FEDERAL MINE SAFETY AND HEALTH REVIEW COMMISSION
















justification of appropriation estimates

for committee on appropriations
















Fiscal Year 2008





FEDERAL MINE SAFETY AND HEALTH REVIEW COMMISSION



SALARIES AND EXPENSES


Table of Contents



FY 2008 Budget

 

Executive Summary. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1

Organization Chart. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .2

Appropriation Language. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3

Authorizing Legislation. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .4

Budget Authority and Staffing by Activity. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5

Summary of Changes. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6

Budget Authority by Object Class. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .7

Personnel Summary. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .8

Amounts Available for Obligation. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .9

Appropriations History. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10

Staffing History. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11

Congressional Directives. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .12

Narrative Justifications

            General Statement. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13

            Activities:

                  Commission Review. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14

                  Administrative Law Judge Determinations. . . . . . . . . . . . . . . . . . . . . . . . . . .20

Agency-wide Management Objectives. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 25

Selected Workload Data . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .28

Commission Members. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .29

Consultants. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .30

 


FEDERAL MINE SAFETY AND HEALTH REVIEW COMMISSION


Executive Summary


            The Federal Mine Safety and Health Review Commission is an independent adjudicative agency that provides administrative trial and appellate review of legal disputes arising under the Federal Mine Safety and Health Act of 1977 as amended. Section 113 of that Act establishes the Commission and sets forth its responsibilities. Public Law 109-236, the Mine Improvement and New Emergency Response Act of 2006 (MINER Act) added an additional responsibility to the Commission for resolving disputes between the Secretary of Labor and underground coal operators with respect to the content of the operator’s accident response plan or the Secretary’s refusal to approve a plan.


            Most cases that come before the Commission involve civil penalties proposed by the Department of Labor’s Mine Safety and Health Administration (MSHA) against mine operators. The Commission is responsible for addressing whether the alleged violations occurred as well as the appropriateness of proposed penalties. Other types of cases include contests of MSHA orders to close a mine for health or safety reasons, miners’ charges of discrimination based on their complaints regarding health or safety, and miners’ requests for compensation after being idled by a mine closure order. Unlike most of the cases that come before the Commission, issues of dispute involving accident response plans must be decided on an expedited basis.

 

            The Commission’s administrative law judges (ALJs) decide cases at the trial level. The five member Commission provides administrative appellate review. Review of an ALJ decision by the Commission is not automatic but requires the approval of at least two Commissioners. Most of the cases accepted for review are generated from petitions filed by parties adversely affected by an ALJ decision. In addition, the Commission on its own initiative may decide to review a case. An ALJ decision that is not accepted for review becomes a final, non-precedential order of the Commission. Appeals from the Commission’s decisions are to the federal circuit courts of appeals.


            The Commission is requesting a budget of $8,096,000 covering 48 FTE for FY 2008. The request includes $288,000 to support 4 additional FTE and $77,000 to support a base staff of 44 and to provide for an anticipated 3.1% pay increase for January 08. Any increase costs of Commission operations are being absorbed with the base funding.


            During FY 2006, the Commission received more than 3,400 new trial cases, a 40 percent increase over FY 2005 and FY 2006 workload projections.



            For FY 2007, new case intake is expected to remain at 3,400, including a substantial number of accident response plan disputes which will require immediate attention. As a result, the FY 2007 end-of-year inventory of undecided cases is expected to swell to 3,756 cases.


            For FY 2008, the Commission anticipates a slowing of new case filings to a rate of 3,000 per year. With the increased resources included in this budget case dispositions should increase to 3,000 holding the end-of-year inventory of undecided cases at the FY 2007 level projected level of 3756.


            At the appellate level, the workload is expected to remain consistent with 86 new cases anticipated for FY 2008, with dispositions of 87 resulting in an end-of-year inventory of 12 undecided cases.


            In addition to conducting its appellate responsibilities, the Commission expects to finalize its procedural rules for resolving disputes under the MINER Act during FY 07.





