<DOC>
[DOCID: f:se2000100.wais]

 
U.S. STEEL MINING COMPANY, LLC
January 10, 2001
SE 2000-100


        FEDERAL MINE SAFETY AND HEALTH REVIEW COMMISSION

               OFFICE OF ADMINISTRATIVE LAW JUDGES
                      2 SKYLINE, 10th FLOOR
                       5203 LEESBURG PIKE
                  FALLS CHURCH, VIRGINIA  22041


                        January 10, 2001

SECRETARY OF LABOR,             : CIVIL PENALTY PROCEEDING
  MINE SAFETY AND HEALTH        :
  ADMINISTRATION (MSHA),        : Docket No. SE 2000-100
               Petitioner       : A.C. No. 01-00851-04075
          v.                    :
                                : Oak Grove Mine
U.S. STEEL MINING COMPANY, LLC, :
               Respondent       :

                             DECISION

Appearances: Terry G. Gaither, Conference and Litigation
             Representative, U.S. Department of Labor,
             Birmingham, Alabama, on behalf of Petitioner;
             Anthony F. Jeselnik, Esq., U.S. Steel, Law Department,
             Pittsburgh, Pennsylvania, on behalf of Respondent.

Before: Judge Zielinski

     This case is before me on a Petition for Assessment of Civil
Penalty filed by the Secretary of Labor against U.S. Steel Mining
Co., L.L.P., pursuant to section 105 of the Federal  Mine  Safety
and  Health  Act  of  1977  (the  "Act").   30 U.S.C. � 815.  The
petition alleges a single violation of the Secretary's  mandatory
health  and  safety  standards  and  proposes a civil penalty  of
$55.00.  A hearing was held in Hoover,  Alabama  on  October  14,
2000.   The  parties submitted post-hearing briefs on December 1,
2000, and reply briefs on December 22, 2000.  For the reasons set
forth below, I  affirm  the  citation  and  assess  a  penalty of
$55.00.

                The Evidence -- Findings of Fact

     On  July  14,  1999, Robert D. Norris, an inspector for  the
Secretary's  Mine  Safety   and   Health  Administration  (MSHA),
conducted an inspection of U.S. Steel's Oak Grove Mine.  At about
10:30 a.m., he issued Citation No. 7664934, for what he perceived
to be a violation of 30 C.F.R. � 75.206(a)(3)(i), which  requires  
that  roof supports "be  installed  to  within  5  feet  of  the  
uncut face."  His observations were described in the citation as 
follows:

          The 6-east set up section has two faces not bolted
     to within  5 feet of the un-cut face.  The left side of
     the #2 face  was  cut  5  feet  beyond  the right side,
     making  a  distance of 10 feet from the last  permanent
     roof bolts installed  to the face.  The crosscut turned
     from #3 to #2 was cut approximately  5  feet beyond the
     right side, making a distance of 7 feet from  the  last
     permanent  roof  bolt  installed to the face. (spelling
     and punctuation errors corrected)

     The citation was subsequently  amended to allege a violation
of 30 C.F.R. � 75.220(a)(1), i.e., that  the  operator had failed
to  follow  its  approved roof control plan, which  mirrored  the
essence  of  the initially  cited  regulation  by  specifying  in
diagrams that the distance between the centerline of the last row
of permanent roof  supports  and  the  face  "shall  not exceed 5
feet."  The diagrams in Respondent's roof control plan depicted a
typical  face  by use of a straight line at right angles  to  the
sides of the entry.   The  distance  between  that  line  and the
parallel  centerline  of  the  closest  row  of  roof  bolts  was
designated  as  "x" and a note specified that the "[d]istance `x'
shall not exceed  5  feet."  Neither the diagrams nor the text of
the plan specifically addressed  offsets  or  any  other  type of
irregularity in a face.

