FEDERAL MINE SAFETY AND HEALTH REVIEW COMMISSION

1331 PENNSYLVANIA AVE., N.W., SUITE 520N

WASHINGTON, DC 20004-1710

 

 

 

SECRETARY OF LABOR                                         :           Docket No. CENT 2020-0043

 MINE SAFETY AND HEALTH                               :           A.C. No. 23-00252-496351

 ADMINISTRATION (MSHA)                                  :

                                                                                    :           Docket No.: CENT 2020-0044

                        v.                                                         :           A.C. No. 23-01978-496352

                                                                                    :

BAILEY QUARRIES, INC.                                        :           Docket No.: CENT 2020-0045

                                                                                    :           A.C. No. 23-02219-498428

                                                                                    :

                                                                                    :

SECRETARY OF LABOR                                         :

 MINE SAFETY AND HEALTH                               :

 ADMINISTRATION (MSHA)                                  :

                                                                                    :

                        v.                                                         :

                                                                                    :           Docket No.: CENT 2020-0046

CARROLL COUNTY STONE, INC.                         :           A.C. No. 03-01232-498119

 

 

BEFORE: Traynor, Chair; Althen and Rajkovich, Commissioners

 

ORDER

 

BY THE COMMISSION:

 

            These matters arise under the Federal Mine Safety and Health Act of 1977, 30 U.S.C.

§ 801 et seq. (2018) (“Mine Act”). On December 6, 2019, the Commission received a motion from Michael Boardman on behalf of Bailey Quarries, Inc., and Carroll County Stone, Inc., seeking to reopen multiple penalty assessments that had become final orders of the Commission pursuant to section 105(a) of the Mine Act, 30 U.S.C. § 815(a).[1]

 

Under section 105(a) of the Mine Act, an operator who wishes to contest a proposed penalty must notify the Secretary of Labor no later than 30 days after receiving the proposed penalty assessment. If the operator fails to notify the Secretary, the proposed penalty assessment is deemed a final order of the Commission. 30 U.S.C. § 815(a).

 

We have held, however, that in appropriate circumstances, we possess jurisdiction to reopen uncontested assessments that have become final Commission orders under section 105(a). Jim Walter Res., Inc., 15 FMSHRC 782, 786-89 (May 1993) (“JWR”). In evaluating requests to

reopen final orders, the Commission has found guidance in Rule 60(b) of the Federal Rules of Civil Procedure, under which the Commission may relieve a party from a final order of the Commission on the basis of mistake, inadvertence, excusable neglect, or other reason justifying relief. See 29 C.F.R. § 2700.1(b) (“the Commission and its Judges shall be guided so far as practicable by the Federal Rules of Civil Procedure”); JWR, 15 FMSHRC at 787. We have also observed that default is a harsh remedy and that, if the defaulting party can make a showing of good cause for a failure to timely respond, the case may be reopened and appropriate proceedings on the merits permitted. See Coal Prep. Servs., Inc., 17 FMSHRC 1529, 1530 (Sept. 1995).

 

Records of the Department of Labor’s Mine Safety and Health Administration (“MSHA”) indicate that three of the proposed assessments were delivered on August 5, 2019, and thus became final orders of the Commission on September 4, 2019 (Docket Nos. CENT 2020-0043, CENT 2020-0044, CENT 2020-0046). A fourth proposed assessment was delivered on September 10, 2019 and became a final order on October 10, 2019 (Docket No. CENT 2020- 0045). The operator asserts that it mistakenly sent the notice of contests along with the payment of the other citations to MSHA’s address in St. Louis, Missouri.

 

The motion, however, does not make clear the relationship between Bailey Quarries and Carroll County Stone. Nor does the motion make clear the relationship between Mr. Boardman and the operators. If Mr. Boardman is an owner, partner, officer, employee of, or attorney for the operators, he is permitted to represent them pursuant to Commission Procedural Rule 3(b)(3) and 3(a). If not, he may be permitted to represent the operators with the permission of the Commission, pursuant to Commission Procedural Rule 3(b)(4).

 

The Secretary does not oppose the motions to reopen, but urges the operator to take all steps to ensure that all future penalty contests are sent to MSHA’s Civil Penalty Compliance Office at the address in Arlington, Virginia as stated in the proposed penalty assessment within 30 days of receipt.

 

            Having reviewed operator’s request and the Secretary’s response, we find that the operators have established that they failed to timely contest the assessments due to a mistake and in the interest of justice, we hereby reopen these matters conditionally. We direct either Mr. Boardman or the parties themselves to file a motion explaining the relationship between Bailey Quarries and Carroll County Stone, as well as their relationship to Mr. Boardman. If required by the nature of the relationship, the motion must also seek permission to have Mr. Boardman represent the operators in reopening the motions.[2]

 

               If the motion directed by this order is not filed within 30 days, our conditional grant of the motion to reopen will lapse and the motion to reopen will be deemed denied with prejudice. Unless the Secretary objects and demonstrates that permitting said representation would be improper, the motion will be granted and will apply retroactively to the date the original motion was filed.

 

 

 

                                                                                                         /s/ Arthur R. Traynor, III

                                                                                                         Arthur R. Traynor, III, Chair

 

 

 

                                                                                    /s/ William I. Althen

                                                                                    William I. Althen, Commissioner

 

 

 

                                                                                    /s/ Marco M. Rajkovich, Jr.

                                                                                    Marco M. Rajkovich, Jr., Commissioner

 

 

 

 

 

 

Distribution:

 

Michael Boardman

Baily Quarries

Carroll County Stone

PO Box 169

Berryville, AR 72616

board.m.j@sbcglobal.net

 

John M. McCracken, Esq.

Office of the Solicitor

Division of Mine Safety and Health

U.S. Department of Labor

201 12th Street South, Suite 401

Arlington, VA 22202-5452

McCracken.John.M@dol.gov

 

April Nelson, Esq.

Office of the Solicitor

U.S. Department of Labor

201 12th Street South, Suite 401

Arlington, VA 22202-5452

Nelson.April@dol.gov

 

Chief Administrative Law Judge Glynn Voisin

Federal Mine Safety & Health Review Commission

1331 Pennsylvania Avenue, NW

Suite 520N

Washington, DC 20004-1710

GVoisin@fmshrc.gov

 

Melanie Garris

Office of Civil Penalty Compliance

Mine Safety and Health Administration

201 12th Street South, Suite 401

Arlington, VA 22202-5452

Garris.Melanie@DOL.GOV



[1] For the limited purpose of addressing the motions to reopen, we hereby grant the operator’s request to consolidate these captioned dockets. 29 C.F.R. § 2700.12.

[2] As stated above, Mr. Boardman is permitted to represent the operators without seeking permission if he is an owner, partner, officer, or employee of the operators. Rule 3(b)(3). He is also permitted to represent any operator for which he is an attorney. Rule 3(a). If Mr. Boardman does not fall into any of these categories, he may file a motion seeking permission to represent any of the operators under Rule 3(b)(4). The motion should state the basis for his request, including basic information identifying his relationship to each operator and the basis for his request to represent each operator.