FEDERAL MINE SAFETY AND HEALTH REVIEW COMMISSION
601 NEW JERSEY AVENUE, NW
SUITE 9500
WASHINGTON, DC 20001
January 12, 2009
SECRETARY OF LABOR, MINE SAFETY AND HEALTH ADMINISTRATION (MSHA) v. SOUTHWEST ROCK PRODUCTS, LLC |
: : : : : : : |
Docket No. WEST 2009-51-M A.C. No. 02-03111-141339 |
BEFORE: Duffy, Chairman; Jordan, Young, and Cohen, Commissioners
ORDER
BY THE COMMISSION:
This matter arises under the Federal Mine Safety and Health Act of 1977, 30 U.S.C. § 801 et seq. (2000) (“Mine Act”). On October 16, 2008, the Commission received from Southwest Rock Products, LLC (“Southwest”) a request to reopen two penalty assessments that had become final orders of the Commission pursuant to section 105(a) of the Mine Act, 30 U.S.C. § 815(a).
Under section 105(a) of the Mine Act, an operator who wishes to contest a proposed penalty must notify the Secretary of Labor no later than 30 days after receiving the proposed penalty assessment. If the operator fails to notify the Secretary, the proposed penalty assessment is deemed a final order of the Commission. 30 U.S.C. § 815(a).
The Secretary supports reopening of the proposed penalty assessments in order that the parties’ agreement to settle the assessments can be approved.
We have held that in appropriate circumstances, we possess jurisdiction to reopen uncontested assessments that have become final Commission orders under section 105(a). Jim Walter Res., Inc., 15 FMSHRC 782, 786-89 (May 1993) (“JWR”). In evaluating requests to reopen final section 105(a) orders, the Commission has found guidance in Rule 60(b) of the Federal Rules of Civil Procedure under which, for example, a party could be entitled to relief from a final order of the Commission on the basis of mistake, inadvertence, or excusable neglect. See 29 C.F.R. § 2700.1(b) (“the Commission and its Judges shall be guided so far as practicable by the Federal Rules of Civil Procedure”); JWR, 15 FMSHRC at 787. We have also observed that default is a harsh remedy and that, if the defaulting party can make a showing of good cause for a failure to timely respond, the case may be reopened and appropriate proceedings on the merits permitted. See Coal Prep. Servs., Inc., 17 FMSHRC 1529, 1530 (Sept. 1995).
Having reviewed Southwest’s request and the Secretary’s response, we grant reopening and hereby remand this matter to the Chief Administrative Law Judge to rule on the motion for approval of the settlement attached to the Secretary’s response.
____________________________________
Michael F. Duffy, Chairman
____________________________________
Mary Lu Jordan, Commissioner
____________________________________
Michael G. Young, Commissioner
____________________________________
Robert F. Cohen, Jr., Commissioner
Distribution:
Christopher Reinesch
Southwest Rock Products, LLC
745 N. Gilbert Rd., #124-304
Gilbert, AZ 85234
W. Christian Schumann, Esq.
Office of the Solicitor
U.S. Department of Labor
1100 Wilson Blvd., Room 2220
Arlington, VA 22209-2296
Myra James, Chief
Office of Civil Penalty Compliance
MSHA
U.S. Department of Labor
1100 Wilson Blvd., 25th Floor
Arlington, VA 22209-3939
Chief Administrative Law Judge Robert J. Lesnick
Federal Mine Safety & Health Review Commission
601 New Jersey Avenue, N.W., Suite 9500
Washington, D.C. 20001-2021