FEDERAL MINE SAFETY AND HEALTH REVIEW COMMISSION
601 NEW JERSEY AVENUE, NW
SUITE 9500
WASHINGTON, DC 20001
August 22, 2006
SECRETARY OF LABOR, MINE SAFETY AND HEALTH ADMINISTRATION, (MSHA), v. PLATEAU MINING CORPORATION |
: : : : : : : : |
Docket No. WEST 2002-207 WEST 2002-278 |
BEFORE: Duffy, Chairman; Jordan, Suboleski, and Young, Commissioners
DECISION
BY THE COMMISSION:
These civil penalty proceedings, arising under the Federal Mine Safety
and Health Act of 1977, 30 U.S.C. ' 801 et seq. (2000) (AMine Act@), concern two citations alleging
safety violations involving the ventilation system of the Willow Creek
Mine, operated by Plateau Mining Corporation (APlateau@). 25 FMSHRC 738 (Dec. 2003) (ALJ).
The Department of Labor=s Mine
Safety and Health Administration (AMSHA@) issued the citations following an
accident at the mine on July 31, 2000, which resulted in two fatalities
and numerous injuries to miners. Id. at 739-40. Administrative Law
Judge Richard Manning affirmed Citation No. 7143395 alleging that the
ventilation system was not functioning as required by 30 C.F.R.
' 75.334(b)(1),[1] and that the violation
was significant and substantial (AS&S@). Id. at 743-57. In
addition, the judge affirmed Citation No. 7143396 alleging that Plateau
had failed to comply with its ventilation plan in violation of 30 C.F.R.
' 75.370(a)(1)[2] but determined that the
violation was not S&S. Id. at 757-60. Plateau filed a petition
for discretionary review, challenging the judge=s findings that it violated sections
75.334(b)(1) and 75.370(a)(1) and that its violation of section
75.334(b)(1) was S&S. The Commission granted the operator=s petition. For the reasons that
follow, the judge=s
determination that Plateau violated section 75.370(a)(1) is reversed, and
the judge=s determination that
Plateau violated section 75.334(b)(1) stands as if affirmed.
I.
Factual and Procedural Background
Plateau, which was then a subsidiary of RAG American Coal, Inc., operated
the Willow Creek Mine, an underground coal mine in Carbon County, Utah,
until the mine was closed after the accident at issue in this case. 25
FMSHRC at 738. The mine had three operating sections: two continuous
miner sections, and the D-3 longwall panel, which was the third longwall
panel that had been developed at the mine. Id. A mine fire had
occurred on the D-1 panel, the first panel mined, on November 25, 1998,
after a roof fall in the worked-out area ignited methane. Id. at
740; Tr. 37-38. Unlike D-2, the D-3 panel would not be separated from the
previous panel by a solid barrier of coal. 25 FMSHRC at 740-41. Rather,
the D-3 panel immediately abutted the D-2 panel, which had been sealed
off after it had been mined. Id. at 739. MSHA granted Plateau=s petition for modification,
allowing Plateau to use a two-entry system to develop the D-3 panel
headgate entries.[3]
Id.; Tr. 139. The remaining one entry of the two headgate entries
that had been driven to develop the D-2 panel served as the sole tailgate
entry for the D-3 panel. Gov=t
Ex. 31, App. I.
Retreat longwall mining began on the D-3 longwall panel on July 17, 2000.
25 FMSHRC at 739; Jt. Ex. 1, Stip. 16. The face of the D-3 longwall panel
was 815 feet wide and the panel was projected to be about 4200 feet long.
25 FMSHRC at 739. Mining the D-3 panel presented a number of challenges
because of the amount of methane liberated, the depth of the cover over
the coal seam, and the resultant roof conditions, including the
occurrence of roof and rib bounces. Id. at 740-41. In addition,
mining released liquid hydrocarbons, which were roughly equivalent to 15%
gasoline, 35% kerosene, and 50% light lubrication oil. Id. at 739,
741. The ventilation plan for the D-3 panel had been given particular
attention by MSHA because of the difficult mining conditions at the mine
and the D-1 panel fire in 1998. Id. at 740.
On the D-3 panel, behind the rubble zone of the Agob,@ or the area that had been mined by
the longwall, two entries ran parallel along the width of the longwall
panel from headgate to tailgate. Id. at 741. These entries were
referred to as Asetup
rooms@ because they had been
used to set up the longwall when the D-3 panel was being prepared for
mining. Id. Once mining began, the setup room closest to the
longwall shields (the ANo.
1" or Aoutby@ setup room) became part of the
rubble zone.[4]
Id.; Tr. 45.
The panel was ventilated by a flow-through bleeder system with multiple
bleeder entries at the rear of the panel. Tr. 46. In a flow-through
bleeder system, air flows through the worked-out area into the bleeder
system, and the bleeder entries are separate from the worked-out area.
Id. A blowing fan installed on the surface forced approximately
850,000 cubic feet per minute (ACFM@) of air into the mine. Tr. 40.
Immediately behind the No. 2 setup room, the setup room farthest from the
longwall shields, there were two L-shaped crosscuts (referred to as Adoglegs@), one on the headgate side and one
on the tailgate side. 25 FMSHRC at 741; Gov=t Ex. 31, App. I. The headgate
dogleg connected the No. 1 headgate entry with the No. 2 setup room. 25
FMSHRC at 741; Tr. 45, 70. The tailgate dogleg connected the No. 2
tailgate entry with the No. 2 setup room. Gov=t Ex. 31, App. I. Behind the doglegs
and setup rooms was a block of coal. 25 FMSHRC at 741. Behind the block
of coal were three bleeder entries, which ran parallel to the longwall
face. Id. The No. 1 bleeder entry, farthest from the longwall
shields, was used to bring intake air to a sump pump at the back of the
bleeders.[5]
Id. The other two bleeder entries were return entries. Id.
The ventilation plan included three alternative methods for ventilating
the D-3 panel. Id. The approved method being used on July 31
ventilated the panel by forcing air across the longwall face from the
headgate to the tailgate. Id. Intake air was brought to the face
from the No. 2 entry of the headgate through the last open crosscut.
Id. After the air ventilated the face, it was coursed through the
tailgate inby toward the bleeder entries and passed through Measuring
Point Locations (AMPLs@) 7 and 8. Id. at 741-42. A
small amount of the intake air from the No. 2 entry of the headgate
entered the last open crosscut and was directed out through the No. 1
headgate entry, which was the belt entry. Id. at 742. Intake air
also traveled from the No. 2 headgate entry directly to the bleeders
through MPLs 5 and 6. Id. In addition, intake air traveled up the
No. 2 tailgate entry, joined with the air that had ventilated the face,
and then was coursed through MPLs 7 and 8. Id.
Intake air traveled through the gob area through various ventilation
pathways. Id.; Gov=t Ex.
3. Air flowed out of the rubble zone into the setup rooms, and then to
the tailgate side and through the regulators at MPLs 7 and 8. 25 FMSHRC
at 742. Intake air also entered the No. 1 setup room from the headgate
through a regulator at MPL 4, which was between the Nos. 1 and 2 headgate
entries. Id. Intake air traveled up the No. 1 headgate entry, inby
the longwall shields, through a hole in an undercast (sometimes referred
to in the transcript as an Aovercast@) built at the intersection of the
No. 1 entry with the No. 2 setup room, through the regulators at MPLs 7
and 8, and into the bleeder entries. Id. Air from the longwall
panel entered the bleeder entries at MPLs 5, 6, 7, and 8 and traveled
approximately 8,000 feet, where the bleeder air joined another split of
air just outby MPLs B1, B2 and B3.[6] 25 FMSHRC at 746 n.6, 749. MPL B1 was
designated as a measuring point under 30 C.F.R. ' 75.323(e).[7] Id. at 748, 749.
Seals were constructed to separate the Nos. 1 and 2 headgate entries once
the longwall retreated outby each crosscut. Id. at 742. The
ventilation system was not designed to course air from the headgate side
of the gob back into the headgate entries to the bleeders. Id.
This is because the headgate portion of the gob was the lowest elevation,
and methane, which is lighter than air, would tend to migrate to the
tailgate side of the gob. Id.
The approved plan also required the use of an automated atmospheric
monitoring system (AAMS@). Id. at 743. This system
was designed to provide instantaneous information about the mine=s ventilation system by giving
information on air velocities, as well as methane, oxygen, and carbon
monoxide levels. Id. AMS sensors were installed at MPL 1 (the
tailgate intake to the longwall), MPL 5 (the headgate No. 2 entry bleeder
connector regulator), MPL 6 (headgate No. 1 entry bleeder connector
regulator), MPL 7 (tailgate No. 2 entry bleeder connector regulator), MPL
8 (tailgate No. 1 entry bleeder connector regulator) and MPL B1 (D-1
tailgate No. 1 entry near the D Northeast Mains). Gov=t Ex. 31 at 21.
Plateau had an internal protocol which required certain actions when
various levels of methane were measured at designated locations. P. Ex.
15. When methane measured 4% at MPLs 7 and 8, the operator was to cease
longwall production. 25 FMSHRC at 746; P. Ex. 15; Gov=t Ex. 31 at 21. At 4.5% methane, the
mine was to be evacuated. 25 FMSHRC at 746; Gov=t Ex. 31 at 21; P. Ex. 15. When
methane measured 1.95% at MPL B1, the operator was to cease production
until methane levels decreased to 1.75%. Tr. 1052; Gov=t Ex. 31 at 21. If methane exceeded
2%, the operator was to Ashut
down and make corrections,@
while at 2.5%, the operator was to evacuate the mine. Tr. 1052.
On July 31, 2000, mining on the D-3 panel had progressed approximately
250 feet. 25 FMSHRC at 741. Plateau was expecting to intersect the first
gob vent borehole, which was designed to remove methane from the gob, in
approximately 100 feet. Id. at 742; Tr. 1005, 1057-58. At
approximately 10:14 p.m., the longwall de-energized as it approached the
tailgate on its third clean-up pass. 25 FMSHRC at 739. The crew
re-energized the longwall after 42 minutes at 10:56 p.m. Id. Later
that evening and into the following morning, a series of events in the
worked-out areas of the D-3 longwall panel resulted in numerous injuries
to miners, including two fatal injuries. Jt. Ex. 1, Stip. 17. The
operator and the Secretary of Labor differ in their explanations of the
events.
The Secretary believes that at 11:48 p.m., a relatively small roof fall
occurred on the headgate side of the gob, between the longwall face and
the setup rooms. 25 FMSHRC at 739. The fall ignited a small pocket of
methane and other gaseous hydrocarbons. Id. The flame traveled
inby to a small methane accumulation in the gob near the setup rooms,
which resulted in the first explosion. Id. The miners believed
that the forces they felt occurred because the gob experienced its first
major cave of the roof. Id. The first event disrupted ventilation
at the longwall, which prevented methane from being removed from the gob
through the bleeder entries. Id. As liquid hydrocarbons became
involved in the fire, two subsequent explosions occurred. Id.
After the second explosion, miners were ordered to evacuate. Id.
at 739. At approximately 12:17 a.m. on August 1, a fourth explosion
occurred. Id. at 740.
Plateau believes that at about 11:48 p.m., the shearer was stopped on the
headgate side of the face while Shield No. 1 was advanced. Id. At
that time, there was a significant cave of the roof in the gob.