FEDERAL MINE SAFETY AND HEALTH REVIEW COMMISSION

ORGANIZATIONAL CHART

KEY PERSONNEL




ARLENE HOLEN (Designee)

 

MARY LU JORDAN

 

MICHAEL F. DUFFY

(Designee)

 

Vacant

 

MICHAEL C. YOUNG


COMMISSIONER



COMMISSIONER



CHAIRMAN


COMMISSIONER


COMMISSIONER


 






|

|

 

|

|

|

|

|

|

|

 






|

|

 


THOMAS A. STOCK

 


Michael McCord

 


ROBERT J. LESNICK


Executive

Director


General

Counsel


Chief Administrative

Law Judge

                                                                                                                           

 


FEDERAL MINE SAFETY AND HEALTH REVIEW COMMISSION


Salaries and Expenses



            For necessary expenses of the Federal Mine Safety and Health Review Commission (30 U.S.C. 801, et. seq.), $8,096,000



Explanation of Language


            Note: A regular 2007 appropriation for this account had not been enacted at the time the budget was prepared; therefore, this account is operating under a continuing resolution (P. L. 109-289, Division B, as amended). The amounts included for 2007 in this budget reflect the levels provided by the continuing resolution.

 


FEDERAL MINE SAFETY AND HEALTH REVIEW COMMISSION


Authorizing Legislation


 

                                                                        FY 2007                      FY 2008


Authorizing Legislation

Containing Indefinite Authority



Federal Mine Safety and Health

Amendments Act of 1977, as amended

(30 U.S.C. 823-824)                                       7,731,000                    8,096,000



FEDERAL MINE SAFETY AND HEALTH REVIEW COMMISSION

 


Budget Authority and Staffing by Activity


 


       FY 2006


        FY 2007 Est.


       FY 2008

Increase over FY 2007 Est.

 

FTE

Amount

FTE

Amount

FTE

Amount

FTE

Amount


Commission Review


24


4,619,340


27


4,619,000


27


4,696,000


--


+77,000

Administrative

Law Judge Determinations


17


3,111,570


17


3,112,000


21


3,400,000


+4


 +288,000

Total BA

41

7,730,910

44

7,731,000

48

8,096,000

+4

+365,000




FEDERAL MINE SAFETY AND HEALTH REVIEW COMMISSION



Summary of Changes


Budget Authority

FY 2007

FY 2008

Net Change

Appropriations

$7,731,000

$8,096,000

+365,000

Full-time Equivalent

44

48

  +4


Explanation of Changes

FTE

Budget Authority

Increases

 

 

        Increased FTE

+4

+288,000

       Maintain Base Staff

+77,000

Decreases

 

 

        

 

 

Net Change

+4

+365,000



 

FEDERAL MINE SAFETY AND HEALTH REVIEW COMMISSION

 

Budget Authority by Object Class

(in thousands of dollars)

 

 

Actual

FY 2006

Estimate

FY 2007

Estimate

FY 2008

Increase or Decrease over 2007 Est.

Personnel Compensation


Full-time permanent



4,297



4,210



4,546



+336

Other than full-time permanent

290

304

311

+7

Total, personnel compensation

4,587

4,514

4,857

+343

Personnel benefits, civilian

945

985

1,031

+46

Benefits former personnel

Travel and transportation

  of persons


100


100


98


-2

Transportation of things

2

2

2

Rental Payments to GSA 

1,217

1,250

1,248

-2

Communications, utilities and

  miscellaneous charges


115


115


112


-3

Printing and reproduction

35

35

34

-1

Other services

585

585

572

-13

Supplies and materials

80

80

78

-2

Equipment

      65

      65

   64

   -1

TOTAL

7,731

7,731

8,096

+365

 


FEDERAL MINE SAFETY AND HEALTH REVIEW COMMISSION

 

Personnel Summary


 

2006

ACTUAL

2007

ESTIMATE

2008

REQUEST

Account: Salaries & Expenses

Executive Level III

Executive Level IV

1

4

1

4

1

4

Subtotal

5

5

5

ES

2

2

2

AL-2

AL-3

1

8

1

8

1

8

Subtotal

9

9

9

GS-15

GS-14

GS-13

GS-12

GS-11

GS-9

GS-8

GS-6

4

2

3

3

2

2

8

1

4

2

3

3

2

2

8

1

4

3

2

3

6

2

7

1

Subtotal

25

25

28

Total Permanent Full-time Positions

41

41

48

Unfilled positions end-of-year

6

Total, full-time permanent employment end-of-year

35

41

48

Full-time equivalent (FTE) usage

41

44

48

____________________________________________________________________________


Average ES salary

Average AL level

Average AL salary

Average GS grade

Average GS salary

$138,008

2.89

$152,000

10.92

$72,873

$141,044

2.89

$155,344

10.92

$74,476

$145,416

2.90

$160,160

10.83

$71,114



FEDERAL MINE SAFETY AND HEALTH REVIEW COMMISSION


Salaries and Expenses


Amounts Available for Obligation


 

