FEDERAL MINE SAFETY AND HEALTH REVIEW COMMISSION

1331 PENNSYLVANIA AVE., N.W., SUITE 520N

WASHINGTON, DC 20004-1710

SECRETARY OF LABOR,

  MINE SAFETY AND HEALTH     

  ADMINISTRATION (MSHA)          

 

                        v.

 

REX COAL CO., INC.

:

:

:

:

:

:

:

 

 

 

Docket No. KENT 2019-0302

A.C. No. 15-18869-492763

 

 

 

 

BEFORE:  Rajkovich, Chairman; Althen and Traynor, Commissioners

ORDER

 

BY THE COMMISSION:

 

            This matter arises under the Federal Mine Safety and Health Act of 1977, 30 U.S.C. § 801 et seq. (2012) (“Mine Act”). On February 10, 2020, the Commission received from Rex Coal Co., Inc. (“Rex Coal”) a motion seeking to reopen a penalty assessment that had become a final order of the Commission pursuant to section 105(a) of the Mine Act, 30 U.S.C. § 815(a).

 

            Under section 105(a) of the Mine Act, an operator who wishes to contest a proposed penalty must notify the Secretary of Labor no later than 30 days after receiving the proposed penalty assessment. If the operator fails to notify the Secretary, the proposed penalty assessment is deemed a final order of the Commission. 30 U.S.C. § 815(a).

 

            We have held, however, that in appropriate circumstances, we possess jurisdiction to reopen uncontested assessments that have become final Commission orders under section 105(a). Jim Walter Res., Inc., 15 FMSHRC 782, 786-89 (May 1993) (“JWR”). In evaluating requests to reopen final orders, the Commission has found guidance in Rule 60(b) of the Federal Rules of Civil Procedure, under which the Commission may relieve a party from a final order of the Commission on the basis of mistake, inadvertence, excusable neglect, or other reason justifying relief. See 29 C.F.R. § 2700.1(b) (“the Commission and its Judges shall be guided so far as practicable by the Federal Rules of Civil Procedure”); JWR, 15 FMSHRC at 787. We have also observed that default is a harsh remedy and that, if the defaulting party can make a showing of good cause for a failure to timely respond, the case may be reopened and appropriate proceedings on the merits permitted. See Coal Prep. Servs., Inc., 17 FMSHRC 1529, 1530 (Sept. 1995).

 

            Records of the Department of Labor’s Mine Safety and Health Administration (“MSHA”) indicate that the proposed assessment in this docket was delivered on June 10, 2019, and became a final order of the Commission on July 10, 2019. In its motion to reopen, Rex Coal says that it had placed its notice of contest in the mailbox outside the local post office on July 10. The mail was not retrieved and postmarked until the next day, July 11.[1]   The Secretary does not oppose the request to reopen, but urges the operator to take steps to ensure that future penalty contests are timely filed.

 

            Having reviewed Rex Coal’s request and the Secretary’s response, we find that the motion sufficiently explains the failure to timely contest the assessment here as the result of inadvertence, mistake, and excusable neglect. In the interest of justice, we hereby reopen this matter and remand it to the Chief Administrative Law Judge for further proceedings pursuant to the Mine Act and the Commission’s Procedural Rules, 29 C.F.R. Part 2700.

 

 

 

/s/ Marco M. Rajkovich, Jr.

                                                            Marco M. Rajkovich, Jr., Chairman

 

 

 

                                                            /s/ William I. Althen

                                                            William I. Althen, Commissioner

 

 

 

                                                            /s/ Arthur R. Traynor, III

Arthur R. Traynor, III, Commissioner

 

 

Distribution (by e-mail):

Ronnie Brock

Representative for Rex Coal Co., Inc.

rbrock8@BellSouth.net

 

Archith Ramkumar, Esq.

Appellate Counsel

Office of the Solicitor

Division of Mine Safety and Health

Ramkumar.Archith@dol.gov

 

Chief Administrative Law Judge Glenn Voisin

Federal Mine Safety & Health Review Commission

GVoisin@fmshrc.gov

 

Melanie Garris

Office of Civil Penalty Compliance

Mine Safety and Health Administration

Garris.Melanie@DOL.GOV



[1] The record shows that the operator paid its uncontested penalties before the expiration of the contest deadline, on July 7.