FEDERAL MINE SAFETY AND HEALTH REVIEW COMMISSION

1331 PENNSYLVANIA AVE., N.W., SUITE 520N

WASHINGTON, DC 20004-1710

 

SECRETARY OF LABOR

  MINE SAFETY AND HEALTH       

  ADMINISTRATION (MSHA)

 

                        v.

 

GREENBRIER MINERALS, LLC

 

 

 

 

Docket No. WEVA 2024-0163

A.C. No. 46-09319-590383

 

 

 

 

 

BEFORE: Jordan, Chair; Baker, and Marvit, Commissioners

           

ORDER

 

BY: Jordan, Chair, and Baker, Commissioner

                                                                                                                

            This matter arises under the Federal Mine Safety and Health Act of 1977, 30 U.S.C. § 801 et seq. (2018) (“Mine Act”). On February 1, 2024, the Commission received from Greenbrier Minerals, LLC (“Greenbrier”) a motion seeking to reopen a penalty assessment that had become a final order of the Commission pursuant to section 105(a) of the Mine Act, 30 U.S.C. § 815(a).

 

Under section 105(a) of the Mine Act, an operator who wishes to contest a proposed penalty must notify the Secretary of Labor no later than 30 days after receiving the proposed penalty assessment. If the operator fails to notify the Secretary, the proposed penalty assessment is deemed a final order of the Commission. 30 U.S.C. § 815(a).

 

            We have held, however, that in appropriate circumstances, we possess jurisdiction to reopen uncontested assessments that have become final Commission orders under section 105(a). Jim Walter Res., Inc., 15 FMSHRC 782, 786-89 (May 1993) (“JWR”). In evaluating requests to reopen final orders, the Commission has found guidance in Rule 60(b) of the Federal Rules of Civil Procedure, under which the Commission may relieve a party from a final order of the Commission on the basis of mistake, inadvertence, excusable neglect, or other reason justifying relief. See 29 C.F.R. § 2700.1(b) (“the Commission and its Judges shall be guided so far as practicable by the Federal Rules of Civil Procedure”); JWR, 15 FMSHRC at 787. We have also observed that default is a harsh remedy and that, if the defaulting party can make a showing of good cause for a failure to timely respond, the case may be reopened and appropriate proceedings on the merits permitted. See Coal Prep. Servs., Inc., 17 FMSHRC 1529, 1530 (Sept. 1995).

 

Records of the Department of Labor’s Mine Safety and Health Administration (“MSHA”) indicate that the proposed assessment was delivered on December 11, 2023, and became a final order of the Commission on January 10, 2024. The following day, Greenbrier filed its contest of the assessment. Greenbrier subsequently received a letter from MSHA informing Greenbrier that the contest for the assessment had been untimely filed. On January 12, 2023, MSHA received partial payment of the assessment.

 

 Greenbrier seeks to reopen the assessment so that it may contest three citations.[1] Greenbrier maintains that its safety specialist missed the deadline to submit the contest of the assessment due to excusable neglect and extraordinarily difficult circumstances, including being busier than normal, the passing of the Safety Manager’s mother, and being short-staffed. This resulted in the contest being filed one day after the deadline to contest the assessment. The Secretary of Labor does not oppose the request to reopen.

 

We note that the motion to reopen was timely filed. The Commission has previously held that “[m]otions to reopen received within 30 days of an operator’s receipt of its first notice from MSHA that it has failed to timely file a notice of contest will be presumptively considered as having been filed within a reasonable amount of time.” Highland Mining Co., 31 FMSHRC 1313, 1316-17 (Nov. 2009). Here, the motion to reopen was filed on February 1, 2024, within 30 days of the final order of January 10, 2024. Therefore, the motion to reopen was filed within a reasonable amount of time.