Id. The large roof fall ignited hydrocarbons. P. Post-Hr=g Br. at 17. In addition, the roof
fall likely disrupted ventilation in the panel, which permitted methane
to come into contact with the hydrocarbon fire and caused the subsequent
explosions. Id. at 15; 25 FMSHRC at 740.
After an investigation, MSHA issued Citation No. 7143395 alleging a
violation of section 75.334(b)(1), Citation No. 7143396 alleging a
violation of section 75.370(a)(1), and other citations which are not the
subject of these proceedings. 25 FMSHRC at 738 n.1, 763. In Citation No.
7143395, the Secretary stated that the bleeder system=s effectiveness was impaired by a
limited mine ventilating potential, the configuration and distribution of
airflow in the bleeder system and worked-out areas, and temporary
controls installed within the worked-out area that restricted airflow.
Id. at 743; Gov=t Ex. 2.
The temporary controls that allegedly restricted airflow included check
curtains in the crosscuts between the setup rooms, a curtain in the
headgate dogleg, and the undercast in the intersection of the No. 1
headgate entry and the No. 2 setup room. 25 FMSHRC at 751. Citation No.
7143396 alleged that Plateau violated section 75.370(a)(1) because the
temporary controls were left intact after retreat mining commenced but
were not shown on the longwall start-up ventilation plan approved on July
7, 2000. Id. at 757; Gov=t Ex. 4. Plateau challenged Citation
Nos. 7143395 and 7143396, and the matter proceeded to hearing before
Judge Manning.
As to Citation No. 7143395, the judge determined that Plateau was not
controlling air passing through the gob so as to continuously dilute and
move methane-air mixtures and other gases from the gob into the bleeders
as required by section 75.334(b)(1). 25 FMSHRC at 745, 763. The judge
found that the Secretary failed to prove two of three reasons that she
argued demonstrated a violation of the standard, namely, that Plateau was
improperly distributing air through the gob (id. at 750-51), and
that temporary ventilation controls restricted air flow in the gob
(id. at 751-53). The judge determined, however, that the Secretary
proved a violation of section 75.334(b)(1) because the ventilation system
was overextended and could not handle the levels of methane liberated.
Id. at 751. In so concluding, the judge relied upon evidence that
methane levels increased (id. at 746-47), that the measuring point
under section 75.323(e) showed artificially low methane readings
(id. at 748-49), and that the accident was caused by the ignition
of a small pocket of methane-air mixture that had accumulated on the
headgate side of the rubble zone. Id. at 753-54. The judge further
concluded that the operator could violate section 75.334(b) even if it
complied with its ventilation plan, and that Plateau should have been on
notice that its bleeder system was not functioning properly on July 31.
Id. at 746. The judge held that the violation was S&S and
assessed a civil penalty of $25,000, the amount proposed by the
Secretary. Id. at 757, 763.
As to Citation No. 7143396, the judge determined that Plateau had
violated section 75.370(a)(1) by failing to comply with its ventilation
plan but determined that the violation was not S&S.[8] Id. at 758-60. In so
holding, the judge rejected the Secretary=s theory that two of the three
temporary ventilation controls, namely, the curtains in the setup rooms
and the curtain in the dogleg, violated Plateau=s ventilation plan. Id. at
758. However, he agreed that the undercast violated the ventilation plan
because it functioned as a regulator, and Plateau had failed to seek
modification of the plan to include the undercast. Id. at 759. The
judge assessed a penalty of $1,000 rather than the penalty of $20,000
proposed by the Secretary. Id. at 760, 763; Pet. for Assess. of
Pen.
II.
Disposition
A. Citation No. 7143396, Section 75.370(a)(1)[9]
Plateau argues that the judge erred in finding a violation of section
75.370(a)(1) because Plateau=s
ventilation plan did not depict the undercast. P. Br. at 30-33. It
asserts in part that there is no evidence that the undercast inhibited
airflow. Id. at 31. Plateau submits that the judge=s finding that the undercast should
have been shown in the ventilation plan as a regulator is also erroneous
because the undercast did not function as a regulator. Id. The
Secretary responds that the judge=s finding of violation should be
affirmed. S. Br. at 45-50.
Section 75.370(a)(1) provides in part that an Aoperator shall develop and follow a
ventilation plan approved by the district manager.@ 30 C.F.R. ' 75.370(a)(1). A ventilation
plan is required to specify the Alocation of ventilating devices such
as regulators, stoppings and bleeder connectors used to control air
movement through the worked-out area.@ 30 C.F.R.
' 75.334(c)(4); see
also 30 C.F.R. '
75.371(bb).
The undercast was located inby the longwall shields at the intersection
of the No. 1 headgate entry and the No. 2 setup room. 25 FMSHRC at 742;
Tr. 51, 70. The undercast was part of the approved ventilation plan
during longwall setup and continuous miner development in the D-3 panel
and was originally constructed to separate air coursing into the No. 2
setup room from air coursing over the undercast. Tr. 736, 1035-36; J. Ex.
3. The amended ventilation plan, which was approved on July 7, 2000 and
applied to the startup of longwall mining in the D-3 panel, did not
include the undercast. 25 FMSHRC at 758; S. Br. at 46; Tr. 110-12;
Gov=t Ex. 5; Jt. Ex. 1.
We conclude that the judge erred in determining that Plateau should have
sought to modify the July 7 ventilation plan to include the undercast as
a ventilation device used to control air movement through the worked-out
area. 25 FMSHRC at 759. It is undisputed that Plateau created a 3 by 4
foot hole in the undercast in order to allow water and air to travel
through the undercast.[10] Id. at 759; Tr. 496, 620, 1038-41. It
is also undisputed that MSHA=s
computer simulations showed that, as a statistical matter, the breached
undercast would have no significant effect on the movement of air through
the worked-out area.[11] Tr. 633-35, 638, 1184, 1321; Gov=t Exs. 28, 29. Moreover, it is
undisputed that the breached undercast no longer functioned as an
undercast to separate air courses. 25 FMSHRC at 759; Tr. 192, 496,
1041-42, 1267. Accordingly, the breached undercast no longer constituted
a Aventilating device[] . . .
used to control air movement through the worked-out area.@ 30 C.F.R. ' 75.334(c)(4).[12]
Furthermore, the judge erred in characterizing the breached undercast as
a regulator. 25 FMSHRC at 759. The Commission has recognized that the
term Aregulator@ means Aa door, of any size, located in a
stopping@ which Acan be opened or closed as
needed.@ VP-5 Mining
Co., 15 FMSHRC 1531, 1532 n.3 (Aug. 1993) (citing Am. Geological
Institute, Dictionary of Mining, Mineral, and Related Terms (ADMMRT@) 910 (1968); see also DMMRT
451 (2d ed. 1997) (ARegulators
are usually set in doors as adjustable, sliding partitions that can be
varied to the desired opening.@). The breached undercast had no
such capability of adjustment. In fact, during a ventilation technical
evaluation of the D-3 panel that took place on July 26, five days before
the accident, MSHA Field Office Supervisor Gene Ray took oxygen and
methane readings at the breached undercast without recognizing the
breached undercast as a regulator that should have been included in
Plateau=s ventilation plan. Tr.
487-88, 494-96, 865, 873, 875-76.
Accordingly, because the breached undercast did not function as a
ventilation device that controlled air through the worked-out area, we
reverse the judge=s
determination that Plateau violated section 75.370(a)(1) by failing to
seek modification of its plan to allow the breached undercast to remain
in place. We therefore vacate Citation No. 7143396 and the penalty
assessed by the judge.
B. Citation No. 7143395, Section 75.334(b)(1)
Plateau argues that its bleeder system complied with the requirements of
section 75.334(b)(1) and that the judge erred in finding a violation. P.
Br. at 13, 18-19. It maintains that the judge erred in interpreting the
standard to prohibit methane accumulations in a gob, and that the
judge=s conclusion that its
ventilation system was overextended is not supported by substantial
evidence. Id. at 13-30. Plateau asserts that the judge also erred
by relying upon a misinterpretation of section 75.323(e) and in
concluding that a violation of section 75.334(b)(1) could exist even if
the operator complied with its ventilation plan. Id. at 18-23, 26.
Finally, Plateau submits that section 75.334(b)(1) does not provide
criteria for determining the effectiveness of a bleeder system, and that
the judge=s finding that
Plateau knew or should have known that its system was not functioning
effectively was not supported by substantial evidence. Id. at 14,
24-25, 26.
The Secretary responds that the judge=s determination that Plateau
violated section 75.334(b)(1) should be affirmed. S. Br. at 50. She
states that the judge properly accepted her interpretation of the
standard that methane must not be allowed to accumulate in the gob, and
that such an interpretation is supported by the standard=s plain language, the legislative
history and purpose of the underlying statutory provision, and Commission
precedent. Id. at 14-23. The Secretary maintains that the judge
properly determined that a violation of section 75.334(b)(1) could exist
even if an operator were in compliance with its ventilation plan and that
the operator=s contrary
contention would render section 75.334 superfluous. Id. at 23-26.
She submits that the judge did not misinterpret, or even interpret,
section 75.323(e) and properly relied on the standard in determining that
the operator violated section 75.334(b)(1). Id. at 26-32. The
Secretary asserts that substantial evidence supports the judge=s findings that the operator
violated section 75.334(b)(1) and that the operator had notice that the
bleeder system was not functioning properly. Id. at 32-45.
Section 75.334, entitled, AWorked-out areas and areas where
pillars are being recovered,@
sets forth, in part, ventilation requirements for such areas, the
circumstances under which such areas must be sealed, and ventilation plan
requirements. 30 C.F.R. '
75.334. Section 75.334(b)(1) requires that during pillar recovery, a
bleeder system shall be used Ato control the air passing through
the area and to continuously dilute and move methane-air mixtures . . .
from the worked-out area away from active workings and into a return air
course or to the surface of the mine.@ 30 C.F.R. ' 75.334(b)(1). Section 75.334 is
derived from section 303(z)(2) of the Mine Act, 30 U.S.C. ' 863(z)(2). The purpose of
section 303(z)(2) of the Mine Act Ais to require bleeder systems
continuously to dilute, render harmless, and carry away methane
effectively within the bleeder system and to protect active workings from
the hazards of methane accumulations.@ RAG Cumberland Res., LP, 26
FMSHRC 639, 647 (Aug. 2004), aff=d sub nom.
Cumberland Coal Res., LP v. FMSHRC, No. 04-1427, 2005 WL 3804997
(D.C. Cir. Nov. 10, 2005) (unpublished).
The Commission has recognized that although section 75.334(b)(1) does not
literally set forth a requirement that a bleeder system shall function
effectively, such a requirement is implicit in the standard=s language and underlying purpose.
Id. Thus, consistent with its underlying statutory purpose, the
Commission has read section 75.334(b)(1) to require a bleeder system
Ato control air passing through
the area and continuously to dilute and move methane-air mixtures away
from active workings and into a return or to the surface in an effective
manner.@ Id. That is,
Aa bleeder system must
effectively ventilate the area within the bleeder system and protect
active workings from the hazards of methane accumulations.@ Id.
