BY THE COMMISSION:
This matter arises under the Federal Mine Safety and Health Act of 1977, 30 U.S.C. § 801 et seq. (2018) (“Mine Act”). On July 13, 2021, the Commission received from JMAC Resources (“JMAC”) a motion seeking to reopen a penalty assessment that had become a final order of the Commission pursuant to section 105(a) of the Mine Act, 30 U.S.C. § 815(a).
Under section 105(a) of the Mine Act, an operator who wishes to contest a proposed penalty must notify the Secretary of Labor no later than 30 days after receiving the proposed penalty assessment. If the operator fails to notify the Secretary, the proposed penalty assessment is deemed a final order of the Commission. 30 U.S.C. § 815(a).
We have held, however, that in appropriate circumstances, we possess jurisdiction to reopen uncontested assessments that have become final Commission orders under section 105(a). Jim Walter Res., Inc., 15 FMSHRC 782, 786-89 (May 1993) (“JWR”). In evaluating requests to reopen final orders, the Commission has found guidance in Rule 60(b) of the Federal Rules of Civil Procedure, under which the Commission may relieve a party from a final order of the Commission on the basis of mistake, inadvertence, excusable neglect, or other reason justifying relief. See 29 C.F.R. § 2700.1(b) (“the Commission and its Judges shall be guided so far as practicable by the Federal Rules of Civil Procedure”); JWR, 15 FMSHRC at 787. We have also observed that default is a harsh remedy and that, if the defaulting party can make a showing of good cause for a failure to timely respond, the case may be reopened and appropriate proceedings on the merits permitted. See Coal Prep. Servs., Inc., 17 FMSHRC 1529, 1530 (Sept. 1995).
Records of the Department of Labor’s Mine Safety and Health Administration (“MSHA”) indicate that the proposed assessment was delivered on April 6, 2021, and became a final order of the Commission on May 6, 2021. JMAC asserts that the notice of contest was timely mailed on April 22, 2021, but was not received by MSHA because it was lost in the U.S. Postal system. JMAC notes that this was not the first instance of mail delivery issues, as receipt of the proposed assessment was also delayed. The Secretary does not oppose the request to reopen, but urges the operator to take steps to ensure that future penalty contests are timely filed.
Having reviewed JMAC’s request and the Secretary’s response, we find that the notice of contest inadvertently failed to reach MSHA due to mail delivery issues. In the interest of justice, we hereby reopen this matter and remand it to the Chief Administrative Law Judge for further proceedings pursuant to the Mine Act and the Commission’s Procedural Rules, 29 C.F.R. Part 2700. Accordingly, consistent with Rule 28, the Secretary shall file a petition for assessment of penalty within 45 days of the date of this order. See 29 C.F.R. § 2700.28.
/s/ Arthur R. Traynor, III
Arthur R. Traynor, III, Chair
/s/ William I. Althen
William I. Althen, Commissioner
/s/ Marco M. Rajkovich, Jr.
Marco M. Rajkovich, Jr., Commissioner
Distribution:
Terry Gadbaw
General Manager
JMAC Resources
3151 N. Beck Road
Post Falls, ID 58504
terryg@jmacresources.com
Emily Toler-Scott, Esq.
Office of the Solicitor
U.S. Department of Labor
201 12th St. South, Suite 401
Arlington, VA 22202-5450
Scott.Emily.T@dol.gov
Chief Administrative Law Judge Glenn Voisin
Federal Mine Safety & Health Review Commission
1331 Pennsylvania Ave. N.W., Suite 520N
Washington, DC 20004-1710
GVoisin@fmshrc.gov
Melanie Garris
Office of Civil Penalty Compliance
Mine Safety and Health Administration
U.S. Department of Labor
201 12th St. South, Suite 401
Arlington, VA 22202-5450
Garris.Melanie@dol.gov