SECRETARY OF LABOR,
MINE SAFETY AND HEALTH
ADMINISTRATION (MSHA)

v.

HIBBING TACONITE COMPANY

:
:
:
:
:
:
:




Docket No. LAKE 2006-152-M
A.C. No. 21-01600-60300

BEFORE: Duffy, Chairman; Jordan and Young, Commissioners



ORDER


BY THE COMMISSION: 


            This matter arises under the Federal Mine Safety and Health Act of 1977, 30 U.S.C. § 801 et seq. (2000) (“Mine Act”). On September 20, 2006, the Commission received from Hibbing Taconite Company (“HTC”) a motion by counsel seeking to reopen a penalty assessment that had become a final order of the Commission pursuant to section 105(a) of the Mine Act, 30 U.S.C. § 815(a).


            Under section 105(a) of the Mine Act, an operator who wishes to contest a proposed penalty must notify the Secretary of Labor no later than 30 days after receiving the proposed penalty assessment. If the operator fails to notify the Secretary, the proposed penalty assessment is deemed a final order of the Commission. 30 U.S.C. § 815(a).


            On June 28, 2005, the Department of Labor’s Mine Safety and Health Administration (“MSHA”) issued a proposed penalty assessment to HTC for two citations. HTC submitted payment for one, Citation No. 6175445, and allegedly indicated on the assessment form that it wished to contest the proposed penalty assessment for the other, Citation No. 6175063. HTC asserts that it intended to contest the penalty within the 30-day time period, and “it is unclear at this point on what date MSHA received the notification of contest.” In her response to HTC’s motion, the Secretary states that although she “has no record that the penalty contest form . . . was received by MSHA,” she further states that she “has no basis . . . for questioning that this form was sent to MSHA in a timely manner as asserted.” Accordingly, the Secretary does not oppose HTC’s motion to reopen.


            On the record before us, we are unable to determine whether HTC timely contested the proposed penalty assessment. If the company did so, the proposed assessment has not become a final order of the Commission and the company’s request for relief would be moot. DS Mine & Development LLC, 28 FMSHRC 462, 463 (July 2006). However, if HTC failed to timely contest the proposed assessment, we would not be able to grant the relief requested. Id. Under Rule 60(b) of the Federal Rules of Civil Procedure, Footnote any motion for relief from a final order must be made within a reasonable time, and in the case of mistake, inadvertence, or excusable neglect not more than one year after the order was entered. Fed. R. Civ. P. 60(b). Here, HTC has requested reopening of a proposed assessment more than one year after it became a final Commission order if the company did not file a timely contest. See J S Sand & Gravel, Inc., 26 FMSHRC 795, 796 (Oct. 2004) (denying request to reopen filed more than one year after penalty proposals had become final orders).


            Accordingly, we remand this matter to the Chief Administrative Law Judge for a determination of whether HTC timely contested the proposed penalty assessment at issue. If it is determined that the company did file a timely contest, the Chief Judge shall order further proceedings as appropriate pursuant to the Mine Act and the Commission’s Procedural Rules, 29 C.F.R. Part 2700. If it is determined that HTC failed to timely contest the proposed assessment, the Chief Judge shall dismiss this proceeding.

 





                                                                                    ____________________________________

                                                                                    Michael F. Duffy, Chairman





                                                                                    ____________________________________

                                                                                    Mary Lu Jordan, Commissioner





                                                                                    ____________________________________

                                                                                    Michael G. Young, Commissioner




Distribution


R. Henry Moore, Esq.

Jackson Kelly, PLLC

Three Gateway Center

401 Liberty Avenue, Suite 1340

Pittsburgh, PA 15222


W. Christian Schumann, Esq.

Office of the Solicitor

U.S. Department of Labor

1100 Wilson Blvd., 22nd Floor

Arlington, VA 22209-2296


Christine M. Kassak Smith, Esq.

Office of the Solicitor

U.S. Department of Labor

230 S. Dearborn St., 8th Floor

Chicago, IL 60604


Chief Administrative Law Judge Robert J. Lesnick

Federal Mine Safety & Health Review Commission

601 New Jersey Avenue, N.W., Suite 9500

Washington, D.C. 20001-2021