Section 75.334(b)(1) is broadly worded, and the concept of Aeffectiveness@ is a general one. As the Commission
has previously observed, however, A[m]any standards must be >simple and brief in order to be
broadly adaptable to myriad circumstances.=@ Alabama By-Products Corp., 4
FMSHRC 2128, 2130 (Dec. 1982), quoting Kerr-McGee Corp., 3 FMSHRC
2496, 2497 (Nov. 1981). Nevertheless, such broad standards must afford
reasonable notice of what is required or proscribed. Alabama
By-Products, 4 FMSHRC at 2129. When faced with a challenge that a
safety standard fails to provide adequate notice of prohibited or
required conduct, the Commission has applied an objective standard, the
Areasonably prudent person
test.@[13] BHP Minerals Int=l Inc., 18 FMSHRC
1342, 1345 (Aug. 1996). The appropriate test Ais not whether the operator had
explicit prior notice of a specific prohibition or requirement, but
whether a reasonably prudent person familiar with the mining industry and
the protective purposes of the standard would have recognized the
specific prohibition or requirement of the standard.@ Ideal Cement Co., 12 FMSHRC
2409, 2416 (Nov. 1990). The Commission has recognized that various
factors that bear upon what a reasonably prudent person would do include
accepted safety standards in the field, considerations unique to the
mining industry, and the circumstances at the operator=s mine. BHP, 18 FMSHRC at
1345.
Commissioners are evenly divided regarding whether the judge correctly
determined that Plateau violated section 75.334(b)(1). Commissioners
Jordan and Young would affirm the portion of the judge=s decision holding that Plateau
violated section 75.334(b)(1). Chairman Duffy and Commissioner Suboleski
would vacate the judge=s
determination of violation and remand for further proceedings. The effect
of the split decision is to allow the judge=s affirmation of Citation No.
7143395 and assessment of penalty to stand. See Pa. Elec. Co., 12
FMSHRC 1562, 1563-65 (Aug. 1990), aff=d on other grounds,
969 F.2d 1501 (3d Cir. 1992). The separate opinions of the Commissioners
follow.
III.
Separate Opinions of the Commissioners
Commissioner Young, in favor of affirming the judge=s determination that Plateau
violated section 75.334(b)(1):
A. Interplay between 30 C.F.R. ''75.370(a) and
75.334(b)
Although the Commission has determined that Plateau did not violate 30
C.F.R.
' 75.370(a)(1) by failing
to seek modification of its ventilation plan to incorporate the breached
undercast, I would reject Plateau=s assertion that such a holding
precludes the Commission from finding that Plateau violated section
75.334(b)(1).
Ventilation regulations and ventilation plan provisions were designed to
recognize that mine ventilation is a dynamic process. The provisions of
section 75.334 set forth a level of safety required at all mines, while
ventilation plan provisions specify precautions and practices applicable
to the particular conditions at a mine. 57 Fed. Reg. at 20,868, 20,900
(May 15, 1992). Such plan provisions are not limited to implementing the
substantive provisions of the Secretary=s ventilation regulations, but may
provide for protection in addition to the standards they implement.
See C.W. Mining Co., 18 FMSHRC 1740, 1745 (Oct. 1996) (stating
that roof control plan provisions are not limited to implementing
regulations).
The Commission has previously held that compliance with a mine=s roof or dust control plan does not
preclude a finding of violation of the underlying roof or dust control
regulations. See, e.g., Southern Ohio Coal Co., 10 FMSHRC 138,
140-41 (Feb. 1988) (concluding that compliance with an approved roof
control plan is not controlling for purposes of determining compliance
with roof control regulation); Utah Power & Light Co., 12
FMSHRC 965, 969 (May 1990), aff=d, 951 F.2d 292 (10th
Cir. 1991) (concluding that compliance with the terms of a dust control
plan does not preclude a finding that an operator violated the terms of a
dust control regulation). Similarly, an operator cannot avoid a finding
of violation of section 75.334(b)(1) by arguing that it was complying
with the provisions of its ventilation plan. Rather, an operator is
required to comply with ventilation plan provisions, which encompass
conditions specific to a mine, in addition to the more general
requirements of section 75.334, which establish a general baseline which
all mines must meet. Conditions in a mine may change unexpectedly so that
compliance with specific ventilation plan provisions may not necessarily
assure that the general protections imposed by ventilation regulations
are being met. Thus, an operator is required to address its bleeder
system if the bleeder system is not effectively controlling air though
the worked-out area as required by section 75.334, even if the operator
is complying with the terms of its ventilation plan. Tr. 698.
Accordingly, I would affirm the judge=s determination that an operator may
be found to have violated section 75.334(b)(1) even though it has not
violated its ventilation plan. 25 FMSHRC at 746.
B. Violation of section 75.334(b)(1)
1. Substantial evidence
I would affirm the judge=s
determination that Plateau violated section 75.334(b)(1). I find
substantial evidence in the record to support the judge=s conclusion that Plateau=s bleeder system failed to
effectively ventilate the worked-out area of the D-3 panel as required by
section 75.334(b)(1). In particular, as discussed below, in the context
of unusually challenging mining conditions, the mine ventilation system
was operating with a Alimited
mine ventilating potential,@
methane levels were increasing and had exceeded a regulatory limit at MPL
B1. Additionally, readings at MPL B1 were artificially low. The record
supports the judge=s conclusion
that the bleeder system was not adequate to overcome these challenges as
Plateau proceeded to increase production, and that the resultant
conditions led to an ignition, several explosions and multiple
fatalities.
The judge=s findings of fact
must be analyzed through the lens of the statutory substantial evidence
test. 30 U.S.C. ' 823(d)(2)(A)(ii)(I). Under
this test, the Commission may not Asubstitute a competing view of the
facts for the view [an] ALJ reasonably reached.@ Donovan ex rel. Chacon v. Phelps
Dodge Corp., 709 F.2d 86, 92 (D.C. Cir. 1983). The fact that evidence
in the record may support a position adverse to the judge=s decision is not determinative.
Rather, the Commission=s review
is statutorily limited to whether the judge=s findings of fact were supported by
A>such relevant evidence as a
reasonable mind might accept as adequate to support [the judge=s] conclusion.=@ See, e.g., Jim Walter Res.
Inc., 19 FMSHRC 1761, 1767 n.8 (Nov.1997) (citing Rochester &
Pittsburgh Coal Co., 11 FMSHRC 2159, 2163 (Nov. 1989)). The
Commission has recognized that it is for the judge in the first instance,
not the Commission on review, to make inferences and findings based on
record evidence. Harlan Cumberland Coal Co., 20 FMSHRC 1275, 1283
(Dec. 1998).
Mining the D-3 panel presented a number of extraordinary challenges.
Mining liberated large quantities of methane and released liquid
hydrocarbons, and the liquid hydrocarbons in turn created hydrocarbon
vapors. 25 FMSHRC at 739, 740-41. The depth of the ground cover over the
coal seam resulted in stresses during mining, such as roof and rib
bounces. Id. at 740-41. In addition, Plateau used a two-entry
system to develop the D-3 panel headgate entries. Id. at 739. A
two-entry system provides fewer entries through which air can flow than a
system with a greater number of entries. Tr. 62, 608-09, 1207. This
increases the demands placed on the available entries. Tr. 62; . This
combination of factors can compound the hazards in the mine. A little
more than two years prior to the subject accident, the mine had
experienced an explosion in the D-1 panel, which also used a two-entry
system, after a roof fall in the worked-out area ignited methane. 25
FMSHRC at 739; Tr. 37-38.
Ventilating the D-3 panel also presented challenges that had not
previously been experienced at the mine. The D-3 panel was the first
panel at the mine that would not be separated from the previous panel by
a solid barrier of coal. 25 FMSHRC at 740-41. Rather, the D-3 panel
immediately abutted the D-2 panel. Id. at 739. Because of this
design, the No. 2 headgate entry of the D-2 panel served as the sole
tailgate entry for the D-3 panel. Gov=t Ex. 31, App. I. The No. 1 tailgate
entry of the D-3 panel was sealed as part of the gob of the D-2 panel.
Id. The No. 1 entries of the D-1 and D-2 panels had not been
similarly sealed at the time that those panels had been mined. Tr. 1207.
Thus, as Plateau=s witness,
Robert Derick, an expert in ventilation and mine fires, testified, the
AD-3 was really the beginning
of the challenging future.@ Tr.
1207-08.[1]
Confronted by these difficult circumstances, it appears that there was a
Alimited mine ventilating
potential.@ Gov=t Ex. 2 (Citation No. 7143395); Tr.
106-07. Kerry Hales, Plateau=s
mine manager (Tr. 731-32) and Stephan Jones, one of the mine=s engineers (Tr. 769), agreed that
the mine fan was operating at capacity and that no additional air could
be added to the system. Tr. 762, 799. In addition, the regulators at MPLs
7 and 8, the point where all airflow left the gob and entered the No. 3
bleeder entry, were wide open. Tr. 606, 798-99. Thus, there was no
capacity to induce more airflow through those regulators. Tr. 606, 799.
Mine Manager Hales acknowledged that without the gob vent boreholes or
horizontal degassing system in place, the system had reached its maximum
capacity for methane dilution and dispersal.[2] Tr. 762.
It is also undisputed that in the days prior to the subject accident
methane liberation increased at the D-3 panel as longwall mining
increased. 25 FMSHRC at 746. On July 19, three days after mining began on
the panel, methane measured between 0.5% and 1% at MPLs 7 and 8. 25
FMSHRC at 746; Gov=t Ex. 31 at
27, Fig. 3. Between July 25 and 30, methane levels at MPLs 7 and 8
averaged around 1.5%, although levels reached 3% on July 24 at MPL 8. 25
FMSHRC at 746; Gov=t Ex. 31,
Fig. 3. On July 31, methane at MPL 7 was measured between 2.5 and 3.0%,
and was measured at 3.5% at MPL 8. Id.
Methane liberation also increased at MPLs B1, B2, and B3, the location
where airflow was measured from the D seam bleeders and the D-1 tailgate.
Gov=t Ex. 31 at 20, 27. On July
18 and 19, methane was measured at MPL B1, MPL B2 and MPL B3 at
approximately 2.5 million cubic feet per day (ACFD@). 25 FMSHRC at 747; Gov=t Ex. 31 at 27. On July 25 and 26,
2000, methane liberation was measured at approximately 6.34 million CFD,
and on July 31, methane liberation had increased to over 7 million CFD.
25 FMSHRC at 746-47; Gov=t Ex.
31 at 27.
There were also increased methane readings at MPL B1, the section
75.323(e) measuring point.[3] Gov=t Ex. 31, Fig. 3. On July 19,
methane at MPL B1 measured between 0.5% and 1.0%. Id. On July 21,
methane averaged between 1 and 1.5% at MPL B1. Id.; 25 FMSHRC at
746. On July 31, 2000, the action level at MPL B1 was exceeded on at
least 2 occasions. 25 FMSHRC at 748; Gov=t Ex. 31 at 21 and Fig. 3; Tr. 164,
1252; P. Br. at 24. The first exceedance occurred at approximately 2:48
a.m. and lasted 11 minutes, while the second exceedance occurred at 3:33
a.m. and lasted approximately 40 minutes. Tr. 164; Gov=t Ex. 31 at 21. It is undisputed
that, although both measurements exceeded the action level of 1.95%, one
measurement also exceeded the 2% limit set forth in section 75.323(e). 25
FMSHRC at 746; Gov=t Ex. 31,
Fig. 3; P. Br. at 19-20.
