<DOC>
[DOCID: f:wv200050.wais]

 
CONSOLIDATION COAL COMPANY
WEVA 2000-50
March 6, 2001


        FEDERAL MINE SAFETY AND HEALTH REVIEW COMMISSION

               OFFICE OF ADMINISTRATIVE LAW JUDGES
                      2 SKYLINE, Suite 1000
                       5203 LEESBURG PIKE
                  FALLS CHURCH, VIRGINIA  22041

                          March 6, 2001

SECRETARY OF LABOR,               : CIVIL PENALTY PROCEEDING
  MINE SAFETY AND HEALTH          :
  ADMINISTRATION (MSHA),          : Docket No. WEVA 2000-50
                      Petitioner  : A. C. No. 46-01318-04419
          v.                      :
                                  :
CONSOLIDATION COAL COMPANY,       :
               Respondent         : Robinson Run No. 95

                             DECISION

Appearances: Melonie J. McCall, Esq., Office of the Solicitor,
             U.S. Department of Labor, Arlington, Virginia, on
             behalf of Petitioner;
             Robert M. Vukas, Esq., Consolidation Coal Company,
             Pittsburgh, Pennsylvania, on behalf of Respondent.

Before: Judge Melick

     This case is before me upon  the  Petition for Civil Penalty
filed by the Secretary of Labor pursuant to Section 105(d) of the
Federal Mine Safety and Health Act of 1977,  30  U.S.C. � 801, et
seq. (1994), "the Act," charging the Consolidation  Coal  Company
(Consol)  with  one  violation  of  the  mandatory standard at 30
C.F.R. � 75.370(a)(1) and proposing a civil  penalty of $5,000.00
for  that  violation.  At hearings on November 14,  2000,  Consol
admitted  the  violation  as  alleged  and  challenged  only  the
Secretary's  "significant  and  substantial"  and  "unwarrantable
failure" findings.  The general issues before me then are whether
the violation was "significant and substantial," whether  it  was
the  result of the operator's "unwarrantable failure" and what is
the appropriate  civil  penalty  to be assessed for the violation
considering the criteria under Section 110(i) of the Act.

     The order at bar, number 4867384,  issued  October  6, 1999,
pursuant to Section 104(d)(2) of the Act, charges as follows:[1]
          The  currently  approved  mine ventilation plan is
     not being complied with on the 084-0 mmu, 13-0 Longwall
     section, in that only 435 fpm velocity  was measured at
     the   No.   10   shield   with  a  properly  calibrated
     anemometer.  This is the fourth  citation that has been
     issued  for inadequate air velocity  on  this  section.
     Citation   No.   7142544   was  issued  on  08/25/1999.
     Citation  No.  4866439  was issued  on  10/04/1999.   A
     methane/dust  face  ignition  occurred  on  09/16/1999.
     Citation  No. 7142156  was  issued  on  09/30/1999  for
     failure to  comply  with the applicable respirable dust
     standard.

     The cited standard requires  in  essence  that  the operator
follow  the  ventilation  plan  that  has  been  approved by  the
District  Manager for the Department of Labor's Mine  Safety  and
Health Administration  (MSHA).   In this case there is no dispute
that the relevant ventilation plan required that the air velocity
at the cited location be maintained  at  500 feet per minute (Jt.
Exh. No. 1 Para. 10).

     Gregory  Fetty  is  Chief  of  the Health  Section  in  MSHA
District  3.   On  October 6, 1999, he was  working  as  an  MSHA
inspector at the Robinson  Run  No.  95  Mine  for the purpose of
abating  a  September 30, 1999, excessive dust violation.   Fetty
took an air velocity  reading at the No. 10 shield and found only
440 feet per minute (fpm)  where  500  fpm  was  required  by the
ventilation  plan.[2] The  violation  was  abated  by  placing  a
curtain between the No. 1 shield  and  the headgate  rib  and  by
tightening the gob check curtain in the No. 3  entry (Gov't  Exh.
No. 1).