 

Having reviewed Greenbrier’s request and the Secretary’s response, we find that Greenbrier has demonstrated good cause for its failure to timely respond and acted in good faith by timely filing its request to reopen. In the interest of justice, we hereby reopen this matter and remand it to the Chief Administrative Law Judge for further proceedings pursuant to the Mine Act and the Commission’s Procedural Rules, 29 C.F.R. Part 2700. Accordingly, consistent with

Rule 28, the Secretary shall file a petition for assessment of penalty within 45 days of the date of this order. See 29 C.F.R. § 2700.28.

 

 

 

/s/ Mary Lu Jordan

                                                                                    Mary Lu Jordan, Chair

 

 

 

/s/ Timothy J. Baker

Timothy J. Baker, Commissioner

 

 

 

Commissioner Marvit, dissenting:

 

I write to disagree with the Majority in this case for the reasons set forth below.

 

In Explosive Contractors, 46 FMSHRC __, No. CENT 2024-0122 (Dec. 4, 2024), I dissented and explained that Congress did not grant the Commission the authority to reopen final orders under section 105(a) of the Mine Act. The Commission’s repeated invocation of Federal Rule of Civil Procedure 60(b) cannot overcome the statutory language. However, in Belt Tech, I explained in my concurrence that “the Act clearly states that to become a final order of the Commission, the operator must have received the notification from the Secretary.” 46 FMSHRC __, slip op. at 3, No. WEVA 2024-0036 (Dec. 5, 2024) (citing Hancock Materials, Inc., 31 FMSHRC 537 (May 2009)). Taken together, these opinions stand for the proposition that the Commission may not reopen final orders under its statutory grant, but an operator may proceed if it has not properly received a proposed order.

 

In the instant case, as the Majority recounts, the Commission’s order became final under the language of section 105(a). The Majority, however, votes to reopen the case. The Mine Act has not granted us authority to reconsider final orders of the Commission as I set out more fully in Explosive Contractors. To the contrary, it has limited our authority to do so. Therefore, I respectfully dissent and would deny reopening.

 

 

 

/s/ Moshe Z. Marvit

Moshe Z. Marvit, Commissioner

 

Distribution:

Lorna M. Waddell, Esq.

Dinsmore & Shohl, LLP

215 Don Knotts Blvd., Suite 310

Morgantown, WV 26501

lorna.waddell@dinsmore.com

 

Tom Canterbury

Manager of Safety

P.O. Box 446

Man, WV 25635

Tom.canterbury@coronadous.com

 

April Nelson, Esq.

Associate Solicitor

Office of the Solicitor

U.S. Department of Labor

Division of Mine Safety and Health

200 Constitution Avenue NW, Suite N4420 – N4430

Washington, DC 20210

Nelson.April@dol.gov

 

Emily Toler Scott, Esq.

Counsel for Appellate Litigation

Office of the Solicitor

U.S. Department of Labor

Division of Mine Safety and Health

200 Constitution Avenue NW, Suite N4420 – N4430

Washington, DC 20210

scott.emily.t@dol.gov

 

Melanie Garris
USDOL/MSHA, OAASEI/CPCO
201 12th Street South, Suite 401
Arlington, VA 22202
Garris.Melanie@DOL.GOV

 

Chief Administrative Law Judge Glynn F. Voisin

Office of the Chief Administrative Law Judge
Federal Mine Safety Health Review Commission
1331 Pennsylvania Avenue, NW Suite 520N
Washington, DC 20004-1710
GVoisin@fmshrc.gov



[1] The operator states that it is in the process of paying the full amount of the proposed assessment but maintains that any payment of these citations is made merely to avoid any potential delinquencies and does not waive its right to contest these three citations. Motion to Reopen, at 2 n.1. Commissioner Baker has previously stated that it is his position that the accidental payment of a civil penalty does not constitute excusable neglect. See, e.g., Omya, Inc., 45 FMSHRC 131 (Mar. 2023). However, in light of the operator’s explanation for its payment of the civil penalty, Commissioner Baker would determine that in the instant case payment was not the result of an inadequate or unreliable internal processing system.