The judge credited the testimony of John Urosek, the chief of the
ventilation division in MSHA=s
Pittsburgh Safety and Health Technology Center (Tr. 533-34), that the
methane readings obtained at MPL B1 were artificially low as the result
of fresher air leaking into the system. 25 FMSHRC at 748. Urosek
testified that on July 31, methane at MPLs 7 and 8 averaged about 3%.
Id.; Tr. 598-99, 655. He stated that the methane measured was less
than 2% by the time the airflow reached MPL B1 because the airflow from
the worked-out area was diluted before it reached MPL B1. Tr. 599-601; 25
FMSHRC at 748. Urosek explained that there was a significant amount of
leakage between the No. 1 bleeder entry, which brought intake air to the
sump pump, and the No. 2 bleeder entry which carried air from the gob to
MPL B1. 25 FMSHRC at 748; Tr. 599-601, 641, 1370-74. I see no basis to
overturn the judge=s
credibility determination. See Farmer v. Island Creek Coal Co., 14
FMSHRC 1537, 1541 (Sept. 1992) (a judge=s determinations may not be
overturned lightly); Penn Allegh Coal Co., 3 FMSHRC 2767, 2770
(Dec. 1981) (a judge=s
credibility determinations are entitled to great weight).
The judge=s findings are also
supported by other substantial evidence in the record. MSHA Supervisory
and Special Investigator Gary Wirth estimated the amount of leakage to be
approximately 50,000 CFM. 25 FMSHRC at 748; Tr. 101; Gov=t Ex. 31 at 22. In addition, intake
air that came from the No. 2 headgate entry through MPLs 5 and 6 provided
a sweetener by entering the No. 3 bleeder entry without ventilating the
worked-out area. Tr. 48-50; 25 FMSHRC at 748. Wirth also testified that
the intake air that coursed up the No. 2 tailgate entry traveled through
MPLs 7 and 8 without ventilating the worked-out area, and thus provided a
sweetening effect. Tr. 81-84.
Based on the record, the judge found that if this sweetening effect had
not occurred, methane levels at the 75.323(e) measuring point would have
been above 2% on a fairly regular basis beginning on July 30. 25 FMSHRC
at 748; Tr. 50, 83, 100-01, 601-02. Urosek testified that after the
airflow traveled through MPLs 7 and 8, it was diluted to a range between
2.3 and 2.6%, and that if there had been no leakage, readings at MPL B1
would also have been between 2.3 and 2.6%.[4] 25 FMSHRC at 748; Tr. 599.
Monitoring the methane levels at a section 75.323(e) measuring point is
critical to evaluating the effectiveness of a bleeder system. 25 FMSHRC
at 748-49; Tr. 1370. As Urosek also testified, the readings at MPL B1
were critical to evaluating the effectiveness of the D-3 panel=s bleeder system because the amount
of methane at such locations indicates whether there is enough airflow in
the system. Id. He explained that more than 2% methane indicates
that the system needs to be changed and either needs more airflow or less
methane. Tr. 595, 652, 1370-71. Urosek stated that section 75.323(e)
measuring points are designed so that an operator can detect small
changes or trends of increasing methane and make changes and adjustments
before the 2% level is exceeded. Tr. 1389. He observed that, prior to the
accident, measurements at MPL B1 showed a trend of increasing methane
indicating that adjustments and changes needed to be made. Tr. 1389-90.
Plateau=s president, John
DeMichiei, acknowledged that if methane exceeded 2% at a 75.323(e)
evaluation point, the situation might reflect an inadequate bleeder
system and should be addressed. Tr. 1288. Plateau=s general manager at the mine,
Charles Burggraf, also acknowledged that if methane exceeded 2%, the mine
Awould have to shut down and
make corrections.@ Tr. 979,
1052. Of course, any correction would have required Plateau to
investigate the exceedance of the 2% methane level, an occurrence that
should have borne some urgency, given the increasing methane trend and
the challenging circumstances involved in mining the D-3 panel.
Nonetheless, it appears that Plateau did not take measures to investigate
the cause or effect of the exceedance of the 2% limit at MPL B1, or to
make adjustments to its system. Tr. 762, 802.
In fact, it appears that Plateau proceeded to accelerate production, as
planned, which could only increase, rather than decrease, methane levels.
It is undisputed that the liberation of methane spiked at times that
production was high and decreased during idle periods. 25 FMSHRC at 746;
Gov=t Ex. 31 at 28, Fig. 4; Tr.
89, 195. Mine Manager Hales and Mining Engineer Jones testified that
while the increasing trend in methane in late July had been noticed, the
only response that the mine could take, given that maximum ventilation
capacity had been reached, was to slow down or cease production. Tr. 762,
793, 802, 812. Nonetheless, Plateau increased production during the days
preceding the accident. Gov=t
Ex. 31, Fig. 4; Tr. 89-90, 98. Up until approximately July 30, production
averaged about four longwall passes per day shift and one to
one-and-a-half passes per evening shift. Tr. 89; Gov=t Ex. 31, Fig. 4. On July 30, there
were eight passes mined during the day shift and four passes during the
evening shift. Id. On July 31, there were six-and-a-half passes
mined during the day shift and, during the evening shift in which the
accident occurred, there were three-and-a-half passes mined. Id.
As the judge acknowledged, factors that must be considered in evaluating
the readings at MPL B1 include the approximately 8,000-foot distance
between MPL B1 and the point where ventilation from the gob entered the
bleeder entries, as well as significant leakage outby the gob. 25 FMSHRC
at 749. Such evidence does not make consideration of the readings at MPL
B1 erroneous, however. Rather, these facts reinforce the judge=s conclusion that Athe readings at MPL B1 gave a false
impression that Plateau=s
bleeder system was functioning properly when it actually was not.@ Id. That is, readings at MPL
B1 were a critical indicator that the bleeder system was ineffective
because actual methane levels at MPL B1 were likely to be higher than
those recorded at MPL B1 after dilution.[5]
As previously discussed, Plateau=s mining of the D-3 panel limited
the system=s ability to
effectively control and continuously dilute and move unanticipated
methane-air mixtures. The judge found that when an operator can no longer
continuously dilute and move methane from the gob, there is a high risk
that an explosive air-mixture will accumulate in the gob, and that such
an accumulation developed at the mine on July 31. 25 FMSHRC at 749.
I agree with the judge that the occurrence of the accident was an
additional factor establishing a violation of section 75.334(b)(1).
Id. at 753. The Commission has long recognized that the Afact of an accident . . . does not
by itself necessarily prove or disprove the existence of a
violation.@ Old Ben Coal
Co., 10 FMSHRC 1800, 1804 n.4 (Oct. 1982); Consolidation Coal
Co., 20 FMSHRC 227, 240 (Mar. 1998) (Commissioners Riley and
Verheggen), aff=d, 1999 WL 335777 (4th
Cir. 1999). However, the Commission has explained that even though a
standard may be violated regardless of whether an accident has occurred,
an accident may Asometimes shed
light on an unsafe situation that had escaped previous notice or
citation.@ Old Ben, 10
FMSHRC at 1804 n.4. Although an accumulation of methane may not, in and
of itself, establish a violation of section 75.334(b)(1), a small
explosive methane-air mixture near the rubble zone constitutes additional
evidence demonstrating that Plateau=s bleeder system was unable to
effectively control the methane-air mixtures and continuously dilute and
move such mixtures from the worked-out area away from the active
workings.
In sum, as methane levels were increasing and had exceeded the 2% limit
at MPL B1, the operation and evaluation of the mine ventilation system
was impeded both by a limited potential for effectively diluting and
dispersing the methane and by air flows which produced artificially low
readings at MPL B1. Given these challenging conditions at the mine, I
conclude that substantial evidence supports the judge=s determination that Plateau=s bleeder system was not effectively
ventilating the worked-out area of the D-3 panel as required by section
75.334(b)(1).
2. Notice
Substantial evidence in the record supports a determination that a
reasonably prudent person familiar with the mining industry and the
protective purposes of section 75.334(b)(1) would have recognized that
Plateau=s bleeder system failed
to control and continuously dilute and move methane-air mixtures from the
worked-out area away from active workings as required by the
standard.[6] A
reasonably prudent person, having knowledge of the circumstances of
Plateau=s mine, would know that
the mine was operating at its maximum ventilation capacity under
difficult mining conditions. Mine Manager Hales and Mining Engineer Jones
agreed that the mine fan was operating at capacity and that no additional
air could be added to the system, and that there was no further capacity
to induce more airflow through the regulators at MPLs 7 and 8. Tr. 606,
762, 799. Mine Manager Hales acknowledged that the system had reached its
maximum capacity for being able to dilute and carry away methane without
the gob vent boreholes or horizontal degassing system in place. Tr. 762.
Moreover, a reasonably prudent person, considering the standard=s requirement that a bleeder system
must effectively ventilate the area within the bleeder system and protect
active workings from the hazards of methane accumulations, would have
recognized a disruption in the effectiveness of the system. The
disruption was manifest in the increasing levels of methane and an
exceedance at the section 75.323(e) measuring point. Jones and Hale
testified that they were aware of an increasing trend in methane in late
July. Tr. 762, 793, 802, 812. Hales acknowledged that methane readings
Awere a little high,@ and that they had been Astruggling with it for a few days,
trying to reach the next gob vent borehole,@ and that reaching the borehole
would have alleviated the Amethane problem.@ Tr. 752-53. Hales testified that
the increasing trend in methane was of particular concern because the fan
was at full capacity. Tr. 762. Hales and Jones testified that the
operator=s only option was to
slow down or cease production to let the methane bleed off. Tr. 762, 812.
Nonetheless, even with this information, the operator increased
production and did not take the corrective action required. Tr. 88-90,
98, 106-07; Gov=t Ex. 31, Fig.
4. Given this evidence, I would reject Plateau=s assertion that it failed to
receive adequate notice that its bleeder system violated the requirements
of section 75.334(b)(1). P. Br. at 14, 24-25, 26.
3. Significant and substantial
A violation is S&S if, based on the particular facts surrounding the
violation, there exists a reasonable likelihood that the hazard
contributed to will result in an injury or illness of a reasonably
serious nature. See Cement Div., Nat=l Gypsum Co., 3 FMSHRC
822, 825 (Apr. 1981). In Mathies Coal Co., 6 FMSHRC 1 (Jan. 1984),
the Commission further explained:
In order to establish that a violation of a mandatory safety standard is
significant and substantial under National Gypsum, the Secretary
of Labor must prove: (1) the underlying violation of a mandatory safety
standard; (2) a discrete safety hazard C that is, a measure of danger to
safety C contributed to by the
violation; (3) a reasonable likelihood that the hazard contributed to
will result in an injury; and (4) a reasonable likelihood that the injury
in question will be of a reasonably serious nature.
Id. at 3-4 (footnote omitted); accord Buck Creek Coal, Inc. v.
MSHA, 52 F.3d 133, 135 (7th Cir. 1995); Austin Power, Inc. v.
Secretary of Labor, 861 F.2d 99, 103 (5th Cir. 1988) (approving
Mathies criteria).