FY 2006

FY 2007

FY 2008

 

FTE

Amount

FTE

Amount

FTE

Amount

Appropriation, total

estimated obligations


41


7,730,910


44


7,731,000


48


8,096,000




FEDERAL MINE SAFETY AND HEALTH REVIEW COMMISSION

Appropriations History Table


Fiscal                   Budget Estimate                House                                 Senate 

Year                     To Congress                       Allowance                         Allowance                     Appropriation

______              ______________          ____________               ____________               ____________

1986                    3,709,000                           3,815,000                           3,815,000                           3,651,000 Footnote

1987                    3,919,000                           3,651,000                           3,919,000                           3,785,000

1988                    4,139,000                           4,080,000                           4,080,000                           3,892,000 Footnote

1989                    4,079,000                           4,079,000                           4,079,000                           4,030,000 Footnote

1990                    4,005,000                           4,030,000                           4,030,000                           4,030,000

1991                    4,292,000                           4,292,000                           4,292,000                           4,188,509 Footnote

1992                    4,719,000                           4,357,000                           4,357,000                           5,143,000

1993                    5,830,000                           5,772,000                           5,772,000                           5,726,000 Footnote

1994                    5,842,000                           5,842,000                           5,842,000                           5,842,000

1995                    6,237,000                           6,200,000                           6,200,000                           6,189,000 Footnote

1996                    6,467,000                           6,467,000                           6,200,000                           6,184,000 Footnote

1997                    6,332,000                           6,060,000                           6,060,000                           6,049,000 Footnote

1998                    6,060,000                           6,060,000                           6,060,000                           6,060,000

1999                    6,060,000                           6,060,000                           6,060,000                           6,060,000

2000                    6,159,000                           6,060,000                           6,159,000                           6,136,000 Footnote

2001                    6,320,000                           6,200,000                           6,320,000                           6,320,000

2002                    6,939,000                           6,939,000                           6,939,000                           6,934,000 Footnote

2003                    7,127,000                                                                                                        7,131,343 Footnote

2004                    7,774,000                           7,774,000                           7,774,000                           7,728,133 Footnote

2005                    7,813,000                           7,813,000                           7,813,000                           7,809,024 Footnote

2006                    7,809,000                      7,809,000                      7,809,000                 7,730,910 Footnote

2007                    7,576,000                           7,731,000                           7,731,000                           7,731,000 Footnote

2008                 8,096,000



FEDERAL MINE SAFETY AND HEALTH REVIEW COMMISSION


Staffing History Table



Fiscal Year                                                                             FTE

 

1986                                                                                        47

1987                                                                                        51

1988                                                                                        52

1989                                                                                        51

1990                                                                                        48

1991                                                                                        47 

1992                                                                                        56

1993                                                                                        53

1994                                                                                        53

1995                                                                                        55

1996                                                                                        52

1997                                                                                        50

1998                                                                                        47

1999                                                                                        45

2000                                                                                        43

2001                                                                                        42

2002                                                                                        38

2003                                                                                        35

2004                                                                                        40

2005                                                                                        40

2006                                                                                        41

2007 Est.                                                                                 44

2008 Est.                                                                                 48


FEDERAL MINE SAFETY AND HEALTH REVIEW COMMISSION


Congressional Directives



            There were no Congressional Directives for the Federal Mine Safety and Health Review Commission for FY 2006 or FY 2007.



FEDERAL MINE SAFETY AND HEALTH REVIEW COMMISSION


Justification


2007
Estimate
________________
2008
Request
________________
Increase or
Decrease
________________
 
FTE Amount FTE Amount FTE Amount
Commission Review 27  4,619,000 27  4,696,000 --  +77,000
 
Administrative Law
Judge Determinations
17  3,112,000 21  3,400,000 +4  +288,000
  ________________________________________________________
 
Total Budget Authority 44  7,731,000 48  8,096,000 +4  +365,000

 

 

GENERAL STATEMENT

 

            The Federal Mine Safety and Health Review Commission was established as an independent agency by Section 113(a) of the Federal Mine Safety and Health Act of 1977, as amended. It is not part of the Department of Labor nor its Mine Safety and Health Administration (MSHA).