     The  entries  in the mine were 20-24 feet wide and crosscuts
were  20  feet  wide.    The   continuous   miner   makes  a  cut
approximately 12 feet wide and, consequently, extends an entry or
crosscut by making a series of cuts generally about 10  feet deep
alternating  between  the  left  and  right  side.   Under normal
circumstances,   both   sides   of   an  entry  will  be  cut  to
approximately  the  same  depth, and roof  bolts  can  easily  be
installed to within 5 feet  of  the  face.   Although there is no
requirement governing the time within which roof  bolts  must  be
installed,  promptly  bolting  to  within  5  feet of the face is
consistent  with  generally  accepted  mining  practice   because
allowing roof to go unsupported can result in sagging, making  it
more  difficult to support.  Ventilation problems can also result
because  miners  cannot  enter  an  unsupported  area  to  extend
ventilation  line  curtain.   In  addition,  the  area  cannot be
cleaned.

     Occasionally,  one  side  of an entry may not be cut to  the
same depth as the other, leaving  an  irregular  or  offset face.
Offsets  may  result  from  operator  error,  a breakdown of  the
continuous  miner,  a  shift change, or adverse roof  conditions.
Offsets should exist only  temporarily.   The respective sides of
the face should be at least roughly evened  out when the miner is
repaired, the subsequent shift begins production  or adverse roof
conditions  are properly addressed.  If roof bolts are  installed
while the offset  face condition exists, bolts may not be able to
be installed to within  five feet of the face.  Some roof bolting
machines, including those  used  by  Respondent, cannot enter the
narrower  cut  of  an  offset, which prevents  bolts  from  being
installed in the offset or deeper side of the face.

     The offset in the #2  entry  was  created  on July 12, 1999.
Roof bolts were installed to within approximately  5  feet of the
face on the right side, but were only within 10 feet of  the face
on  the  left  side.[1]   The  offset  in  the #3-#2 crosscut was
created  on  July  13,  1999,  when the continuous  miner  became
inoperable.  It was bolted during  the  evening shift on July 13,
1999.  Bolts were installed within approximately  2  feet  of the
right side of the face, but were 7 feet from the left side of the
face.[2]    Respondent's   Exhibit  1  (Exhibit  R-1)  accurately
depicted the conditions of the  faces  and roof bolts at the time
the citation was issued, 10:30 a.m., on July 14, 1999.

     MSHA's   acting  field  office  supervisor,   Kenneth   Ely,
recognizing that  there may be a legitimate reason why a face may
be temporarily offset  resulting  in bolts not being installed to
within  5  feet, testified that an inspector  should  attempt  to
ascertain the  reason  for the offset.  If the second side of the
cut was not made because a shift ended, for example, it should be
completed when the next  shift  engaged  in  production  of  coal
commences  work.   If due to a breakdown of the continuous miner,
the cut should be completed  when  production  resumes  after the
miner  is repaired.  If there is no viable excuse for failing  to
make the  cut to even out the face, and roof bolts, consequently,
are not installed within 5 feet of the deeper side of the face, a
citation should be written for the violation.

     Inspector  Norris did not undertake a detailed investigation
of the reasons for  the  offset faces in the areas cited.  He did
know,  however,  that  the continuous  mining  machine  had  been
inoperable about the time that the crosscut was being made, which
could explain the failure to bolt to within 5 feet of the face at
that location.  It would  not,  however,  explain  the failure to
even  the  face  in  the #2 entry and resultant failure  to  bolt
within  5  feet of the deeper  side  of  that  face.   He  placed
considerable  significance on the fact that there were two offset
faces, which indicated  to  him  that  no effort had been made to
even  out  the  faces  so  that  roof  bolts  could  be  properly
installed.

     Respondent called one witness, Phillip Sumpter.  Sumpter had
not  been  identified  as  a  witness on Respondent's  prehearing
report.  His testimony was intended  to  substitute  for  that of
Carl  Harless,  the  foreman  on the day shift on July 13 and 14,
1999, to explain the circumstances  surrounding the offset faces.
Harless had been listed as a witness on the prehearing statement,
but had been allowed to take vacation and was not present for the
hearing.   Sumpter was allowed to testify  over  the  Secretary's
objection on the condition that the Secretary could use testimony
given by Harless  in  a  previous  hearing to impeach Sumpter.[3]
Harless'  prior testimony regarding the  offset  faces  was  also
admitted as  substantive evidence during the Secretary's rebuttal
case.