I would reject Plateau=s
argument that its alleged violation of section 75.334(b)(1) is not
S&S because the events that occurred on July 31 were unlikely. PDR at
13 n.7; P. Br. at 12 n.8. In effect, Plateau is arguing that the judge
should have confined his consideration to whether an injury-producing
event was reasonably likely to occur during continued mining operations.
The A>operative time frame for
determining if a reasonable likelihood of injury exists includes
both the time that a violative condition existed prior to the
citation and the time that it would have existed if normal mining
operations had continued.=@ Bellefonte Lime Co., 20
FMSHRC 1250, 1255 (Nov. 1998) (quoting Rushton Mining Co., 11
FMSHRC 1432, 1435 (Aug. 1989)) (emphasis added); Elk Run Coal Co.,
27 FMSHRC 899, 905 (Dec. 2005). The conditions creating the potential for
injury occurred prior to the citation and, in fact, resulted in multiple
fatal injuries. 25 FMSHRC at 739. Thus, the judge appropriately
considered the violative conditions that existed prior to the citation.
Id. at 756-57.
C. Conclusion
For the foregoing reasons, I would affirm the judge=s determination that Plateau
violated section 75.334(b)(1) and that the violation was S&S.
Michael G. Young, Commissioner
Commissioner Jordan, in favor of affirming the judge=s determinations that Plateau
violated 30 C.F.R. '' 75.334(b)(1) and 75.370(a)(1):
I agree with the reasoning and conclusions expressed in Commissioner
Young=s opinion affirming the
judge=s determination that
Plateau violated section 75.334(b)(1) and that the violation was S&S.
I also agree with his analysis affirming the judge=s determination that an operator may
be found to have violated section 75.334(b)(1) even though it has
complied with the terms of its ventilation plan. However, I would also
affirm the judge=s ruling that
Plateau violated section 75.370(a), and therefore dissent from the
majority=s holding regarding
that citation.
Section 75.370(a)(1) provides in relevant part that an Aoperator shall develop and follow a
ventilation plan approved by the district manager.@ 30 C.F.R. ' 75.370(a)(1). Sections
75.334(c)(4) and 75.371(bb) set forth an illustrative list of ventilation
devices that must be included in a ventilation plan based upon the
device=s function to control
air through a worked-out area. See 30 C.F.R. ' 75.334(c)(4) (stating that a
ventilation plan must specify the Alocation of ventilating devices
such as regulators, stoppings and bleeder connectors used to
control air movement through the worked-out area@ (emphasis added)); see also
30 C.F.R. ' 75.371(bb). By
the regulations= plain
language, if a ventilation device controls air through a worked-out area,
it must be included on a ventilation plan. The regulations do not set
forth limitations on the types of ventilation devices that must be
specified, nor do they set forth limitations on the locations of the
ventilation devices. Thus, under the plain terms of the standards, if the
breached undercast controlled air movement through the worked-out area,
it was required to be shown in the ventilation plan.[1]
In determining whether substantial evidence[2] supports the judge=s finding, it is therefore important
to keep in mind exactly what is and what is not relevant under this
regulation. Whether the undercast controlled air movement is dispositive;
whether the undercast was functioning as a regulator is not.[3] Whether the undercast
had an impact on air movement is pertinent; whether that impact was Asignificant@ is not. Consequently, the
majority=s rationale for
reversing the judge, slip op. at 7-8, is grounded on assertions that have
nothing to do with the plain meaning of the regulation at issue.
Substantial evidence supports the judge=s conclusion that the breached
undercast was inhibiting the flow of air up the No. 1 headgate entry into
the No. 2 setup room, although it may have done so to an insignificant
degree. 25 FMSHRC 738, 759 (Dec. 2003) (ALJ); Tr. 112-13, 118-19, 620,
638-39, 1321. Testimony from MSHA witnesses supports this conclusion. For
instance, MSHA official Gary Wirth stated that the overcast Awas still functioning to limit
airflow in that area and, therefore, played a role in inhibiting airflow
on the headgate side in the worked-out area. . . . [T]hat three-by-four
hole would not have rendered that overcast completely in effective
[sic].@ Tr. 112-13, 118. MSHA
ventilation expert John Urosek, testified that the overcast Awould impact the air flow on the
headgate,@ Tr. 620, and that
Athe overcast, and the holes in
the overcast . . . would have impacted. We have that from experience. . .
. [A hole in the overcast] will control air flow.@ Tr. 638-39.
MSHA=s ventilation staff
expected the undercast to be removed, leaving the area completely open in
accordance with the approved ventilation plan. 25 FMSHRC at 759; Tr.
110-12; Gov=t Ex. 5; Jt. Ex. 1.
Instead, Plateau retained the undercast and created a three-by-four foot
hole in it, to allow water and air to travel through it. 25 FMSHRC at
759. Although the breached undercast may not have affected airflow in the
worked-out area to a significant degree, the area of the No. 1 headgate
at the location of the breached undercast was less than completely open.
P. Ex. 3B. Thus, as the judge found, the operator was required to seek to
modify its plan to include the breached undercast. 25 FMSHRC at 759.
I reject Plateau=s argument
that the judge=s determination
of violation should be reversed because there is no requirement to obtain
MSHA approval of ventilation control devices that
exist in the gob.[4] P. Br. at 31. The parties do not dispute that
the undercast existed in the worked-out area. Id. at 32. As
discussed above, however, section 75.334(c)(4) and 75.371(bb) require
ventilation devices that control air through a worked-out area to be
included in a ventilation plan and do not set forth any limitations based
on the location of a ventilation device. Moreover, as the Secretary
submits, S. Br. at 49, the purpose of the standard is to inform MSHA of
the locations of ventilation devices and allow MSHA to decide whether to
approve those devices. Unauthorized changes in a ventilation plan can
have unintended effects on ventilation. 25 FMSHRC at 760. In short, the
evidence put forth by Plateau regarding that the undercast was in the gob
and could not be maintained or examined, Tr. 1200, is irrelevant.
I also reject Plateau=s
argument that it should not have been cited for violating its ventilation
plan because MSHA inspectors observed the breached undercast and failed
to cite it as a violation of the ventilation plan. The Commission has
refused to acknowledge estoppel as a defense to a violation, holding that
MSHA was not estopped from issuing a citation because the operator relied
on MSHA=s previous actions.
King Knob Coal Co., 3 FMSHRC 1417, 1421-22 (June 1981); see
also Emery Mining Corp. v. Sec=y of Labor, 744 F.2d
1411, 1416 (10th Cir. 1984). Rather, MSHA=s failure to previously cite a
disputed condition is appropriately considered in the context of the
operator=s negligence. Here,
the judge noted that Inspector Ray=s tacit approval of the breached
undercast supported a low negligence finding. 25 FMSHRC at 759.
For the foregoing reasons, I respectfully dissent.
Mary Lu Jordan, Commissioner
Chairman Duffy and Commissioner Suboleski, in favor of vacating the
judge=s determination that
Plateau violated 30 C.F.R. ' 75.334(b)(1) and remanding:
A. Overview
This is a case in which MSHA had little evidence that
the ventilation system was malfunctioning, yet the mine experienced an
explosion and fire. Prior to the first explosion, air volumes were above
design levels and all measuring points were within expected ranges. The
explosion itself was caused by a very small amount of methane (50 cubic
feet), a volume that would not be unexpected at the fringe of the rubble
zone. However, MSHA found what it believed to be the causes of a
distribution problem, near the headgate at the inby corner of the gob,
where the explosion was believed to have originated. This problem, which
was allegedly caused by a combination of a largely intact undercast, an
un-removed check curtain, and a series of check curtains in the set up
rooms, combined to restrict air flow in this corner, and resulted in a
violation of section 75.334(b)(1). However, trial testimony showed that
these obstructions were not present and MSHA=s primary case
fell apart.
In the course of presenting that case, MSHA witnesses
pointed out that the mine fan was at capacity; that, as production
increased from start-up at the longwall, methane levels were rising; that
the tailgate-side bleeder regulators were open as wide as possible to
maximize air flow across the face and gob; that it took a great deal of
air to dilute the methane level from the face and gob to the 2%
concentration limit specified at the point where the bleeder air enters
another air stream; and that once, two shifts before the explosion, the
system=s ability to dilute to the 2% level, i.e., the
bleeder-system capacity, had briefly been reached. Finally, MSHA
testified that Plateau=s only recourse
when it reached system capacity was to temporarily halt
production.
The judge, rather than dismissing the case, used
these circumstantial facts to construct an entirely new theory of the
case since MSHA had failed to prove that the ventilation system had
significant distribution problems. Moreover, he added a crucial element
that directly contradicted the testimony of the MSHA witnesses
B that the
volume of air in the gob was inadequate. For the following reasons, we
find that the judge=s analysis was
incorrect and we would remand to him for reconsideration of his
decision.
B. Section 75.334(b)(1)
We disagree with the conclusions reached by our colleagues, who would
affirm the judge=s finding that
Plateau violated section 75.334(b)(1). Our disagreements with the
judge=s decision lie in three
areas. First, some of the judge=s factual findings are not supported
by the record. In this regard, the judge failed to explain or address
conflicting evidence on several key issues. Second, the judge drew
conclusions or inferences that were not warranted by the underlying
facts. Finally, the judge did not adequately address, under Commission
precedent, whether Plateau had notice that, under the Secretary=s regulation, its bleeder system was
in violation because it was not moving and diluting methane in the gob
area.
These errors largely flow from the basis for the judge=s decision B that there was an inadequate volume
of air in the bleeder system. The theory of the judge=s decision stands in contrast to the
Secretary=s litigation theory
B that volume was not the
problem, but the air in the system was not being distributed properly
within the gob. Significantly, if the Secretary and the judge cannot
agree on the basis for determining whether the bleeder system was
operating effectively, it is unclear how Plateau could have responsively
addressed any performance problems in the system under section
75.334(b)(1).
We begin our analysis of the judge=s decision by noting, AThe Mine Act imposes on the
Secretary the burden of proving each alleged violation by a preponderance
of the credible evidence.@
In re: Contests of Respirable Dust Sample Alteration Citations, 17
FMSHRC 1819, 1878 (Nov. 1995), aff=d sub nom. Sec=y of Labor v. Keystone
Coal Mining Corp., 151 F.3d 1096 (D.C. Cir. 1998) (quotingGarden
Creek Pocahontas Co., 11 FMSHRC 2148, 2152 (Nov. 1989). AThe preponderance standard, in
general, means proof that something is more likely so than not so.@ In re: Contests of Respirable
Dust, 17 FMSHRC at 1838. Further, the occurrence of an ignition is
not, in and of itself, evidentiary proof of an inadequate bleeder system.
Consolidation Coal Co., 20 FMSHRC 227, 240 (Mar. 1998) (Comm=rs Riley and Verheggen) (citing
Mar-Land Indus. Contractor, Inc., 14 FMSHRC 754, 758 (May 1992);
Old Ben Coal Co., 4 FMSHRC 1800, 1804 n.4 (Oct. 1982)).
When reviewing an administrative law judge=s factual determinations, the
Commission is bound by the terms of the Mine Act to apply the substantial
evidence test. 30 U.S.C.
' 823(d)(2)(A)(ii)(I).