 

            The Commission is charged with the responsibility of reviewing the enforcement activities of the Secretary of Labor, including hearing miners’ complaints challenging unlawful health or safety-related discrimination, and resolving compensation issues for miners idled due to mine closure orders issued by MSHA. The Commission’s ALJs hear and decide cases at the trial level initiated by the Secretary of Labor, mine operators, miners, and miners’ representatives.

 

            The 5-member Commission hears appeals from ALJ decisions. The Commission may review these decisions by granting a petition for discretionary review from one or more of the parties or by directing review on its own motion.

 

 

FEDERAL MINE SAFETY AND HEALTH REVIEW COMMISSION

 

Commission Review

 

 


       2006


        2007


       2008

Increase or

    Decrease

 

FTE

Amount

FTE

Amount

FTE

Amount

FTE

Amount

Commission Review, Total Budget Authority



24



4,619,340



27



4,619,000



27



4,696,000





+77,000

 

 

Introduction:


            The responsibility for the review of ALJ decisions is set forth in section 113(d)(1) of the Act. The Act states that an ALJ’s decision shall become final 40 days after its issuance, unless within that period any two Commissioners direct that the decision be reviewed.


            Most cases come before the Commission when two or more Commissioners vote to grant a petition for discretionary review filed by a party adversely affected or aggrieved by the ALJ’s decision. Petitioners may include miners, miners’ representatives, mine operators or the Secretary of Labor. The Commission is also charged with the responsibility of reviewing disputes arising over the accident response plans of underground coal operators pursuant to the Mine Improvement and New Emergency Response Act of (MINER Act) 2006, P.L. 109-236. Two or more Commissioners may also direct any case for review sua sponte (on the Commission’s own motion, without the parties filing a petition). Sua sponte review is limited to ALJ decisions that are contrary to law or Commission policy, or that present a novel question of policy. By law, a quorum of three Commissioners is required to consider and decide cases appealed from the Commission’s ALJs. Many of the Commission’s cases present issues of first impression under the Mine Act. That is, the cases raise issues that have not been resolved by prior decisions of the Commission or the courts or the cases involve the interpretation of safety and health standards and regulations newly promulgated by MSHA.


2008 Budget Request:


            The Commission is requesting a budget of $4,696,000 and 27 FTE for its appellate review activities in FY 2008. This is an increase of $77,000 over the amount estimated to be available for FY 2007. The request includes funding of a projected 3.1 pay increase in January 08, and other costs of Commission operations.




            A total of 86 new cases are anticipated for review by the Commission during FY 2008. Eighty-six dispositions are expected resulting in an end-of-year inventory of 12 undecided cases.

 

            The Commission’s FY 2008 budget includes the following performance objectives:


             Objective 1 — Issue opinions in a timely manner 

 

Performance Goals for FY 2008:

 

                      All Commission cases will be assigned when briefing is completed.

 

                      All Commission cases will be decided within 18 months of receipt.

 

                       The average age of substantive decisions will be maintained at 12 months or less.

 

             Objective 2 — Issue well-reasoned Commission opinions providing clear legal precedent and thoughtful analysis of issues

 

Quality Indicators for FY 2008:

 

                      Track Commission decisions that are appealed to the Courts of Appeals.


Fiscal Year 2007 Activity:


            The FY 2007 resource level for the Commission Review Activity is $4,619,000 and 27 FTE. The Commission began FY 2007 with an inventory of 12 undecided cases and anticipates receiving 86 new cases during the year. Eighty-six dispositions are anticipated during FY 2007, resulting in 12 undecided cases remaining at the end of the fiscal year.


            During the last quarter of BY 2006, the Commission issued a permanent rule implementing its responsibilities under the Mine Improvement and New Emergency Responder Act of 2006 (MINER Act). Interim procedural rules were issued on July 2006 at which time members of the interested public were invited to submit comments to assist the Commission in its deliberations regarding adoption of a permanent rule.




            The Commission’s Budget includes the following objectives for its appellate activity in FY 2007:


            Objective 1 — Issue opinions in a timely manner.

 

Performance Goals for FY 2007:

 

                      All Commission cases will be assigned when briefing is completed.

 

                      All Commission undecided cases currently in excess of 18 months of receipt will be decided.

 

                      All Commission remaining cases will be decided within 18 months of receipt.

 

                      Reduce the average age of substantive decisions to 12 months or less.


            Objective 2 – Commission’s rules


            Performance Goals for FY 2007:


                      Complete MINER Act rulemaking by March 31, 2007.

 

            Objective 3 — Issue well-reasoned Commission opinions providing clear legal precedent and thoughtful analysis of issues.

