.
THUNDER BASIN COAL COMPANY
September 29, 1997
WEST 94-370


       FEDERAL MINE SAFETY AND HEALTH REVIEW COMMISSION

                  1730 K STREET, N.W. 6TH FLOOR

                   WASHINGTON D. C.  20006-3868


                        September 29, 1997

SECRETARY OF LABOR            :    CIVIL PENALTY PROCEEDING
     MINE SAFETY AND HEALTH   :
     ADMINISTRATION (MSHA),   :    Docket No.  WEST 94-370
               Petitioner     :    A . C. No. 48-00977-03525
                              :
          v.                  :
                              :    Black Thunder Mine
THUNDER BASIN COAL COMPANY,   :
               Respondent     :


                        DECISION ON REMAND

Before: Judge Merlin

     On  September 5, 1997, the Commission remanded this case for
a reassessment  of  civil penalties.  The parties have waived the
filing of briefs.

     A citation dated February 22, 1994, issued under section 104
(a) of the Mine Act charged  the  operator with a violation of 30
C.F.R.  �  40.4  for  refusing to post  a  form  designating  two
officials of the United  Mine  Workers  who were not employees of
the operator, as miner representatives under  section  103(f)  of
the  Mine  Act.[1]    The  abatement time allowed by the citation
was 15 minutes, and  an order under section 104(b) of the Act for
failure to abate was issued  on  the  same  day  as the citation.
However, MSHA did not begin to assess a daily penalty until March
27,  1994,  two  days  after  a  Commission judge had denied  the
operator's  request for temporary relief.   The  operator  sought
temporary relief  from  the  Commission  and  did  not  abate the
violation until 13 days later when the Commission denied relief.

     In  its  decision  the  Commission  found  that  the judge's
failure  to assess a penalty for the initial violation set  forth
in the citation  amounted  to  legal  error  that  necessitated a
remand.    Section  110(i)  of  the  Act,  30  U.S.C.  �  820(i),
identifies six  factors  which  must  be  taken  into  account in
determining  the  appropriate  amount of penalty.  Four of  these
factors are the subject of stipulations which have been  accepted
by the Commission.  Accordingly,  I  find  that  the  operator is
large  in  size,  imposition  of  a  penalty will not affect  its
ability  to  continue  in  business  and the  violation  was  non
serious.  I also find that the history of  violations for the two
years  preceding  issuance  of  the  citation   consisted  of  23
violations  and  no  violation  of  the  cited  regulation.   The
assessment sheet for the citation shows that the  operator had 32
inspection  days  in  the  two  year  period  and  less than  one
violation per inspection.  Considering the operator's  large size
this is a good history.

     The  record  shows  that  the  citation was given after  the
operator had requested issuance of a citation so that its refusal
to accept non employees as miner representatives could be adjudi-
cated and resolved.  As the Solicitor's  brief  to the Commission
acknowledges, in issuing the citation the Mine Safety  and Health
Administration was cooperating with the operator in attempting to
move  the  matter through the administrative and judicial  review
process as expeditiously  as  possible.   Clearly,  the  operator
knowingly and intentionally violated the Act by refusing to  post
the  names.   An  intentional  violation  usually  connotes  high
negligence.  However, in this instance the citation was issued as
a  result  of an agreement between the parties to obtain a prompt
ruling on the issue presented.  Under these limited circumstances
the operator's  degree  of  negligence  is  mitigated  and I find
negligence  was  moderate  with  respect to the issuance of   the
citation.

     The  remaining  factor  is  whether   or  not  the  operator
demonstrated good faith in attempting to achieve rapid compliance
after notification of the violation.  Abatement required only the
posting  of  the  designation.   The  15  minutes   allowed   was
sufficient  to  post  the names.  I find there  was no good faith
abatement.  The circumstances  relating  to  the failure to abate
are set forth more below in the analysis of the withdrawal order.

     Turning  to  the  withdrawal  order,  I  again   accept  the
stipulations of the parties and in accordance therewith find that
the operator was large in size, imposition of a penalty  will not
affect its ability to continue in business, the violation was non
serious and history of previous  violations was good.

     Evaluation  of negligence with respect to the order involves
circumstances very  different  from those attendant upon issuance
of the citation.  There is no dispute  that  the  operator  could
have  abated  within the time allowed.  However, it intentionally
chose not to do  so  and  instead  sought  temporary relief.  The
operator  knew from the outset that MSHA did  not  agree  to  its
refusal to  abate.   The MSHA district manager wrote the operator
that he intended to recommend  a  daily  penalty unless abatement
occurred  by  March 1, 1994.  However, the operator  pursued  its
application for  temporary  relief  which was denied on March 25,
1994, by a Commission judge.  Two days  after  the judge's denial
of  relief, the MSHA Director of Assessments wrote  the  operator
that  a  penalty  of  $2,000  per day was being imposed until the
violation was abated.  Nevertheless,  the  operator  appealed the
denial  of  temporary  relief  to the Commission.  Only when  the
Commission denied relief  thirteen  days  later  did the operator
abate.    Accordingly,  the  operator's  failure  to  abate   was
intentional  and  its  course  of conduct was taken with the full
knowledge that MSHA did not approve.