ASubstantial evidence@ means A>such relevant evidence as a
reasonable mind might accept as adequate to support [the judge=s] conclusion.=@ Rochester & Pittsburgh Coal
Co., 11 FMSHRC 2159, 2163 (Nov. 1989) (quoting Consolidated Edison
Co. v. NLRB, 305 U.S. 197, 229 (1938)). In reviewing the whole
record, an appellate tribunal must consider anything in the record that
Afairly detracts@ from the weight of the evidence
that supports a challenged finding. Midwest Material Co., 19
FMSHRC 30, 34 n.5 (Jan. 1997) (quoting Universal Camera Corp. v.
NLRB, 340 U.S. 474, 488 (1951)). Further, the Commission has held
that Athe substantial evidence
standard may be met by reasonable inferences drawn from indirect
evidence.@ Mid-Continent
Res., Inc., 6 FMSHRC 1132, 1138 (May 1984). The Commission has
emphasized that inferences drawn by the judge are Apermissible provided they are
inherently reasonable and there is a logical and rational connection
between the evidentiary facts and the ultimate fact inferred.@ Id.
Finally, we apply the principles established by the Commission regarding
notice. Slip op. at 10. In a case such as this, the existence of a
violation turns on whether the Secretary can establish that a reasonable
operator familiar with the conditions in the mine, including the
mine=s history of methane
liberation and the capacity of its ventilation system, would have made
adjustments to the bleeder system so as to ensure that methane
continuously and effectively was diluted and moved away from active
workings and into a return. See U.S. Steel Mining Co., 27 FMSHRC
435, 439 (May 2005) (the reasonably prudent person test must be based on
conclusions drawn by an objective observer with knowledge of relevant
facts that must be reasonably ascertainable prior to the alleged
violation).
Under section 75.334(b)(1), Plateau was required to use its bleeder
system Ato control the air
passing through the [worked out] area and to continuously dilute and move
methane-air mixtures . . . from the worked-out area away from active
workings and into a return air course or to the surface of the mine.@ 30 C.F.R. ' 75.334(b)(1). In RAG
Cumberland Res., LP, 26 FMSHRC 639, 647 (Aug. 2004), aff=d sub nom. Cumberland Coal
Res., LP v. FMSHRC, No.
04-1427, 2005 WL 3804997 (D.C. Cir. Nov. 10, 2005) (unpublished), the
Commission read section 75.334(b)(1) to require that a ventilation system
must function effectively in order to comply with the regulation. The
Commission has also noted that not every accumulation of methane in the
gob is a violation of this requirement. See VP-5 Mining Co., 15
FMSHRC 1531, 1539 (Aug. 1993) (AIf the Secretary believes that air
flowing through a gob should contain no more than 4% methane as it enters
bleeder entries, he should consider promulgating a safety standard
containing such a requirement.@); Island Creek Coal Co., 15
FMSHRC 339, 350 (Mar. 1993) (AIf the Secretary believes that
specific accumulations of methane create a hazard in gobs or other
inactive areas of underground coal mines, he should consider promulgating
safety standards to deal with this problem.@). Here, the Secretary conceded as
much before the judge. 25 FMSHRC 738, 744 (Dec. 2003) (ALJ).[1]
Consistent with this approach to interpreting the regulation, MSHA
investigator David Wirth testified, Athere will be some point within [the
longwall gob] that the methane will be in the explosive range.@ Tr. 203. MSHA experts Stephan and
Urosek testified to the same effect. Tr. 531-32; 663-64. Indeed, because
methane is liberated at a level of 100% and has to be diluted to the 2%
level at the section 75.323(e) measurement point, methane will be found
at explosive levels, on a transient basis, in the gob. 25 FMSHRC at 747.
Nevertheless, the judge concluded, AMethane must not be allowed to
accumulate in the gob because explosive concentrations are likely to
develop . . . .@ Id.
This conclusion is contrary to record testimony. Moreover, this
conclusion appears to have influenced, to a large degree, the judge=s analysis of Plateau=s bleeder system and its ability to
dilute and control methane in the gob.[2] We would instruct the judge not to rely on
this consideration in determining whether Plateau=s bleeder system met the
requirements of section 75.334(b)(1) on remand.[3]
In addition to this fundamental misunderstanding regarding the operation
of the ventilation system in the gob, the judge made other factual
findings at odds with the record. In further analyzing Plateau=s bleeder system, the judge found
that the system Awas
over-extended so that it could not, on July 31, 2000, control the
air passing through the [worked-out] area so as to continuously dilute
and move methane-air mixtures and other gases from the gob into the
bleeders.@ 25 FMSHRC at 746
(emphasis added). The judge=s
finding on this point does not reflect record testimony and relies on
evidence not probative of the issue. Moreover, his analysis fails to
address conflicting evidence.[4]
The underpinning of the judge=s
finding, id., that the bleeder system was over-extended, was MSHA
investigator Wirth=s testimony
that the main mine fan was operating at or near capacity and that the
operator could not make any adjustments to bring in additional airflow or
create additional pressure. Tr. 58-59. However, the fact that the mine
fan was running at maximum is unrelated to the capacity of the bleeder
system to handle the level of methane being liberated at the mine.[5] Nor is the capacity of
the mine fan, by itself, probative of the adequacy of the bleeder
ventilation system. In this regard, it is significant that the judge
failed to address the testimony of Plateau=s general manager Charles Burggraf,
who testified that the mine=s
ventilation system was operating well within the limits of methane levels
that it was designed to handle. Tr. 1004-05. See P. Ex. 4A
(degasification chart). We would instruct the judge to address this
testimony and any contrary evidence on remand.[6]
The judge, in concluding that there was an insufficient quantity of air
moving methane from the gob, also found that there was not a sufficient
air pressure drop between the last open crosscut in the headgate entries
and the connection between the gob and the bleeder entries. 25 FMSHRC at
747. From that finding, the judge further concluded, AAs the methane levels increased, the
amount of intake air sweeping the gob actually decreased because of
increased resistance to air movement in the gob.@ Id. at 747-48.
Initially, the judge=s
suggestion that there was an insufficient air pressure differential is
incorrect and contrary to record evidence. MSHA=s own ventilation expert, Urosek,
testified, without contradiction, that the pressure differential was
sufficient. Tr. 665, 1366-67. Other record evidence is also at odds with
the judge=s findings. The last
open crosscut in the headgate entries is outby MPLs 5 and 6, and
regulators at that point were only slightly open to prevent excess air
from escaping into the bleeder entries (under Plateau=s ventilation plan no more than 10%
of the air could be allowed through). Tr. 48-50. Because MPLs 5 and 6 are
upstream of MPLs 7 and 8, the pressure drop from the last open crosscut
in the headgate to the bleeder entries in the tailgate section (MPLs 7
and 8) must be even larger than to outby MPLs 5 and 6. Thus, the pressure
drop from the last crosscut in the headgate entry to the connection to
the bleeder entry was large.
Even if the factual basis for the judge=s analysis were correct, his
conclusion B Athe amount of intake air sweeping
the gob actually decreased because of increased resistance to air
movement in the gob,@ 25 FMSHRC
at 747-48 B is not probative of
the issue of whether the volume of air sweeping the gob was sufficient.
The record reflects that as roof falls occur in the gob, there is
increased resistance to airflow. Tr. 76, 169-70, 668. However, that
occurrence is not determinative of whether there is sufficient air
entering the gob. While the pressure differential between the headgate
and tailgate entries impacts the volume of air sweeping the gob, it does
not prove whether sufficient flow exists. In fact, there was no
allegation or evidence of insufficient flow through the gob presented by
the Secretary.[7]
Decreased flow is not the same as insufficient flow.
In sum, the judge=s reliance on
pressure differentials between the headgate and bleeder entries is
factually incorrect, and his conclusion regarding the decrease in air
sweeping the gob based on resistance in the gob does not support a
conclusion that there was an insufficient airflow in the mine.
A further basis for the judge=s
finding that the bleeder system was over-extended was his finding that
the section 75.323(e) measuring point, MPL B1, had reached capacity. 25
FMSHRC at 748. As the judge correctly recognized, methane levels in the
mine increased as production at the longwall picked up and as the gob
grew in size. Id. at 746. This trend began when production started
on July 17 and continued through July 31, and was reflected by the
readings at MPLs 7 and 8, where air left the gob and entered the No. 3
bleeder entry. Id. During this same period, methane readings at
MPL B1 also increased. Id. In his decision, the judge placed
particular reliance on the occurrence of increased readings at MPL B1
that twice reached actionable levels, above 1.95% methane, and briefly
exceeded the 2% level on July 31, two shifts prior to the shift when the
explosion occurred. Id. Plateau=s protocol required the cessation of
production at the face when methane registered at the actionable level, a
fact that we would instruct the judge to consider on remand.[8] Tr. 595.
The judge=s analysis reflects a
fundamental misunderstanding of the relationship between the section
75.323(e) measuring point and compliance with section 75.334(b)(1). MPL
B1 measured the combined airstream from five distinct air flows: the
face, the gob, the headgate, the tailgate, and the sump pump and was
located over 8000 feet from the gob. See Gov=t Ex. 31, App. I. Notwithstanding
the elevated readings at MPL B1, methane levels at MPLs 7 and 8 remained
below actionable levels throughout the period preceding the accident.
These readings gave a much more accurate picture of methane in the gob
because these measurement points were the closest to the gob and captured
readings in the bleeders before gob air exited and mixed with air from
the headgate and sump pump. Tr. 84-85. Therefore, the judge=s reliance on readings at MPL B1 to
support his conclusion that there was a violation of section 75.334(b)(1)
was misplaced.[9]
See also RAG Cumberland, 26 FMSHRC at 650 (air in the eastern
bleeder entry likely had higher methane levels before it was diluted by
air and exited from the mine through the bleeder shaft). Significantly,
there is no evidence that we can glean from the record testimony that
readings at MPLs 7 and 8 would have indicated that the ventilation system
was not operating effectively. We would instruct the judge to give
primary consideration to measurements at MPL 7 and 8 in determining the
bleeder system=s efficacy under
section 75.334(b)(1) on remand.
The judge further erred in his lengthy consideration of the injection of
Asweetened@ air into the bleeder system which
resulted in lowering methane levels at the section 75.323(e) measuring
point, MPL B1. 25 FMSHRC at 748-49. As noted above, the judge=s primary focus under section
75.334(b)(1) should have been on MPLs 7 and 8, which were the best
indicators of the methane level in air coming out of the gob. It is not
alleged that Plateau was doing anything improper under section 75.323(e)
or its ventilation plan by the leakage of intake air into its bleeder
system. Thus, the judge=s
finding that the sweetened air Aartificially lower[ed] the
methane concentrations@ at MPL
B1 is without factual or legal significance and we would instruct him not
to consider the matter on remand.1[0]
To the extent that the judge considered the readings at MPLs 7 and 8 at
all, he examined them primarily in relation to readings at MPL B1. Not
surprisingly, the judge initially noted that, as production increased,
readings at MPLs 7 and 8 increased. 25 FMSHRC at 749. The judge further
noted that the spread between methane readings at MPLs 7 and 8 and those
at MPL B1 was growing from 0.25%, prior to July 28, to 0.75% by July 31.