 

Quality Indicators for FY 2007:

 

                      Track Commission decisions that are appealed to the Courts of Appeals.


Fiscal Year 2006 Activity:


            The FY 2006 resource level for the Commission Review Activity was $4,619,340 with actual employment of 24 FTE. The Commission began FY 2005 with an inventory of 14 undecided cases and 81 new cases are anticipated for the year. Eighty-three cases are expected to be decided, resulting in a docket of 12 undecided cases at the end of the fiscal year.


            Of the 83 cases expected to be decided in FY 2006, 11 were substantive decisions, 69 were procedural orders, and 3 were denials of petitions for review. The average age of the 12 matters pending on the Commission’s docket as of September 30, 2006 was 3.4 months, and the average age of the 11 substantive decisions issued in FY 2006 is expected to be 15.5 months.


            During FY 2006, the Commission completed with the August 4, 2006 publication of a final rule, revising many of its procedural rules, the regulations implementing the Equal Access to Justice Act, and the Privacy Act. This rule making process began with the October 27, 2004, advance notice of public rulemaking and included participation from the mining and legal communities, and interested individuals for the general public.


            The Commission also issued on July 18, 2006, an interim procedural rule implementing the Mine Improvement and New Emergency Response Act of 2006 outlining its procedures in resolving disputes arising between operators and the Secretary of Labor over the contents of accident response plans for underground coal miners. Although the interim rule became effective upon publication, the Commission invited public comments in order to assist in its deliberations regarding the adoption of a permanent rule.


            The Commission developed the following performance objectives associated with its

FY 2006 budget. The objectives and accomplishments achieved during the year were:


             Objective 1 — Issue opinions in a timely manner

 

Performance Goals for FY 2006:

 

                      All Commission cases will be assigned when briefing is completed

 

Accomplishments: This goal was met. All cases that were briefed were assigned.

 

                      The Commission will have decided all cases that are 18 months or older.

 

Accomplishments: This goal was met. Through September 30, 2006, the 5 undecided cases that reached 18 months or older were decided.

 

                      The average age of substantive decisions will be maintained at 12 months or less.

 

Accomplishments: This goal was not met. As of September 30, 2006, the average age of the substantive dispositions is expected to be 15.5 months. The Commission could not meet this goal due to the majority of its substantive case dispositions being more than 12 months old.

 

            Objective 2 — Commission Rules


            Performance Goals for FY 2005

 

                      Complete the rulemaking BY September 30, 2006.

 

Accomplishments: This goal was met. The Commission published a final rule on August 4, 2006, the rule revising many of its procedural rules, the regulations implementing the Equal Access to Justice Act and the Privacy Act will take effect October 3, 2006 and will apply to cases initiated after that date as well as most pending proceedings.

 

            Objective 3 — Issue well-reasoned Commission opinions providing clear legal precedent and thoughtful analysis of issues.

 

Quality Indicators for FY 2006:

 

                      Track Commission decisions that are appealed to the Courts of Appeals.

 

Accomplishments: During FY 2006, 2 cases were appealed to the Courts of Appeals. The Court of Appeals decided 3 cases in FY 2005. The Court affirmed the Commission in 1 case and reversed the Commission in 2 cases. As of September 30, 2006, 2 cases remained pending.



Performance Measurement Matrix

 

Commission Review

 

 

 

FY 2001

FY 2002

FY 2003

FY 2004

FY 2005

 FY 2006


FY 2007

FY 2008

Actual

Actual

Actual

Actual

Actual

Goal

Actual

Goal

Goal

 

Objective: Issue opinions in a timely manner

 

 

 

Undecided cases over 24 months of age


1


0


1


1


0


0


0


0


             0


Undecided cases over 18 months of age (inclusive)


1


2


2


1


3


0


1


0


0


 

Undecided cases over 12 months of age (inclusive)


6


3


7


6


4


0


1


0


0

Cases briefed but unassigned


3


0


0


0


0


0


0


0


0

Substantive disposition age

16.4

12.2

12.5

18.6

13.1

12.0

15.5

12.0

12.0

▲ Current performance goals or quality indicators

 


 

FEDERAL MINE SAFETY AND HEALTH REVIEW COMMISSION

 

Administrative Law Judge Determinations

 

 


       2006


        2007


       2008

Increase or

       Decrease

 

FTE

Amount

FTE

Amount

FTE

Amount

FTE

Amount

Administrative

Law Judge Determinations



17



3,11,570



17



3,112,000



21



3,400,000



4



+288,000

 

Introduction:

 

            The Commission employs administrative law judges to hear and decide contested cases at the trial level, as initiated by the Secretary of Labor, mine operators, and miners or their representatives. The judges are also responsible for evaluating and approving or denying settlement agreements under the Mine Act.