     The Secretary maintains  that the violation was "significant
and  substantial."   A  violation   is   properly  designated  as
"significant and substantial" if, based on  the  particular facts
surrounding that violation, there exists a reasonable  likelihood
that  the  hazard  contributed  to  will  result in an injury  or
illness  of  a  reasonably  serious  nature.   Cement   Division,
National Gypsum Co., 3 FMSHRC 822, 825 (April 1981).  In  Mathies
Coal   Co.,   6 FMSHRC   1,3-4  (January  1984),  the  Commission
explained:

          In  order  to establish  that  a  violation  of  a
     mandatory   safety    standard   is   significant   and
     substantial under National  Gypsum  the  Secretary must
     prove:   (1) the  underlying  violation of a  mandatory
     safety standard, (2) a discrete  safety  hazard -- that
     is, a measure of danger to safety -- contributed  to by
     the  violation,  (3)  a  reasonable likelihood that the
     hazard contributed to will  result  in  an  injury, and
     (4) a reasonable likelihood that the injury in question
     will be of a reasonably serious nature.

     See also Austin Power Inc. v. Secretary, 861 F.2d 99, 103-04
(5th  Cir.  1988),  aff'g  9  FMSHRC  2015, 2021 (December  1987)
(approving Mathies criteria).

     The  third  element  of  the Mathies formula  requires  that
the Secretary  establish  a  reasonable   likelihood   that   the
hazard contributed  to  will  result  in  an event in which there
is an injury (U.S. Steel Mining Co., 6 FMSHRC  1834, 1836 (August
1984)).  The likelihood of such injury must be evaluated in terms
of continued normal mining operations without any  assumptions as
to abatement.  U.S. Steel Mining Co., Inc., 6 FMSHRC  1573,  1574
(July  1984);  See  also  Halfway,  Inc., 8 FMSHRC 8, 12 (January
1986) and Southern Ohio Coal Co.,
13 FMSHRC 912, 916-17 (June 1991).

     According  to  Inspector Fetty, several  health  and  safety
hazards were presented  by  the  violation at issue including the
inhalation of excessive respirable  dust  contributing  to  black
lung  disease  and  the  contribution  to  a  fire  or  explosion
resulting  from  a  face  ignition  because methane would not  be
promptly removed from the longwall face.   Fetty  opined that, in
the  latter cases, fatal injuries were reasonably likely.   Fetty
also noted  that  the subject mine was under the "Section 103(i)"
gassy mine spot inspection  program  involving  mines  liberating
more  than  1,000,000  cubic feet of methane in a 24-hour period.
He also noted that there  had  been  an ignition on September 16,
1999, on the same 13D longwall face.   Within  this  framework of
evidence  and  the reasonable inferences to be made therefrom,  I
conclude  that  indeed,   the   violation  was  "significant  and
substantial" and of high gravity.

     In reaching this conclusion  I have not disregarded Consol's
argument that, because the violation  was  quickly abated, it was
short  lived  and therefore, the hazard, if any,  was  minimized.
However, under present law, in determining whether a violation is
"significant and  substantial"   the likelihood of an injury must
be  evaluated  in  terms of continued  normal  mining  operations
without any assumptions  as  to abatement, U.S. Steel Mining Co.,
Inc., 6 FMSHRC at 1574.  Consol  also  appears  to argue that the
Secretary failed to prove that this violation "would  necessarily
lead  to  an  explosion,  a  fire  or black lung."  As previously
noted, however, the correct standard  of proof requires only that
the  Secretary  establish  by direct evidence  or  by  reasonable
inference a reasonable likelihood  that the hazard contributed to
will result in an event in which there  is  an injury or illness.
U.S. Steel Mining Co., at 1836.  That standard  of proof has been
met herein.

     The Secretary also argues that the violation  was the result
of Consol's "unwarrantable failure" and high negligence.  In this
regard the Secretary argues that prior violations for  inadequate
ventilation were issued at the same location on August 25, August
30,  1999,  and,  on  September  30, 1999 (Gov't Exhs. No. 3  and
4).[3]   The  Secretary  also argues  that  Inspector  Fetty  had
discussed with the operator  at  a closeout conference on October
4,   the   importance   of   compliance  with   the   ventilation
requirements.  The Secretary also  alleged  but  failed  to prove
that  the  anemometer  utilized  by  the  section foreman was not
properly calibrated and that he was not using  any  correction or
error  factor  in  calculating  air velocity.  Fetty acknowledged
however, that he did not know how  the  section  foreman actually
took   his   air  readings  for  compliance  purposes.   Finally,
Inspector Fetty  testified  that he relied in part also upon what
he  apparently  believed was a  serious  deficiency  in  the  air
velocity,  i.e., 440  fpm  when  500  fpm  was  required  by  the
ventilation plan.