     The record was  held  open  to  allow  submission of the 
parties' respective  designations  of  additional  portions   of  
Harless' testimony  deemed  necessary  to  place  the admitted 
portion in proper context.[4]

     Sumpter was a continuous miner coordinator,  and he observed
the continuous miner around 1:30 p.m. on July 13, 1999.   It  had
been  backed  out of the #3-#2 crosscut into the #3 entry and was
not capable of  mining due to a burst water hose and insufficient
hydraulic fluid because  of  a leak in the packing of a hydraulic
jack.   He arranged for the evening  shift  to install roof bolts
in the unfinished #3-#2 crosscut and for repairs  to  be  made to
the  continuous  miner.   The  repairs  were completed during the
midnight shift on the 14th and the miner  was  ready  to continue
mining  on  the  day  shift of the 14th.  By 10:30 a.m., however,
when the citation was written,  neither offset condition had been
corrected.  Subsequently, the crosscut was cut through and bolted
and a production cut was taken in  the  #2 entry, thereby abating
the violations.  Sumpter believed that the  conditions  cited  by
inspector  Norris  were  not  violations of the roof control plan
because bolts had been installed  within  5 feet of the shallower
side of the faces.  Sumpter believed that the offset in the #3-#2
crosscut  was  attributable to the breakdown  of  the  continuous
miner. He had no  explanation  for the existence of the offset in
the #2 entry.[5]

     Excerpts from the prior testimony  of  Carl Harless, the day
shift   foreman,  indicate  that  the  continuous  miner   became
inoperable due to leakage of hydraulic fluid around 10:30 a.m. on
July 13,  1999,  after  mining  the  #3-#2 crosscut to the offset
condition.  It was backed out of the crosscut  into the #3 entry,
which is where Sumpter saw it.  After Sumpter had  left the area,
however,  Harless  was able to temporarily restore the  miner  to
operation for the remainder  of the shift by adding 40 gallons of
hydraulic fluid.  Rather than  returning to the #3-#2 crosscut to
even off the face, he directed that cuts be made in the #4 entry.
The  reason  for doing so was because  he  could  claim  no  more
production if  he  evened  up  the crosscut face, but could if he
mined  in  the  #4  entry.   Since  he  was  rated  on  how  much
production, i.e., how many feet of entry  he  mined,  he chose to
get credit for more production, leaving the crosscut face offset.


     The  Secretary  contends  that  Respondent's  approved  roof
control  plan requires that permanent roof supports be  installed
to within  5 feet of the entire width of the face; that there was
no justification for creating or failing to eliminate the offsets
in the #2 entry  and  the  #3-#2  crosscut;  and,  the failure to
install  roof  bolts within 5 feet of the sides of the  faces  in
question  constitutes a violation of the roof control plan.

     Respondent contends that it cannot be found to have violated
its  roof control  plan  based  upon  a  condition  that  is  not
specifically  referred  to in the plan.  Alternatively, it argues
that bolts were placed as close as possible to the face under the
circumstances and, thus,  it should not be found to have violated
the provision.

                        Conclusions of Law

     I conclude that the conditions  observed by inspector Norris
violated   Respondent's  roof  control  plan.    There   was   no
justification  for  creation  of  the  offset  in entry #2 and no
justification  for  failing to correct the offset  in  the  #3-#2
crosscut once the continuous miner became temporarily operational
at the end of the day  shift  on  July  13, 1999.  Had the offset
faces been eliminated timely, roof bolts could, and likely would,
have been installed within 5 feet of the faces.

     The plan's depiction of the 5 foot minimum  distance between
the roof bolts and the face is clear and unambiguous.   The face,
the  exposed  surface  of  the  coal deposit in the working place
where mining is proceeding,[6] is  depicted  by use of a line and
the reference to the required 5 foot minimum distance between the
centerline of the closest row of roof bolts and the face, applies
to  each  point on that line, i.e., the entire surface  or  face.
Portions of the face that are further than
5 feet from  the  centerline of the nearest row of roof bolts are
not in compliance with  Respondent's roof control plan.  There is
no indication that the diagram  was  intended  to refer only to a
face  consisting  of  a  single  plane surface, no doubt  a  rare
occurrence  due to the difficulty of  precisely  controlling  the
depth of cuts  with  a  continuous mining machine.  The fact that
the plan contains no specific  reference  to, or depiction of, an
offset or irregular face, or that neither Respondent,  nor  MSHA,
sought  to  create  an exception in the plan for offsets or other
irregularities, cannot inure to Respondent's benefit.