 

            Administrative law judges travel to hearing sites located at or near the mine involved in order to afford mine operators, miners and their representatives the full opportunity to participate in the hearing process.

 

2008 Budget Request:

 

            The budget request contains $3,400,000 and 21 FTE for the Commission’s trial activities of its administrative law judges in FY 2008.

 

            The request includes an increase of $288,000 for 4 additional personnel, and funding of a projected 3.1 percent pay increase in January 08 and other costs of Commission operations.

 

            The additional staff increase includes four law clerks. The Commission believes that the request of law clerks is an efficient and economical approach for assisting the judges in deciding the increased caseload on its trial docket, the use of law clerks will provide the Commission with the added flexibility to make staffing adjustments consistent with case filings and undecided case inventories.

 

            A total of 3,000 new cases are anticipated for FY 2008, with an equal number of dispositions being projected for the year. The end of year inventory of undecided cases is estimated to be 3,756.

 

            The Commission believes that the number of new case filings will decrease in FY 2008 as more operators gain experience under the MINER Act and as precedence setting decisions of the Commission are implemented. However, a high level of new case filing experienced in FY 2006, and anticipated in FY 2007 and FY 2008 are expected to continue as a result of the Secretary of Labor’s increased enforcement and prosecutory efforts.


            The Commission’s FY 2008 budget includes the following performance objectives:

 

             Objective 1 — Issue opinions in a timely manner

 

Performance Goals for FY 2008:

 

                       Manage the case assignment process to assure that initial filings and response time frames are adhered to, resulting in case assignment averages that are less than the time frames in the Commission’s procedural rules.

 

                      Issue 90 percent of decisions within 90 days of receipt of post-hearing brief.

 

                      Issue 95 percent of settlement decisions within 30 days of receipt of settlement motions.

 


                      Decide 90 percent of cases within 270 days of assignment.

 

                      Decide all cases within an average of 195 days from receipt by the Commission.

 

            Objective 2 — Issue trial decisions based on sound factual and legal analysis

 

Quality Indicators for FY 2008:

 

                      Track appeal rate and affirmance rate of substantive ALJ decisions.

 

Fiscal Year 2007 Activity:

 

            The FY 2007 resource level for the Administrative Law Judge Determination Activity is expected to be $3,112,000 and 17 FTE.

 

            The Commission estimates to begin FY 2007 with an inventory of 2,756 undecided trial cases. A total of 3,400 new cases is anticipated for FY 2007, with 2,400 dispositions projected, leaving an end-of-year inventory of 3,756 cases.

 

            The Commission’s budget includes the following objectives for its trial activity in FY 2007:

 

            Objective 1 — Issue opinions in a timely manner

 

                        Performance Goals for FY 2007

 

                      Manage the case assignment process to assure that initial filings and response time frames are adhered to, resulting in case assignment averages that are less than the time frames in the Commission’s procedural rules.

 

                      Issue 90 percent of decisions within 90 days of receipt of the post-hearing brief.

 

                      Issue 95 percent of settlement decisions within 30 days of receipt of settlement motions.

 

                      Decide 90 percent of cases within 270 days of assignment.

 

                      Decide all cases within an average of 195 days from receipt by the Commission.

 


            Objective 2 — Issue trial decisions based on sound factual and legal analysis

 

Quality Indicators for FY 2007:

 

                      Track appeal rate and affirmance rate of substantive ALJ decisions.

 

Fiscal Year 2006 Activity:

 

            The FY 2006 funding level for the Administrative Law Judge Determinations Activity is $3,111,570 with actual employment of 17 FTE. As of October 1, 2005, the Commission’s ALJs had an inventory of 1,589 with 3, 406 new cases expected to be received during the year. Case dispositions for the year were 2, 239, resulting in an end-of-year inventory of 2,756 undecided cases. The number of new trial cases received are 40 percent higher than FY 2005 and were received at a rate not experienced in the past 10 years. As a result, the inventory of undecided cases as of September 30, 2006 represents a workload of 15 months.