     In defense of the Secretary's allegations of  "unwarrantable
failure" and  high  negligence   Consol presented the reports for
the three pre-shift examinations preceding  the  issuance  of the
order  at  bar  performed  at the No. 10 shield.  The most recent
pre-shift examination prior to the issuance of the order showed a
reading of 605 (presumably feet  per minute) at the No. 10 shield
measured during the examination between  5:00 a.m. and 7:15 a.m.,
on  October  6,  1999  (Resp.'s  Exh.  No. 4).   The  examination
preceding that showed 612 (presumably feet per minute) at the No.
10 shield and the exam preceding that showed 730 (presumably feet
per  minute)  at the No. 10 shield.  In addition,  the  pre-shift
examination for  the  preceding  day,  October  5,  1999,  showed
readings  at  the  No.  10 shield of 700, 600 and 625 (presumably
feet per minute).  The uncontradicted  and  credible  record thus
shows that for  the  six  pre-shift  examinations  preceding  the
issuance of the order at bar the  air  measurements  at  the  No.
10 shield were well above the minimum required by the ventilation
plan.

     In further defense of the unwarrantable failure allegations,
Consol  cites  the  testimony  of  longwall  section foreman Gary
Graham that he obtained an air reading on October  6,  1999, only
five  or ten minutes before 9:00 a.m., and found 535 fpm  at  the
No. 10  shield.   Since the order at bar was issued at 9:05 a.m.,
it is apparent that Graham's readings were obtained only 10 to 15
minutes before inspector  Fetty found the air reading had dropped
to 440 fpm at the No. 10 shield.   Graham  also testified that it
required only five minutes to tighten the curtains  necessary  to
bring  the  air  readings up to the requisite level.  Graham also
observed that the  curtains  had been tight at that location when
he passed earlier around 9:00 that morning and noted that when he
later returned to that location  after  the order had been issued
he observed that the curtain had been torn  out  from  the  spad.
Graham opined that this could have been caused by someone passing
through  the  curtain  in  the  interim.  He noted that the other
curtain had been loosened by moving the shield.

     Longwall section foreman Graham's  testimony is not disputed
and  his  credibility  is  not otherwise challenged.   Under  the
circumstances I accord Graham's  testimony significant weight and
conclude that indeed he checked the  air  velocity  at the No. 10
shield only ten or fifteen minutes before the violative condition
was discovered by Fetty.  Fetty's lower and violative air reading
was   apparently   the   result  of  curtains  becoming  loosened
subsequent to their examination  by  Graham,  thereby causing the
decrease in ventilation.  Because of the extremely  brief  period
during  which  the  violative  condition  therefore  existed, the
permissible   air   reading  obtained  only  shortly  before  the
violation was discovered and the fact that the six preceding pre-
shift reports showed air readings well above the requisite level,
I  cannot  find  that  the  violation  herein  was  a  result  of
"unwarrantable failure" or high negligence.

     I do find however,  that  the  violation  was  the result of
moderate  negligence based on  Graham's admission that  they  had
been having  trouble  keeping  air  at the face for several weeks
before the order in this case was issued.   At  the  same  time I
also  note  that  the  mine foreman had instructed Graham to take
four to five readings per  shift  to  monitor the problem.  Under
all the circumstances the order at bar  must  be  modified  to  a
citation under Section 104(a) of the Act.

Civil Penalty

     Under  Section  110(i)  of  the Act, the Commission and  its
judges must consider the following criteria  in assessing a civil
penalty:   the  operator's  history  of previous violations,  the
appropriateness of such penalty to the  size  of  the business of
the  operator  charged,  whether the operator was negligent,  the
effect on the operator's ability  to  continue  in  business, the
gravity of the violation and the demonstrated good faith  of  the
person  charged  in  attempting to achieve rapid compliance after
notification of a violation.

