FEDERAL MINE SAFETY AND HEALTH REVIEW COMMISSION

601 NEW JERSEY AVENUE, NW

SUITE 9500

WASHINGTON, DC 20001

November 18, 2011

SECRETARY OF LABOR, 

MINE SAFETY AND HEALTH 

ADMINISTRATION (MSHA) 

 

v.

 

STEYER FUEL MINING CO., INC.

:
:
:
:
:
:
:
:

Docket No. YORK 2011-245

A.C. No. 18-00761-248657

 

Docket No. YORK 2011-246

A.C. No. 18-00761-254061



BEFORE: Jordan, Chairman; Duffy, Young, Cohen, and Nakamura, Commissioners

ORDER


BY THE COMMISSION:


            This matter arises under the Federal Mine Safety and Health Act of 1977, 30 U.S.C. § 801 et seq. (2006) (“Mine Act”). On July 21, 2011, the Commission received from Steyer Fuel Mining Co., Inc. (“Steyer”) two motions seeking to reopen two penalty assessments that had become final orders of the Commission pursuant to section 105(a) of the Mine Act,  30 U.S.C. § 815(a). Footnote The Secretary does not oppose the requests to reopen.


            Under section 105(a) of the Mine Act, an operator who wishes to contest a proposed penalty must notify the Secretary of Labor no later than 30 days after receiving the proposed penalty assessment. If the operator fails to notify the Secretary, the proposed penalty assessment is deemed a final order of the Commission. 30 U.S.C. § 815(a).


            We have held, however, that in appropriate circumstances, we possess jurisdiction to reopen uncontested assessments that have become final Commission orders under section 105(a). Jim Walter Res., Inc., 15 FMSHRC 782, 786-89 (May 1993) (“JWR”). In evaluating requests to reopen final section 105(a) orders, the Commission has found guidance in Rule 60(b) of the Federal Rules of Civil Procedure under which, for example, a party could be entitled to relief from a final order of the Commission on the basis of mistake, inadvertence, or excusable neglect. See 29 C.F.R. § 2700.1(b) (“the Commission and its Judges shall be guided so far as practicable by the Federal Rules of Civil Procedure”); JWR, 15 FMSHRC at 787. We have also observed that default is a harsh remedy and that, if the defaulting party can make a showing of good cause for a failure to timely respond, the case may be reopened and appropriate proceedings on the merits permitted. See Coal Prep. Servs., Inc., 17 FMSHRC 1529, 1530 (Sept. 1995).


            Having reviewed Steyer’s requests and the Secretary’s responses, in the interests of justice, we hereby reopen this matter and remand it to the Chief Administrative Law Judge for further proceedings pursuant to the Mine Act and the Commission’s Procedural Rules, 29 C.F.R. Part 2700. Accordingly, consistent with Rule 28, the Secretary shall file a petition for assessment of penalty within 45 days of the date of this order. See 29 C.F.R. § 2700.28.




 

/s/ Mary Lu Jordan

Mary Lu Jordan, Chairman





/s/ Michael F. Duffy                                                            

 Michael F. Duffy, Commissioner





/s/Michael G. Young

Michael G. Young, Commissioner





/s/ Robert F. Cohen, Jr.

Robert F. Cohen, Jr., Commissioner





/s/ Patrick K. Nakamura                                                                               

 Patrick K. Nakamura, Commissioner

Distribution:


Rebecca S. Cato, Secretary/Treasurer

Steyer Fuel Mining Co., Inc.

P.O. Box 549

Dellsolow, WV 26531


W. Christian Schumann, Esq.

Office of the Solicitor

U.S. Department of Labor

1100 Wilson Blvd., Room 2220

Arlington, VA 22209-2296


Melanie Garris

Office of Civil Penalty Compliance

MSHA

U.S. Dept. Of Labor

1100 Wilson Blvd., 25th Floor

Arlington, VA 22209-3939


Chief Administrative Law Judge Robert J. Lesnick

Federal Mine Safety & Health Review Commission

601 New Jersey Avenue, N. W., Suite 9500

Washington, D.C. 20001-2021