 

            The Commission developed the following performance objectives associated with its FY 2006 budget. These objectives and accomplishments during the year were:

 

            Objective 1 — Issue opinions in a timely manner

 

Performance Goals for FY 2006:

 

                      Manage the case assignment process to assure that initial filings and response time frames are adhered to, resulting in case assignment averages that are less than the time frames in the Commission’s procedural rules.

 

Accomplishments: This goal is being met. The average time for a case to be assigned to an ALJ was 61 days. Penalty cases are being assigned in 78 days, less than the 85-day goal and the timeframe specified in the Commission’s rules. Review cases are being assigned in 24 days, well within the 30-day goal.

 

                      Issue 92 percent of decisions involving hearings within 90 days of receipt of post-hearing brief.

 

Accomplishments: This goal is not being met. Through August 31, of the 87 decisions issued after hearings, 88 percent were issued within 90 days of receipt of the post-hearing brief.

 

                      Issue 96 percent of settlement dispositions within 30 days of receipt of settlement motion.

 

Accomplishments: This goal is being met. Through August 31, of the 1,261 settlement motions that were approved during this year, 96 percent were approved within 30 days of receipt of the settlement motion.

 

 

                      Decide 95 percent of cases within 270 days of assignment.

 

Accomplishments: This goal is being met. Through August 31, of the 2,010 cases that were disposed, 98 percent were disposed within 270 days of assignment to an ALJ.

 

                      Decide all cases within an average of 135 days from receipt by the Commission.

 

Accomplishments: Data on this performance goal is currently not available.

 

            Objective 2 — Issue trial decisions based on sound factual and legal analysis

 

Quality Indicators for FY 2007:

 

                      Track appeal rate and affirmance rate of substantive ALJ decisions.

 

Accomplishments: Since the beginning of FY 1998, the Commission has calculated appeal and affirmance rates of its trial decisions. During FY 2005, Commission judges issued 87 decisions after hearings. Ten decisions were appealed to the Commission for an appeal rate of 11 percent. Of the nine substantive decisions issued by the Commission, one upheld the judge decision. Three cases were affirmed in part and reversed in part. Four cases were remanded to the judge for further proceedings and one case was dismissed.

 

 


Performance Measurement Matrix

Office of Administrative Law Judges

 

 

FY 2001

FY 2002

FY 2003

FY 2004

FY 2005

FY 2006

FY 2007

FY 2008

Actual

Actual

Actual

Actual

Actual

Goal

Actual

Goal

Goal

 

Objective 1: Issue opinions on a timely manner

 

 


Average time (days) for assignment of penalty cases


69


80


80


81


73


<85


78


<85


<85


Average time (days) for assignment of review cases


22


28


26


35


27


<30


24


<30


<30

 

Average time (days) for assignment of all cases


60


71


71


70


61


71


53


71


71


Percentage of decisions issued within 90 days of post-hearing brief



92%



61%



88%



85%



96%



92%



88%



90%



90%


Percentage of settlement approvals issued within 30 days of settlement motion



98%



96%



93%



86%



90%



96%



96%



95%



95%

 

Average time (days), case assignment to disposition


70


74


63


53


62


63


62


93


93


Average time (days), case receipt to disposition


131


145


134


123


121


145


NA


195


195


Cases decided within 270 days of assignment


97%


94%


98%


98%


97%


95%


98%


90%


90


 

Undecided cases over 270 days of age


48


25


83


1


18


0


5


0


0

 

Objective 2: Issue Trial Decisions on Sound Factual and Legal Analysis

 

Appeal rate

20%

17%

28%

16%

10%

N/A

11%

N/A

N/A

Affirmance rate

64%

55%

80%

43%

43%

N/A

25%

N/A

N/A

             Information on performance measurement is currently not available.

             ▲Current performance goals or quality indicators




Agency-wide Management Objectives

Management Objectives


            The Commission’s management goal is to manage its human resources, operations, facilities, and systems to ensure a continually improving, effective and efficient organization. The objectives of this goal, as they relate to the fiscal years covered by the FY 2008 budget submission are as follows:


Objective 1 — Ensure Organizational and Management Effectiveness

 

Performance Goals: 

 

          Provide efficient and effective administrative management and support services

 

The Commission obtains many of the services required as an independent agency from other Federal agencies. Payroll services are provided by the Department of Agriculture. Personnel and accounting services and website hosting are contracted through the Bureau of Public Debt (BPD). The Commission also uses the Department of Treasury developed Gov Trip as its E-Travel program. The franchise agency also perform similar services to other government organizations thus providing the Commission with economies that could not be independently achieved. A further advantage is that the Commission receives the benefit of system enhancements required by new laws and can more effectively participate in the President’s Management Agenda.