     There is no question that the operator had the right to seek
temporary relief  afforded  by  the  statute  and  regulations.
30  U.S.C.  � 815(b)(2), 29 C.F.R. � 2700.46.   However,  the
existence  of  that right does not mean  it can be exercised
without consequences, particularly when the course of action
selected  by  the   operator   poses  a  conflict  with  the
fundamental   statutory   scheme.   The   Mine   Act   vests
enforcement in the Secretary.   Thunder  Basin  Coal  Co. v.
Reich,  510 U.S. 200 (1994);  Mechanicsville Concrete, Inc.,
18 FMSHRC  877,  879 (June 1996).  Under Sections 104(b) and
110(b), 30 U.S.C.  �� 814(b), 820(b), the Secretary is given
the authority to set  times for abatement, determine whether
there  has  been  abatement,  issue  withdrawal  orders  and
propose civil penalties  to  obtain  abatement.   The use of
these  powers,  which  are  critical  to proper enforcement,
cannot be compromised or inhibited by an operator's decision
to  pursue  adjudicative  or  judicial  avenues  of  relief.
Otherwise, operators, and not the Secretary, will decide the
times and terms of enforcement.

     In  light of the foregoing, I conclude that  the  operator's
intentional  and  knowing  refusal to abate  constituted  high
negligence.  Eastern Associated  Coal  Corp., 13 FMSHRC 178,
187  (February  1991); Mettiki Coal Corporation,  13  FMSHRC
760, 770 (May 1991);  See  Also, Tanglewood Energy, Inc., 18
FMSHRC 1315, 1319-1320 (August  1996).   The  same consider-
ations compel the conclusion that the operator intentionally
and  knowingly  failed  to abate the violation in  a  timely
manner.

     I take careful note that  the  Secretary's  proposed penalty
 is $2,000 per day.  The Secretary's regulations  state  that
the  formula  used  to determine proposed penalty amounts is
based upon the six factors  of  section  110(i). 30 C.F.R. �
100.3.  Special assessments also take into  account  the six
factors.  30 C.F.R. � 100.5.  However, the Secretary is  not
required  to  explain how she arrives at a proposed penalty.
Therefore in this  case  there  is  no  way  to know how the
Secretary  viewed and weighed each of the six criteria.   30
U.S.C. � 820(i); See Also, Conf. Rep. No. 461, 95th Cong.,
1st Sess. 58,  reprinted  in  Senate  Subcommittee on Labor,
Committee  on  Human  Resources,  95th  Cong.   2nd   Sess.,
Legislative  History  of  the Federal Mine Safety and Health
Act of 1977, at 1336 (1978);  Redland  Genstar Incorporated,
19 FMSHRC 442, 446 (February 1997).

     In any event, it is well established that penalty proceedings
before the Commission and its judges are de novo and that the
Secretary's proposed penalties are not binding on the Commis-
sion and its judges.  Sellersburg Stone Company, 5 FMSHRC
287, 290-29 (March 1983),
aff'd, 736 F.2d 1147 (7th Cir. 1984); U.S. Steel Mining Co.,
6 FMSHRC 1148, 1150 (May 1984); Missouri Rock, Inc., 11
FMSHRC 136, 140 (February 1989); Doss Fork Coal Company,
18 FMSHRC 122, 130 (February 1996); Wallace Brothers Inc., 18
FMSHRC 481, 483-484
(April 1996);  Mechanicsville Concrete, Inc., 18 FMSHRC 877,
881 (June 1996).  As the Commission stated in its remand
order in this case, Commission judges are accorded broad
discretion in assessing penalties under the Act and these
assessments must reflect proper consideration of the six
criteria set forth in section 110 (i).

     As set forth herein, I have considered and made findings
with respect to the six criteria.  It is my reasoned
judgment that a penalty of $350 is an appropriate penalty
for the underlying violation.  I believe this amount is
consistent with lack of gravity, moderate negligence and
good history.  In addition, in reaching this amount I have
taken into account the operator's large size and ability to
continue in business.  Finally, I am cognizant of the
operator's failure to timely abate, a factor that also is
central to reaching an appropriate penalty amount for the
order.

     Upon a review of the six criteria it is my reasoned judgment
that a daily penalty of $1,000 per day is  suitable for the
violation cited in the 104(b) order.  In my view this amount
recognizes the non serious nature of the violation and the
operator's good prior history.  However, it also is premised
on the finding of  high negligence.  I further believe this
fine is consistent with the operator's large size and
ability to continue in business.  Finally, the failure to
timely abate after issuance of the order has been weighed in
the balance.  The substantial penalty being assessed is
sufficient to have the desired deterrent effect.

                              ORDER

     It is ORDERED that a penalty of $350 be assessed for
Citation No. 3589040.

     It is further ORDERED that a penalty of  $1,000 a day be
assessed for the operator's failure to comply with Order No.
3589101 for a total penalty of $13,000.

     It is further ORDERED that the operator pay these penalties
within 30 days of the date of this decision.
                            

                              Paul Merlin
                              Chief Administrative Law Judge


Distribution:(Certified Mail)

Colleen A. Geraghty, Esq., Office of the Solicitor, U. S.
Department of Labor, 4015 Wilson Boulevard, Suite 400, Arlington,
VA 22203

Margaret A. Miller, Esq., Office of the Solicitor, U. S.
Department of Labor, 1999 Broadway, Suite 1600, Denver, CO 80202-
5716

Thomas C. Means, Esq., Crowell & Moring, 1001 Pennsylvania
Avenue, N.W., Washington, DC 20004

Thomas F. Linn, Esq., Atlantic Richfield Company, 555 17th
Street, 20th Floor, Denver, Co 80202

/gl


**FOOTNOTES**

     [1]:The operator's argument that non employees  cannot serve
as a miner representatives was eventually rejected by  the  Court
of  Appeals  for  the  Tenth Circuit.  Thunder Basin v. Fed. Mine
Saf. and Health Rev. Com.,56 F.3d 1275 (1995).