FEDERAL MINE SAFETY AND HEALTH REVIEW COMMISSION

1331 PENNSYLVANIA AVENUE, NW, SUITE 520N

WASHINGTON, D.C. 20004-1710

July 30, 2013


SECRETARY OF LABOR,
MINE SAFETY AND HEALTH
ADMINISTRATION (MSHA)

v.

BODELL CONSTRUCTION COMPANY
:
:
:
:
:
:
:


Docket No. WEST 2013-538-M
A.C. No. 04-02542-309510 YUD


BEFORE: Jordan, Chairman; Young and Nakamura, Commissioners

ORDER


BY THE COMMISSION:


            This matter arises under the Federal Mine Safety and Health Act of 1977, 30 U.S.C. § 801 et seq. (2006) (“Mine Act”). On February 26, 2013, the Commission received from Bodell Construction Company (“Bodell”) a motion seeking to reopen a penalty assessment that had become a final order of the Commission pursuant to section 105(a) of the Mine Act, 30 U.S.C. § 815(a).


            Under section 105(a) of the Mine Act, an operator who wishes to contest a proposed penalty must notify the Secretary of Labor no later than 30 days after receiving the proposed penalty assessment. If the operator fails to notify the Secretary, the proposed penalty assessment is deemed a final order of the Commission. 30 U.S.C. § 815(a).


            We have held, however, that in appropriate circumstances, we possess jurisdiction to reopen uncontested assessments that have become final Commission orders under section 105(a). Jim Walter Res., Inc., 15 FMSHRC 782, 786-89 (May 1993) (“JWR”). In evaluating requests to reopen final section 105(a) orders, the Commission has found guidance in Rule 60(b) of the Federal Rules of Civil Procedure under which, for example, a party could be entitled to relief from a final order of the Commission on the basis of mistake, inadvertence, or excusable neglect. See 29 C.F.R. § 2700.1(b) (“the Commission and its Judges shall be guided so far as practicable by the Federal Rules of Civil Procedure”); JWR, 15 FMSHRC at 787. We have also observed that default is a harsh remedy and that, if the defaulting party can make a showing of good cause for a failure to timely respond, the case may be reopened and appropriate proceedings on the merits permitted. See Coal Prep. Servs., Inc., 17 FMSHRC 1529, 1530 (Sept. 1995).


            MSHA’s records indicate that the proposed assessment was delivered on December 26, 2012, and became a final order of the Commission on January 25, 2013. Bodell asserts that its counsel erroneously construed the proposed assessment as a “pleading” served by mail and that Bodell’s time to respond had been extended by five calendar days, and filed the contest on January 30. Bodell discovered the error after receiving a delinquency notice, dated February 6, 2013. The Secretary does not oppose the request to reopen, and urges the operator to take steps to ensure that future penalty contests are timely filed.


            Having reviewed Bodell’s request and the Secretary’s response, in the interest of justice, we hereby reopen this matter and remand it to the Chief Administrative Law Judge for further proceedings pursuant to the Mine Act and the Commission’s Procedural Rules, 29 C.F.R. Part 2700. Accordingly, consistent with Rule 28, the Secretary shall file a petition for assessment of penalty within 45 days of the date of this order. See 29 C.F.R. § 2700.28.





/s/ Mary Lu Jordan

Mary Lu Jordan, Commissioner




/s/ Michael G. Young

Michael G. Young, Commissioner



/s/ Patrick K. Nakamura

Patrick K. Nakamura, Commissioner



Distribution:


D. Ryan Robinson, Esq.

Bostwick & Price, P.C.

Walter Ctr., 16 Fl.

175 South Main St.

Salt Lake City, UT 84111

ryan@bostwickprice.com


W. Christian Schumann, Esq.

Office of the Solicitor

U.S. Department of Labor

1100 Wilson Blvd., Room 2220

Arlington, VA 22209-2296


Melanie Garris

Office of Civil Penalty Compliance

MSHA

U.S. Dept. Of Labor

1100 Wilson Blvd., 25th Floor

Arlington, VA 22209-3939


Chief Administrative Law Judge Robert J. Lesnick

Federal Mine Safety & Health Review Commission

1331 Pennsylvania Avenue, N. W., Suite 520N

Washington, D.C. 20004-1710