 

The Accountability of Tax Dollars Act requires that the Commission’s financial statements be audited annually. The Commission utilized audit specifications and negotiated audit contracts developed by BPD for all the organizations it services. The Commission received a “clean” audit report for FY 2005. Auditing of the Commission’s FY 06 records is currently in process.

 

          Evaluate Program Effectiveness

 

The Commission will continue to review its Strategic Plan to assure that its resources effectively address its statutory requirements and constituent needs.

 

Performance plans are evaluated annually to assure that goals and objectives fairly and accurately report accomplishments. Commission goals and objectives are included in individual performance standards upon which employees are evaluated. Interaction during evaluations provide an excellent method to further improve performance and gain greater efficiency.




Objective 2 — Provide Effective Information Technology Systems


Performance Goals:

 

          Maintain and enhance secure electronic information systems for case management, legal research, management operations support, and public access of data through the Internet.

 

The Commission has one staff member devoted full time to information technology and operation of its network.

 

The Commission continues to devote a major portion of its information technology efforts to network security with the constant threat from hackers, spammers, and viruses. Upgraded security software and patches were installed as they were released. Anti-virus scans are conducted daily on servers and individual workstations. Those security efforts will continue throughout fiscal years 2007 and 2008.

 

The Commission’s website, http://www.fmshrc.govrecorded 39,000 visits in July 2006. The website includes information about the Commission, its rules, guides and publications, strategic and performance plans, GILS records, a database of Commission and ALJ published decisions, transcripts of oral arguments, and links to related agencies and legal materials, including the Mine Act and MSHA. Constituents are promptly informed of ALJ and Commission’s decisions through prompt posting on the Commission’s website and can listen to audio recordings of its Commission meetings and oral arguments.

 

Objective 3 — Sustain a High Performing Workforce


Performance Goals:

 

          Recruit, train, and retain a diverse workforce of skilled, highly motivated employees to effectively and efficiently accomplish the Commission’s mission.

 

The Commission evaluated all vacant positions to assure that any added staff represents the best use of the Commission’s limited FTE resources and can be fully funded within available resources.


            During FY 2006, Congress passed the MINER Act which added an additional responsibility to the Commission of deciding disputes involving accident response plans for underground coal mines. Although no cases have been received to date, a substantial number of disputes are anticipated and must be acted upon immediately. In addition, the number of new case filings from MSHA enforcement actions have increased 40 percent and are expected to continue at a higher than normal level during the period covered by this budget request.


            For FY 2008, the Commission is requesting 4 additional FTE to cope with the burgeoning increase of undecided trial cases. Rather than substantially increase its corps of administrative law judges, the Commission believes that it can more effectively and economically increase the case dispositions through the employment of law clerks. This approach will also allow the Commission to effect staffing adjustments as the backlog of undecided cases is reduced.


            Currently, the Commission has three Commissioners to hear and decide cases at the appellate level. An additional Commissioner nominee is pending before the Senate and the fifth position is vacant. These vacancies and supporting staff and associated funding is being held in abeyance pending confirmation.

                                                                                    



FEDERAL MINE SAFETY AND HEALTH REVIEW COMMISSION


Selected Workload Data


 

2006
Actual
2007
Estimate
2008
Estimate
Commission Review Activities
 
Cases pending beginning of year 14 12 12
New cases received 81 86 86
Total case workload 95 98 98
Cases decided 83 86 86
Cases pending end of year 12 12 12

 

 

Administrative Law Judge Determinations

 

Cases pending beginning of year 1,589 2,756 3,756
New cases received 3,406 3,400 3,000
Total case workload 4,995 6,156 6,756
Cases decided 2,239 2,400 3,000
Cases pending end of year 2,756 3,756 3,756

 

 


FEDERAL MINE SAFETY AND HEALTH REVIEW COMMISSION

 

Commission Members

 

 

 

NAME                                                                  TERM EXPIRATION

 

Michael F. Duffy, Chairman Designee                 August 30, 2012

 

Arlene Holen, Designee                                        August 30, 2012

 

Mary Lu Jordan                                                    August 30, 2008

 

Michael G. Young                                                August 30, 2008

 


FEDERAL MINE SAFETY AND HEALTH REVIEW COMMISSION


Consultants