Id. at 749-50. Based on this factual circumstance, the judge
concluded that Agob airflow was
becoming a smaller percentage of the total airflow at MPL B1@ and, therefore, Amethane was accumulating in the gob
more rapidly than the ventilation system was able to dilute and move it
into the bleeders.@ Id.
at 750. However, the judge=s
conclusion simply does not follow from the facts.
First, the basis for the judge=s conclusion is mathematically
incorrect. As the level of methane at MPLs 7 and 8 increased, the
difference between those readings and readings at MPL B1 would grow
regardless of whether the percentage of air going through MPLs 7 and 8
decreased, remained constant, or even modestly increased.1[1] Second, it is apparent
from the record that methane readings at MPL B1 were not probative of the
volume of gob airflow. The record shows that bleeder air at MPL B1 came
from multiple areas of the mine, including the face where increasing
amounts of methane were liberated as production increased. Thus, unless
the effect of methane liberation from the face, as well as airflow from
other areas, could be eliminated, any correlation between the difference
in readings at MPL B1 and MPLs 7 and 8, and gob airflow is tenuous at
best.
Finally and most significantly, the judge=s further conclusion, drawn from the
readings at MPL B1 and MPLs 7 and 8, that methane was accumulating in the
gob too rapidly to be removed by ventilation simply does not follow from
the record evidence. An increase in the level of methane being removed
from the gob and an excess accumulation are not the same thing. An
increase in the level of methane at MPLs 7 and 8, by itself, could just
as logically lead to the conclusion that the ventilation system was
operating effectively. Moreover, methane liberation at the face also
would cause an increase in the level of methane at MPLs 7 and 8.
Even if methane levels at MPL B1 and MPLs 7 and 8 were increasing, the
judge=s ultimate conclusion
B that methane was accumulating
more rapidly than the ventilation system was able to remove it, 27 FMSHRC
at 750 B does not follow from
this. As we have noted, higher levels of methane at these measurement
points were expected as production increased and the gob area expanded.
Methane levels at MPLs 7 and 8 never reached actionable levels. Even the
Secretary=s own expert,
Stephan, opined that the initial explosion that touched off the later
more serious explosions occurred as a result of the ignition of a very
small amount of methane, approximately 50 cubic feet. Thus, we believe
that the judge should rely on other record evidence if he is to support
this conclusion.
Because of these factual discrepancies in the judge=s decision, a remand to the judge to
reevaluate the record evidence would be warranted. In addition, for the
reasons more fully discussed below, we would instruct the judge to also
further analyze the notice issue before him, using the correct legal
standard.
C. Notice
We disagree with the judge=s
terse analysis of whether a reasonably prudent person would have been on
notice that there was a violation of section 75.334(b)(1). The judge
concluded, AI agree with the
Secretary that Plateau should have been on notice that its bleeder
system was not functioning properly on July 31, 2000.@ 25 FMSHRC at 746 (emphasis added).
However, the Commission has long rejected a subjective approach to the
reasonably prudent person test. See Canon Coal Co., 9 FMSHRC 667,
668 (Apr. 1987). Rather, as the Commission has explained, A[T]he reasonably prudent person test
must be based on conclusions drawn by an objective observer with
knowledge of the relevant facts. It follows that the facts to be
considered must be those which were reasonably ascertainable prior to the
alleged violation.@ U.S.
Steel, 27 FMSHRC at 439 (citation omitted). The judge=s reliance on a Ashould have known@ test substitutes a subjective
standard that the Commission has long eschewed. Therefore, for this
additional reason, his decision should be vacated and remanded for
application of the correct legal standard that is set forth above, slip
op. at 24.
We would instruct the judge to consider the factual circumstances
surrounding the ventilation system prior to July 31 on remand. As the
judge noted, 25 FMSHRC at 745, the only numerical requirement in the
safety standards is that methane cannot exceed 2% in the return air just
before it joins another split of air.1[2] 30 C.F.R. ' 75.323(e). However, section
75.334(b)(1), the regulation alleged to have been violated here, has no
numerical standards against which an operator=s ventilation plan may be evaluated.
In addition, Plateau was in full compliance with its ventilation plan.
While we do not agree with Plateau=s position that complying with an
approved ventilation plan is an absolute defense to a citation under
section 75.334(b)(1),1[3] MSHA=s involvement at this mine was much
more extensive.
Further, there is little in the record to suggest that there was a
problem in the gob. All volume measurements appear to have been within
the desired range. Measurements of methane levels at MPLs 7 and 8 were
within the acceptable range. The methane level at MPL B1 had also
remained below the action level for all of this shift and the previous
shift, after twice briefly exceeding that level two shifts prior.
Plateau=s protocol dictated
that an elevated level of methane would be addressed by a cessation of
production, and the methane level at MPL B1 had fallen below the action
level during the idle period. While we leave it to the judge to
thoroughly review the record, we can find no evidence to indicate that
there were dangerous levels of methane accumulating in violation of
section 75.334(b)(1), that the system was in any way not performing as
expected, or that there was any reason to suspect that the system was not
performing as expected. Given the above facts, it is difficult to
ascertain how a reasonably prudent operator would have known that there
was a violation of the regulation.
Finally, we note that it is difficult to ascertain how a reasonably
prudent operator should have responded to the problems that the Secretary
found in the ventilation system. The Secretary presented several experts
at trial who testified that Plateau failed to adequately distribute air
in the gob. The judge rejected the Secretary=s theory and concluded that the
problem was one of inadequate volume of air. 25 FMSHRC at 750-51. In
fact, Plateau responded to the elevated readings at MPL B1 as its
protocol required.1[4] Absent other evidence that the ventilation
system was not performing as expected, it is not evident to us what
further actions a reasonably prudent operator should have taken.
In sum, we would instruct the judge to apply the reasonably prudent
person test from the perspective of an objective mine operator who
considers the totality of factual circumstances and evaluate all
conflicting testimony and evidence that are relevant to this inquiry on
remand. U.S. Steel, 27 FMSHRC 444.
Michael F. Duffy, Chairman
Stanley C. Suboleski, Commissioner
Distribution
R. Henry Moore, Esq.
Jackson Kelly, PLLC
Three Gateway Center, Suite 1340
401 Liberty Avenue
Pittsburgh, PA 15222
Robin A. Rosenbluth, Esq.
Office of the Solicitor
U.S. Department of Labor
1100 Wilson Blvd., 22nd Floor West
Arlington, VA 22209-2247
Administrative Law Judge Richard Manning
Federal Mine Safety & Health Review Commission
Office of Administrative Law Judges
1244 Speer Blvd., Suite 280
Denver, CO 80204
[1] 30 C.F.R. ' 75.334(b)(1) provides:
During pillar recovery a bleeder system shall be used to control the air
passing through the area and to continuously dilute and move methane-air
mixtures and other gases, dusts, and fumes from the worked-out area away
from active workings and into a return air course or to the surface of
the mine.
[2] 30 C.F.R. ' 75.370(a)(1) provides in part:
The operator shall develop and follow a ventilation plan approved by the district manager. The plan shall be designed to control methane and respirable dust and shall be suitable to the conditions and mining system at the mine. The ventilation plan shall consist of two parts, the plan content as prescribed in ' 75.371 and the ventilation map with information as prescribed in ' 75.372.
[3] The petition also allowed Plateau to use a two-entry system to mine the D-1 and D-2 panels. 25 FMSHRC at 739; Tr. 139. A two-entry system uses two entries for longwall headgate and tailgate development. Tr. 35-36. The two-entry system is used to minimize the hazards created by roof stresses. 25 FMSHRC at 741; Tr. 35, 140-41. However, this minimizes the availability of air passages provided by additional entries for the movement of air. Tr. 62, 608-09, 1207.
[4] On the map attached to the judge=s decision, the judge mislabeled the No. 2 setup room as the ANo. 1 setup room,@ and mistakenly referred to the No. 2 setup room as the No. 1 setup room and vise-versa, throughout his decision (see, e.g., 25 FMSHRC at 741, 752, 758). P. Br. at 3 n.3; Tr. 45, 70. The error was harmless, however.
[5] The pump operated to keep water from accumulating in the bleeder entries. 25 FMSHRC at 742; Tr. 46-47.
[6] MPLs B1 and B2 were located between crosscuts 6 and 7 in the D-1 tailgate Nos. 1 and 2 entries, which now formed part of the bleeder for D-3, and MPL B3 was located between crosscuts 6 and 7 in the No. 3 entry of the D seam bleeders. Gov=t Ex. 31 at 20.
[7] Section 75.323(e) provides in part that A[t]he concentration of methane in a bleeder split of air immediately before the air in the split joins another split of air . . . shall not exceed 2.0 percent.@ 30 C.F.R. ' 75.323(e).
[8] In concluding that the violation was not S&S, the judge determined that the Secretary failed to prove that Plateau=s failure to completely remove the undercast contributed to the explosions. 25 FMSHRC at 760.
[9] Commissioner Jordan dissents from Part II.A of this opinion. See slip op. at 20-22.
[10] At the time of the citation, MSHA mistakenly believed that the hole in the undercast was smaller than 3 feet by 4 feet. Tr. 620, 675, 1321. MSHA stated in part that the undercast had been Aleft intact@ in the citation issued to Plateau for failing to include the undercast in its July 7 ventilation plan. Gov=t Ex. 4.
[11] Although two of MSHA=s witnesses stated that they believed the undercast would have impacted airflow, they acknowledged that the computer simulations did not show a significant impact on airflow caused by the breached undercast. Tr. 635, 1321.
[12] Our dissenting colleague effectively interprets the regulatory language that a plan is required to specify devices Aused to control air movement@ to mean that a plan must depict any device that might affect air flow, even to an insignificant degree. Slip op. at 21-22. Such an overly broad interpretation essentially ignores the Aused to control air movement@ language and would appear to encompass within the regulatory parameters such things as mining equipment left in an area that might have a de minimus impact on airflow.
[13] In RAG Cumberland, the operator did not argue that it failed to receive adequate notice that section 75.334(b)(1) applied to the cited conditions but merely submitted that reading the standard to require adequate dilution could Apotentially deprive operators of due process notice.@ 26 FMSHRC 647 n.14. In contrast, Plateau has raised the issue of notice. P. Br. at 14, 24-25, 26.
[1] The record shows that the estimated methane capacity of the D-3 panel was based on the range of concentrations that the mine experienced on the D-1 and D-2 panels. Tr. 1001-02. Given the critical differences between the panels, as discussed above, it would appear that methane liberation and the capacity of the panels would be inappropriate for comparison. Moreover, as noted by the Secretary (S. Br. at 43), there was no evidence admitted regarding the reliability of the studies used by Plateau to estimate capacity. Although a finding regarding the methane capacity of the D-3 panel would have been relevant, given this evidence, the judge=s failure to make such a finding is of no avail.
[2] While my colleagues contend that the ventilation system was operating well within its capacity (slip op. at 26-28 & n.7), I view this admission by Plateau=s mine manager to be highly probative and amply supported by the record. It also appears that Plateau did not promptly cease production, but that the exceedances occurred while production was idle and prompted no investigation or action by Plateau. See Gov=t Ex. 31 at 21, 30; Tr. 103, 107, 164, 762, 793, 802, 812.
[3] Section 75.323(e) provides in part that the concentration of methane in a bleeder split of air immediately before the air in the split joins another split of air shall not exceed 2%. 30 C.F.R. ' 75.323(e).
