pond's.  (Tr. 123.)

     [2] O/C stands for "overcast."

     [3] I find  it  curious  that  Marsili  made  it a point of
informing  the inspector of the situation, if this was  his  only
concern.

     [4] 75.360(b)  states:  "The person conducting the preshift
examination shall examine for hazardous conditions . . . ."

     [5] Section 104(d)(1), 30 U.S.C. � 814(d)(1), states:

               If, upon  any  inspection  of  a coal or
          other  mine, an authorized representative  of
          the Secretary  finds  that  there  has been a
          violation  of any mandatory health or  safety
          standard, and  if  he  also finds that, while
          the conditions created by  such  violation do
          not cause imminent danger, such violation  is
          of  such  nature  as  could significantly and
          substantially contribute  to  the  cause  and
          effect  of  a  coal  or  other mine safety or
          health hazard, and if he finds such violation
          to be caused by an unwarrantable  failure  of
          such  operator  to comply with such mandatory
          health or safety  standards, he shall include
          such finding in any  citation  given  to  the
          operator under this Act.  If, during the same
          inspection  or  any  subsequent inspection of
          such mine within 90 days  after  the issuance
          of     such     citation,    an    authorized
          representative of the Secretary finds another
          violation of any  mandatory  health or safety
          standard and finds such violation  to be also
          caused  by  an unwarrantable failure of  such
          operator to so  comply,  he  shall  forthwith
          issue  an  order  requiring  the operator  to
          cause  all  persons in the area  affected  by
          such violation, except those persons referred
          to in subsection  (c)  to  be withdrawn from,
          and to be prohibited from entering, such area
          until  an  authorized representative  of  the
          Secretary determines  that such violation has
          been abated.