     Respondent's argument, that there is no violation where roof
bolts have been installed  as  close  to the face as possible, is
also unavailing.  While it is true that  the roof bolting machine
used by Respondent could not enter the relatively narrow offsets,
those  conditions were created by Respondent.   As  found  above,
there was no justification for creation of the offset in the #2
entry and  there  was no justification for maintaining the offset
in  the  #3-#2 crosscut  after  the  continuous  miner  was  made
temporarily  operational  at the end of the day shift on July 13,
1999, prior to the installation  of  roof  bolts in the crosscut.
It  was,  therefore,  entirely  possible for Respondent  to  have
eliminated the offsets and bolted to within 5 feet of the faces.

                     The Appropriate Penalty

     Inspector  Norris  assessed the  probability  of  injury  as
"unlikely,"  the  operator's   negligence   as   "moderate"   and
determined   that   the   violation   was   not  significant  and
substantial.   The operator demonstrated good  faith  in  rapidly
abating the violation  within  the  time specified.  Accordingly,
the  violation  was assessed as a single  penalty  assessment  of
$55.00.  See, 30 C.F.R. � 100.4.  Respondent  i  a large business  
with  an apparently unremarkable  history of violations.  The 
proposed penalty  would not affect its  ability  to  continue  in  
business.   Having  no disagreement  with  Inspector  Norris'  
determinations,  and upon consideration of the factors in � 110(i)  
of the Act, I find  that  the  proposed  penalty  of  $55.00  is 
appropriate.

                              ORDER

     Based  upon   the  foregoing,  Citation  Number  7664934  is
Affirmed and Respondent  is  Ordered  to  pay  a civil penalty of
$55.00 within 30 days.


                                  Michael E. Zielinski
                                  Administrative Law Judge


Distribution:

Terry G. Gaither, Conference and Litigation Representative,  U.S.
Department  of  Labor, Mine Safety and Health Administration, 135
Gemini Circle, Suite 213, Birmingham, AL 35209 (Certified Mail)

Anthony F. Jeselnik,  Esq.,  U.S.  Steel,  Law  Dept., USX Tower,
Fifteenth   Floor,  600  Grant  St.,  Pittsburgh,  PA  15219-2749
(Certified Mail)

/mh


**FOOTNOTES**

     [1]: The  offset  in  the  #2 entry also was not cut to full
height, which also would have prevented  the installation of roof
bolts.

     [2]: Roof bolts cannot be installed within  2  feet  of  the
face  because they would be torn out by the continuous miner when
it started the next cut.

     [3]: Harless  had been called to testify on August 23, 2000,
at a hearing in a discrimination  case  brought  under  the  Act.
Secretary   o/b/o  McGill  v.  U.S.  Steel  Mining  Co.,  L.L.C.,
Commission Docket No. SE 2000-39-DM.

     [4]: On October 31, 2000, Respondent designated pages 350-75
of the transcript  of Harless' prior testimony as being necessary
to place the previously  admitted portions in proper context.  On
November 2, 2000, the Secretary  counter-designated  pages 340-49
and  369-403.   While  Respondent  objected  to admission of  the
testimony, neither party challenged the propriety  of the other's
designations.

     [5]: Sumpter  had  stated at one point in his testimony,  in
response to a question about  the  #2  entry, that the offset was
due to the continuous miner's breakdown.  However, that testimony
occurred while he was being questioned about  the  #3-#2 crosscut
and I find that his testimony was, in fact, in reference  to  the
#3-#2  crosscut.   On cross examination he was specifically asked
about the #2 entry and  clearly stated that he had no idea how or
why that offset came into existence.

     [6]: See, American Geological  Institute,  A  Dictionary  of
Mining, Mineral and Related Terms 198 (2d ed. 1996).