     Gravity has been  found  to have been high and negligence to
have been moderate.  Respondent  has  a  significant  history  of
violations as shown by Gov't Exh. No. 10.  It has been stipulated
that  Consol  is a large mine operator.  There is no dispute that
Consol demonstrated  good  faith  in  attempting to achieve rapid
compliance  after  notification of the violation.   There  is  no
evidence that the penalty imposed herein would have any effect on
the operator's ability  to  continue  in  business.   Within this
framework  of  evidence I find that a civil penalty of $2,500.00,
is appropriate.

                              ORDER

     Order  No. 4867384 is hereby modified to a citation pursuant
to Section 104(a) of the  Act.   Consolidation  Coal  Company  is
hereby  directed  to  pay  a  civil penalty of $2,500.00, for the
violation charged in Citation 4867384  within 40 days of the date
of this decision.


                               Gary Melick
                               Administrative Law Judge


Distribution: (Certified Mail)

Melonie J. McCall, Esq., Office of the Solicitor, U.S. Department
of Labor, 4015 Wilson Blvd., Suite 400, Arlington, VA 22202

Robert   M.  Vukas,  Esq.,  Consolidation  Coal   Company,   1800
Washington Road, Pittsburgh, PA 15241

\mca


**FOOTNOTES**

     [1]: Section 104(d) provides as follows:

(1)  "If,   upon   any  inspection  of  a  coal  or  other  mine,
an authorized  representative   of   the   Secretary  finds  that
there has been   a   violation   of  any  mandatory   health   or
safety standard,   and  if  he  also  finds   that,   while   the
conditions created by   such  violation  do  not  cause  imminent
danger,   such   violation   is   of   such   nature   as   could
significantly and  substantially  contribute  to  the  cause  and
effect of a coal or  other  mine  safety or health hazard, and if
he finds such  violation  to  be  caused   by   an  unwarrantable
failure of such   operator   to   comply   with   such  mandatory
health or safety standards,   he   shall   include  such  finding
in any citation  given  to  the  operator under  this  Act.   If,
during the  same  inspection  or  any  subsequent  inspection  of
such mine within 90 days after the  issuance  of  such  citation,
an authorized  representative  of  the  Secretary  finds  another
violation   of   any mandatory  health  or  safety  standard  and
finds such  violation to  be  also  caused  by  an  unwarrantable
failure  of  such operator  to  so  comply,  he  shall  forthwith
issue an order  requiring  the  operator  to  cause  all  persons
in the area  affected  by  such  violation,  except those persons
referred  to  in  subsection  (c) to be withdrawn  from,  and  to
be prohibited  from  entering,  such  area  until  an  authorized
representative of the Secretary determines  that  such  violation
has been abated."


(2)  If a withdrawal order with respect to any area in a  coal or
other   mine  has  been  issued  pursuant  to  paragraph  (1),  a
withdrawal  order  shall  promptly  be  issued  by  an authorized
representative  of  the  Secretary  who finds upon any subsequent
inspection the existence in such mine  of  violations  similar to
those that resulted in the issuance of the withdrawal order under
paragraph  (1)  until  such  time  as  an inspection of such mine
discloses no similar violations.  Following an inspection of such
mine  which discloses no similar violations,  the  provisions  of
paragraph (1) shall again be applicable to that mine.

     [2]: The parties apparently agree that Inspector Fetty found
440 cfm not the 435 cfm alleged in the order at bar.

     [3]: At  hearing  the Secretary sought to amend the citation
at bar by also referencing  a charging document issued October 4,
1999, for a similar violation  of  inadequate  air  in  the cited
section.   However,  because the Secretary had failed to disclose
this information in a  timely  manner, the proposed amendment was
denied.  The admission of that charging  document was also barred
for purposes of establishing "unwarrantable  failure" because the
Secretary's failure to disclose her intended use of that document
in a timely manner.  In any event, even had that  prior  charging
document  been  admitted  and  considered, it would not have been
sufficient under all the circumstances  to  support  a finding of
unwarrantability or greater negligence than found herein.