[4] The last recorded airflow at MPLs 7 and 8 prior to the accident was approximately 185,600 CFM of air. Gov=t Ex. 31 at 22. Wirth testified that three small splits entered the bleeder system but did not ventilate the gob, namely, a split from the No. 2 intake entry that entered the bleeder system at MPL 5 (5,200 CFM), and at MPL 6 (14,500 CFM), and a third split of intake air, approximately 65,000 CFM, which was directed into the No. 1 bleeder entry and measured 15,000 CFM when it reached the pump (50,000 CFM). Gov=t Ex. 31 at 22; Tr. 100-01; Gov=t Ex. 7. The total airflow for this worked-out area (MPLs 5, 6, 7, and 8 and the pump) was 220,300 CFM of air. Approximately 331,600 CFM of air was measured exiting from MPLs B1, B2, and B3. Gov=t Ex. 31 at 22. The Secretary submitted that approximately 111,000 CFM of air that was not used to ventilate the gob and was not acknowledged in the ventilation plan, was leaking into the bleeder system. See S. Br. at 30-31 n.10; S. Post-Hr=g Br. at 12-13.
[5] I disagree with my colleagues= conclusion that the judge erred by failing to give primary consideration to measurements at MPLs 7 and 8 in determining the bleeder system=s efficacy under section 75.334(b)(1). Slip op. at 28-29. First, it is not clear that the readings at MPLs 7 and 8 provided a materially more accurate picture of methane in the gob given that those readings were diluted by intake air from the No. 2 tailgate entry. Tr. 81-84. Moreover, my colleagues effectively deem the readings at MPL B1 irrelevant, contrary to the inherent significance of MPL B1 as the measuring point established by section 75.323(e) and its underlying statutory provision as an indicator of the effectiveness of the bleeder system. The 2% limit set by section 75.323(e) was exceeded at MPL B1 even though the judge found leakage diluted the methane reading at that measuring point.
[6] Although the judge did not explicitly apply the Commission=s Areasonably prudent person test,@ he concluded that Plateau should have been on notice that its bleeder system was not functioning properly on July 31. 25 FMSHRC at 746. Contrary to my colleagues= assertion that this conclusion injects subjectivity into the process (slip op. at 31), the judge merely inferred constructive notice from the circumstances. This is not improper. See generally Dolese Bros. Co., 16 FMSHRC 689, 693-94 (Apr. 1994) (affirming finding of violation upon application of reasonably prudent person test where judge in part inferred constructive knowledge).
[1] The undercast at issue here was not included in the ventilation plan. Gov=t Ex. 4.
[2] When reviewing a judge=s findings of fact, the Commission must by statute apply the substantial evidence test. 30 U.S.C. ' 823(d)(2)(A)(ii)(I). Under this test, the Commission may not Asubstitute a competing view of the facts for the view [a judge] reasonably reached.@ Donovan ex rel. Chacon v. Phelps Dodge Corp., 709 F.2d 86, 92 (D.C. Cir. 1983). The fact that evidence exists in the record to support a party=s position adverse to the judge is not determinative. Rather, the Commission=s review is statutorily limited to whether the judge=s findings of fact were supported by A>such relevant evidence as a reasonable mind might accept as adequate to support [the judge=s] conclusion.=@ See, e.g., Jim Walter Res., Inc., 19 FMSHRC 1761, 1767 n.8 (Nov. 1997) (citing Rochester & Pittsburgh Coal Co., 11 FMSHRC 2159, 2163 (Nov. 1989)).
[3] The operator argues that the judge=s decision should be reversed because his ruling is based on his finding that the undercast was a regulator, an issue not raised by the Secretary or addressed by the parties below. P. Br. at 31. Although the parties did not litigate whether the breached undercast acted as a regulator, they litigated whether the undercast affected airflow through the worked-out area. See S. Post-Hr=g Br. at 29-31; P. Post-Hr=g Br. at 58-59. In addition, as the Secretary argues, S. Br. at 48, the citation sets forth the Secretary=s position that Plateau violated section 75.370(a)(1) because the undercast controlled air movement through the worked-out area but was not depicted in the ventilation plan. Gov=t Ex. 4. In addition, Plateau litigated whether the undercast controlled air movement. P. Post Hr=g Br. at 59 (Athe breached [undercast] had no effect on the ventilation of the worked-out area . . . . Thus the presence of the breached [undercast] provided no support for a violation of the ventilation plan.@). Thus, the parties litigated the underlying basis for the judge=s determination.
[4] The Secretary asserts that the Commission need not reach Plateau=s argument that a ventilation device in a gob, effective or not, does not have to be in a ventilation plan, because Plateau failed to raise the issue before the judge. S. Br. at 48-49. However, as Plateau contends, it appears that Plateau raised the issue before the judge. Tr. 1200; P. Post-Hr=g Br. at 61.
[1] The Secretary=s position on this point before the Commission is less clear; nevertheless, the Secretary has failed to explain under what circumstances a small accumulation of methane, such as the one that caused the initial explosion at Plateau=s mine, becomes a violation under section 75.334(b)(1). See S. Br. at 18-21.
[2] Earlier in his decision, the judge inconsistently stated, AThe presence of explosive levels of methane in the gob does not establish a violation of the Mine Act or the Secretary=s safety standards.@ 25 FMSHRC at 745.
[3] As the judge noted, the occurrence of an explosion in the gob does not indicate the ventilation system was not operating effectively under section 75.334(b)(1). 25 FMSHRC at 745, citing Consolidation Coal, 20 FMSHRC at 240.
[4] A judge must analyze and weigh the relevant testimony of record, make appropriate findings, and explain the reasons for his decision. Anaconda Co., 3 FMSHRC 299, 299-300 (Feb. 1981). The substantial evidence standard of review requires the Commission to weigh all probative evidence and to examine the fact finder=s rationale in arriving at the decision. Pittsburgh & Midway Coal Mining Co., 15 FMSHRC 2243, 2245-46 (Nov. 1993) (citing Universal Camera, 340 U.S. at 487-88. The judge=s broad statement that AAny evidence or argument not discussed herein that is inconsistent with my findings and conclusions is hereby rejected[,]@ 25 FMSHRC at 744, is not adequate given the complex factual and technical issues in this case.
[5] That is, because the fan could not do more does not indicate it was not doing enough.
[6] Our colleagues compound the omission of the judge by adopting the Secretary=s post-accident allegation in the citation, stating that Ait appears@ that Plateau had Alimited mine ventilating potential.@ Slip op. at 13. Such a conclusory statement, however, cannot substitute for the record review that we would ask the judge to make. Moreover, our colleagues state that a finding regarding the methane capacity of Plateau=s bleeder system in the D-3 longwall panel would be Aof no avail@ in deciding this case. Slip op. at 12-13 n.1. At best, this statement is contradictory, given their willingness to embrace the Secretary=s allegation noted above. See also slip op. at 13-14 (analyzing levels of methane liberation). For purposes of reviewing the judge=s finding that the system was Aover-extended@ and reaching the ultimate conclusion whether the system was able to continuously dilute and move methane, we conclude that such a finding is an essential part of such an analysis. 25 FMSHRC at 746.
[7] Two of the Secretary=s witnesses, investigator Wirth (Tr. 61) and ventilation expert Urosek (Tr. 645), testified that there was not a volume problem.
[8] Reaching capacity is signaled by exceeding action levels at the evaluation points, and having excess capacity is demonstrated by staying below those levels. Here, the record shows that, two shifts prior to the explosion, methane measurements at MPL B1 briefly reached action levels of 1.95% twice. Thus, the ventilation system was operating well within capacity 100% of the time on the shift during which the accident occurred and the immediately preceding shift, and over 95% of the time on the day of the accident. Finally, our colleagues= implication that Plateau should have addressed the elevated readings at MPL B1 by changing the ventilation system ignores the realities of the ventilation plan approval process and the fact that Plateau timely and effectively addressed the high readings by ceasing production, as required by its protocol.
[9] We disagree with our colleagues that Plateau somehow erred by not investigating the Acause or effect of the exceedance . . . at MPL B1.@ Slip op. at 15. See also slip op. at 13 n.2. Plateau performed exactly as its protocol demanded by ceasing production (which had stopped prior to the high reading because of a shift change). Further, with the idling of production, methane levels at MPL B1 dropped, as intended by Plateau=s protocol. In these circumstances, we fail to see what Plateau would have investigated.
1[0] Because what
Plateau was doing here was permissible, indeed intended under section
75.323(e), the judge=s
suggestion, reinforced by our colleagues= analysis, slip op. at 12, 14-17,
that the measurement point was improperly placed, because of its distance
from the gob and injection of additional air, is not well taken. Indeed,
only the Secretary can change the section 75.323(e) measurement point
through notice-and-comment rulemaking. Labeling this determination as a
credibility issue, 25 FMSHRC at 748, slip op. at 14, does not change the
legal nature of the ruling, which is to move the location of the section
75.323(e) measurement point within the bleeder system. Finally, even
while chastising Plateau for allegedly inappropriately diluting the air
stream measured at MPL B1, our colleagues nevertheless give primacy to
readings taken there over those taken at MPLs 7 and 8. This displays a
misunderstanding of the purposes of these distinct measuring points.
[1]1 For example, if the air from MPLs 7 and 8 remained at a
constant 75% of the total air flowing to MPL B1 and contained 1.5%
methane, while the remainder of air contained 0.5% methane, then the air
at MPL B1 would contain 1.25% methane [(1.5% x 0.75) + (0.5% x 0.25) =
1.25%]. The difference between the methane levels at the MPLs is: (1.50%
- 1.25%) or 0.25%. Now, if the methane content at MPLs 7 and 8 increases
to 3.5% and nothing else changes, the level at MPL B1 becomes 2.75%
[(3.5% x 0.75) + (0.5% x 0.25)] and the difference between the methane
levels at the MPLs increases to: (3.50% - 2.75%) or 0.75%. Furthermore,
even if the Agob flow@
were to increase to 85% of the total in the second
case, the difference between the MPLs would have risen from 0.25% to
0.45%, contrary to the judge=s conclusion
that a rising difference indicates a decrease in flow from the
gob.
1[2] Our
colleagues= de novo
analysis of the record relating to notice ignores the crucial question of
how a reasonably prudent operator would know that the ventilation
system was not operating effectively in light of measurements that were,
except in the two instances previously noted, within permissible and
expected ranges. See slip op. at 17-18. In an effort to address
this issue, our colleagues describe the two exceedances at the section
75.323(e) measurement point and the elevated readings at MPLs 7 and 8 as
evidencing a Adisruption@ in the system. However, the
Secretary has never alleged that Plateau violated the terms of its
approved ventilation plan in any regard.
1[3] AOnce a ventilation plan is approved
and adopted, its provisions and revisions are enforceable as mandatory
standards.@ Wyoming Fuel
Co., 16 FMSHRC 1618, 1624 (Aug. 1994) (citations omitted). Major
changes in the plan require MSHA=s approval before they can be
implemented. Id.
1[4] The elevated readings at MPL B1 actually appeared near the start of an idle shift, possibly reflecting the length of time that it would take air to travel the long distance from the face and gob to the section 75.323(e) measuring point.